Residential Plans Review Delivery Form (PDF) - Indicates whether you want the permit and forms mailed to you or held for three days at the Building Inspection office for you to pick up.
Construction plans (two or more copies) - We'll return one copy to you with the issued permit.
Construction Plan Requirements (two or more copies)
An overview floor plan with the room use clearly labeled and a brief description of the repairs to be made.
If sections of the structure must be rebuilt, you need framing plans. See Addition Projects (PDF).
If the whole structure has to be rebuilt down to the foundation, you need a sealed letter from an engineer verifying that the existing foundation is still structurally adequate.
If the whole structure has to be rebuilt, requirements will be the same as those for a new houseunless you have a sealed letter from an engineer verifying that the existing foundation is still structurally adequate.