Revenue sharing funds (50% state funds and 50% county funds) were used to improve the intersection of Otterdale Road and Old Hundred Road. A citizen information meeting was held on Tuesday, April 10, 2018. Right-of-way acquisition and utility relocations are complete. JR Caskey was awarded the construction contract. 

Project Timeline

Construction was substantially complete May 2021. Final construction activities were completed October 2021.