Route 10 (Route 1 to I-95) Widening

Revenue Sharing funds (50% state funds and 50% county funds), federal Regional Surface Transportation Program (RSTP) funds, and local funds will be used to widen Route 10 to six lanes between Route 1 and I-95. A Design Public Hearing was held on December 15, 2015. The major design features were approved on November 6, 2016. Right-of-way acquisition is complete. Utility relocations are complete. Construction is expected to begin in October 2019 with completion anticipated in Fall 2020.

Traffic Impacts

See Traffic Engineering Analysis Report and Access Management Waiver (PDF).

Project Timeline

Fall 2019 to Fall 2020

Contact

Stan Newcomb
Phone: 804-748-1037
Email Stan Newcomb