Harrowgate/Cougar Trail Bike and Ped Improvements

Plans were developed for a project to extend sidewalk on Cougar Trail and Harrowgate Road:

  • on the north side of Cougar Trail from Harrowgate Road to Carver Middle School, and
  • on the east side of Harrowgate Road from just north of South Street through North Street to connect with the existing sidewalk.

A citizen information meeting was held December 2019.

Traffic Impacts 

During construction, Harrowgate Road and Cougar Trail was open to traffic; however, lane closures during off-peak hours were necessary.

Project Timeline

Construction began May 2, 2022, and was completed in mid-November of 2022.