Building & Structural Inspections

Drainage & Waterproofing

Prior to backfilling the foundation.

Drainage and Waterproofing Examples

Final Building

After all sub-trade final inspections and other required departmental inspections are approved.

Final Building Examples

Fireplace Throat

After the smoke chamber is constructed and prior to completion of the chimney above the smoke chamber.

Fireplace Throat Examples

Floor Slab

After the vapor barrier and perimeter insulation (if required) are installed, and prior to the placement of concrete. If there are any pipes wires or vents that are being installed below the slab those sub-trade inspections are to be approved and backfilled prior to the slab inspection.

Floor Slab Example

Footing

After the trench is dug and reinforcement is installed, and prior to placement of the footing material.

Footing Examples

Foundation

After backfilling the crawl space and prior to placement of foundation sill plates.

Foundation Examples

Framing

After all structural members are installed and all sub-trade rough-ins are approved, and prior to concealment by insulation or drywall.

Framing Examples

Insulation

After the framing inspection is approved and prior to concealment.

Insulation Examples

Monolithic Pour

After the trench is dug and reinforcement, vapor barrier and perimeter insulation (if required) are installed, and prior to placement of concrete.

Monolithic Pour Examples

Poured Wall

After the reinforcement is installed and prior to placing concrete in the forms.

Poured Wall Example

Projection

At any point after the first course of block is laid and before the foundation is backfilled.

Projection Examples

Veneer

After the exterior sheathing, flashing, windows and doors are installed, and prior to the installation of exterior wall coverings.

Veneer Examples