Subdivision Review Comments
All Subdivision Review Comments for Case # 16CP0051




For VDOT’s comments please contact Virginia Department of Transportation at (804) 674-2814 or send e-mail to Boris.Solomonov@VDOT.Virginia.gov

For Tentative Subdivision resubmittals:

1. Please note that submittal fees include the original submittal and two (2) additional reviews.

2. A letter of transmittal is required to accompany each submittal.

3. Please verify that Environmental Engineering, Fire, CDOT, VDOT, and Planning have reviewed the submittal before resubmitting. A resubmittal tendered, prior to receiving all the required departments’ review, will be counted as an additional submittal. Go to Case Selection Form or Go to Project List


 
CASE NO: 16CP0051 STATUS: PENDING APPROVAL
PROJECT NAME: CENTRALIA STATION - LAST INTERNET UPDATE: 11/20/17
SUBMITTAL TYPE: CONSTRUCTION PLAN
DEPARTMENT...REV..ROUTED..RESPONSE..STATUS....DATE...RVW..PHONE
ENVIR.ENGR.-: 02 04/18/16 05/09/16 COMPLETE 06/01/16 MCJ 751-2335
FIRE DEPT.--: 02 04/18/16 05/09/16 AMENDED* 05/31/16 JKL 748-1489
PLANNING----: 02 04/18/16 05/09/16 COMPLETE 05/09/16 CH 717-6042
TRANSPORT.--: 02 04/18/16 05/09/16 COMPLETE 04/29/16 SES 751-4912
UTIL.PLAN.--: 02 04/18/16 05/09/16 ******** ********
UTILITIES---: 02 04/18/16 05/09/16 AMENDED* 06/01/16 WBV 748-1343
UTIL.R.O.W.-: 02 04/18/16 05/09/16 ******** ********
VDOT--------: 02 04/18/16 05/09/16 ******** ********
REVIEW DEPARTMENT: UTILITIES
REVIEW/PHONE #: BILL VIER/748-1343
PLAN NAME: CENTRALIA STATION
PLAN NUMBER: 16CP0051
ORIGINAL PLAN DATE: 12/15/15
REVIEW DATE: 1/12/16
LATEST SUBMISSION DATE: 1/4/16
SUBMITTAL NUMBER: 1
STATUS: REVISIONS REQUIRED
TABLE REVIEW: NO
IN REGARD TO YOUR SUBMITTAL OF UTILITIES PLANS FOR THE
ABOVE REFERENCED PROJECT DATED DECEMBER 15, 2015,
WE MAKE THE FOLLOWING COMMENTS AND RECOMMENDATIONS:
1. A COPY OF VIRGINIA DEPARTMENT OF TRANSPORTATION'S
APPROVAL LETTER REGARDING PAVEMENT REPLACEMENT, METHOD
OF CROSSING, AND ALIGNMENT OF UTILITY WITH STATE RIGHT
OF WAY, AND A COPY OF ENVIRONMENTAL ENGINEERING'S
INITIAL REVIEW LETTER MUST BE SUBMITTED BEFORE REVISED
PLANS ARE SUBMITTED FOR RE-REVIEW.
2. PRIOR TO RELEASING TO THE CONSTRUCTION SECTION, A
COPY OF THE ENVIRONMENTAL ENGINEERING APPROVAL LETTER
AND/OR ALL OTHER APPLICABLE LOCAL STATE AND FEDERAL
AGENCIES' APPROVAL LETTERS MUST BE RECEIVED BY THIS
DEPARTMENT. IN ADDITION, ALL EASEMENTS NOT INCLUDED
WITH THE SUBDIVISION PLAT MUST BE DEDICATED WITH A
SEPARATE PLAT AND AGREEMENT TO THE COUNTY PRIOR TO
RELEASING THE PROJECT TO THE CONSTRUCTION SECTION.
3. SHOW THE COUNTY PROJECT NUMBER 08-0043 ON THE LOWER
RIGHT HAND CORNER OF EACH SHEET.
4. SHOW THE EXISTING WATER SERVICE AND METER BOX THAT
SERVED THE CLARKE HOUSE AT ITS ORIGINAL LOCATION AND
LABEL IT AS TO BE ABANDONED AS PER THE CURRENT COUNTY
SPECIFICATIONS, PART IV, SECTION 3, ITEM 3.06,
"ABANDONMENT OF WATER SERVICES."
5. CLEARLY SHOW ALL EXISTING AND PROPOSED VALVES,
TEES, CROSSES, ETC., USING THE CORRECT LINE TYPE AND
LABELING EACH VALVE THAT IS TO BE USED FOR CUT OFF
PURPOSES DURING EACH WATERLINE TIE IN AS SUCH.
6. TAKE ALL STEPS NECESSARY TO PROVIDE AT LEAST 1 LF
OF UNDISTURBED EARTH BETWEEN THE LIMITS OF THE TRENCH
DUG TO INSTALL THE SANITARY SEWER AND THE EDGE OF THE
CURB AND GUTTER AT ALL LOCATIONS. IN THE EVENT A
REALIGNMENT OF THE SEWER TO ACHIEVE THIS IS NOT
FEASIBLE, SPECIFY THAT THE SEWER TRENCH BE BACKFILLED TO
THE TOP WITH THOROUGHLY COMPACTED 21 A STONE. THIS
REQUIREMENT SHALL APPLY FOR 5 LF PRIOR TO, AS WELL AS
AFTER SAID EXPOSURE. IN ADDITION CLEARLY NOTE THIS AS
SUCH AT EACH APPLICABLE LOCATION IN THE PROFILE VIEWS.
7. COMPLETE ITEM NUMBER 4 UNDER THE "STANDARD SEWER
AND WATER NOTES" WITH ELEVATION 122' AND NOTE THIS
CONDITION ON EACH APPLICABLE LOT IN THE PLAN VIEWS.
8. PROVIDE 10 LF MINIMUM HORIZONTAL SEPARATIONS
BETWEEN ALL FLUSHING HYDRANTS AND ALL WATER
SERVICES/METER BOXES.
9. SPECIFY EACH WATER SERVICE GREATER THAN OR EQUAL TO
60 LF AS 1" IN DIAMETER AND NOTE THIS CONDITION ON EACH
APPLICABLE LOT IN THE PLAN VIEWS.
10. LABEL THE 8" WATERLINE IN CALLISTO LANE AND PROVIDE
AN 8" PLUG AND A 2" FLUSHING HYDRANT AT ITS TERMINUS
POINT. ALSO INCLUDE IT IN THE PROFILE VIEWS ON THIS
SHEET.
11. PROVIDE PERMANENT WATERLINE EASEMENTS AS NECESSARY
TO FULLY ENCUMBER ALL WATERLINE NOT LOCATED IN A RIGHT-
OF-WAY.
12. PROCEED AS FOLLOWS REGARDING THE PROPOSED WATER
LINE IN THE AREA OF STATION 39 + 90 ±, CENTRALIA STATION
ROAD:
A. DEFLECT THE WATER LINE AROUND THE DRAINAGE
STRUCTURES.
B. PROVIDE A PERMANENT WATER LINE EASEMENT
(SPECIFICALLY LABELED AS SUCH) TO FULLY ENCUMBER THIS
DEFLECTED WATER LINE.
C. SHOW AND "CALL OUT" EACH WATER LINE BEND IN
THE PLAN AND PROFILE VIEWS.
D. THIS REVISED ALIGNMENT WILL REQUIRE AN
ENGINEERED, DESIGNED, JOINT RESTRAINT SYSTEM. PROVIDE A
COPY OF ALL CALCULATIONS PERFORMED TO THE LENGTHS OF
PIPE REQUIRING JOINT RESTRAINT AND CLEARLY SHOW THESE
DISTANCES IN THE PROFILE VIEWS.
E. STANDARD DETAIL DRAWING NUMBER WAT-12 DIRECTLY
ADDRESSES THESE SITUATIONS. PROCEED EXACTLY AS PER THAT
DETAIL, AND PROVIDE A COPY OF IT IN THE PLANS,
REFERENCING ITS LOCATION.
13. LABEL CENTRALIA STATION COVE ON SHEET C-14 AND
REVISE THE LOT NUMBERS FOR IT ON ALL SHEETS.
14. LABEL THE PROPOSED TIE IN MANHOLE WITH ITS AS BUILT
NUMBER (I.E. 15-19) AT ALL LOCATIONS IT APPEARS IN THE
PLAN AND PROFILE VIEWS.
15. PROVIDE A NOTE STATING EXISTING MANHOLE NUMBER 15-
19 IS TO BE CORE DRILLED AND A KOR-N-SEAL GASKET IS TO
BE INSTALLED AT ALL APPLICABLE LOCATIONS IN THE PLAN AND
PROFILE VIEWS.
16. LABEL AMALTHEA LANE ON SHEET C-16.
17. FIELD VERIFY THE TOP AND ALL INVERT ELEVATIONS OF
THE PROPOSED TIE-IN MANHOLE, REFLECTING THE FIELD DATA
ON THE PLANS.
18. SPECIFY 1 VF OF ADDITIONAL STONE ABOVE THE PIPE AT
ALL LOCATIONS WITH GREATER THAN OR EQUAL TO 14 VF OF
COVER OVER A PVC SEWER LINE, CLEARLY NOTING AS SUCH AT
ALL APPLICABLE LOCATIONS IN THE PROFILE VIEWS.
19. PROVIDE "COMPLETE" (I.E. MANHOLE TO MANHOLE,
WITHOUT MATCH LINES) PROFILE VIEWS OF ALL SANITARY SEWER
PROPOSED WITH THIS PROJECT.
20. A "STANDARD DROP CONNECTION" WILL BE REQUIRED AT
MANHOLE NUMBER 8. REVISE THE PLANS AS NECESSARY.
21. SHOW ALL STORM/SANITARY SEWER CROSSINGS IN THE
PROFILE VIEWS AND PROVIDE THE EXACT VERTICAL SEPARATION
DISTANCE AT EACH.
22. THERE ARE VERTICAL CONFLICTS (I.E. LESS THAN 1.5 VF
CLEARANCE) AT EACH OF THE FOLLOWING LOCATIONS:
A. LOT # 2 - SEWER CONNECTION AND STORM PIPE.
B. LOT # 4 - SEWER CONNECTION AND STORM PIPE.
C. LOT # 5 - SEWER CONNECTION AND STORM PIPE.
D. LOT # 24 - SEWER CONNECTION AND WATER LINE.
E. LOT # 54 - SEWER CONNECTION AND WATER LINE.
F. LOT # 36 - SEWER CONNECTION AND WATER LINE.
23. THE MINIMUM SLOPE ON AN 8" SEWER IS 0.40%. REVISE
AS NECESSARY TO SATISFY THIS SPECIFICATION AT ALL
LOCATIONS (I.E. MANHOLE 15-16 AND 17-19).
24. PROVIDE 0.10 VF OF DROP ACROSS EACH MANHOLE (I.E.
MANHOLE # 39).
25. PROVIDE THE DIAMETER, MATERIAL, DISTANCE AND SLOPE
FOR EACH PROPOSED RUN OF SANITARY SEWER (I.E. MANHOLE
NUMBERS 40-39 AND 38-37-36).
26. REVISE THE SLOPE OF THE SANITARY SEWER BETWEEN
MANHOLE NUMBERS 23 - 24 0.52%.
27. REVISE AS NECESSARY TO PROVIDE A SEWER CONNECTION
(WITH THE MINIMUM REQUIRED VERTICAL SEPARATION DISTANCE
BETWEEN THE CONNECTION AND ANY STORM SEWER IT CROSSES)
FOR EACH PROPERTY NOT LOCATED IN THIS PROJECT BUT
FRONTING CENTRALIA STATION ROAD.
28. DUE TO THE NUMBER AND COMPLEXITY OF THE COMMENTS
BEING MADE ON THIS PROJECT, THIS OFFICE RESERVES THE
RIGHT TO MAKE ADDITIONAL COMMENTS, NOT NECESSARILY
CONTAINED HEREIN, ON FUTURE SUBMITTALS OF THIS PROJECT.
29. THOROUGHLY EXAMINE ALL SHEETS TO CORRECT ALL
EXTRANEOUS MARKINGS, OVERLAPPING TEXT, ILLEGIBLE TEXT
AND DRAWING FEATURES, ETC. IN ORDER TO FACILITATE A
CLEAN DRAWING WITH ALL TEXT AND DRAWING FEATURES
COMPLETELY LEGIBLE AND ABUNDANTLY VISIBLE.
30. REVISE THE "MATERIALS LIST" AS NECESSARY.
PLEASE MAKE ALL OF THE SUGGESTED CHANGES AND SUBMIT
ONE (1) SET OF REVISED PLANS.
THE OWNER MUST ENTER INTO A COUNTY CONTRACT PRIOR TO THE
START OF CONSTRUCTION. PLEASE SEND ME A COPY OF THE
"ACCEPTED" BID PROPOSAL BETWEEN THE DEVELOPER AND THE
CONTRACTOR SO WE MAY PREPARE THE COUNTY CONTRACT. THE
BID PROPOSAL MUST BE BASED ON THE LATEST REVISED
UTILITIES PLANS REFLECTING THE REVIEWER'S STAMP, AND ALL
WORK MUST BE PERFORMED BY AN ACCEPTABLE UTILITIES
CONTRACTOR. IF PLANS ARE REVISED AFTER CONTRACT
PREPARATION DUE TO A CHANGE BECAUSE OF VIRGINIA
DEPARTMENT OF TRANSPORTATION'S AND/OR ENVIRONMENTAL
ENGINEERING DEPARTMENT'S APPROVAL OF THE ROAD, DRAINAGE,
AND EROSION CONTROL DESIGN OR BECAUSE OF STATE AGENCIES'
REVIEW AND APPROVAL OF THE UTILITIES DESIGN, A REVISED
BID PROPOSAL MAY BE NECESSARY TO ACCURATELY REFLECT THE
LATEST UTILITIES DESIGN AND A NEW CONTRACT PREPARATION
MAY BE NECESSARY AND EXECUTED PRIOR TO THE START OF
CONSTRUCTION.
IF YOU HAVE ANY QUESTIONS, DO NOT HESITATE TO CONTACT ME
AT 748-1343.
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
REVIEW DEPARTMENT: UTILITIES
REVIEW/PHONE #: BILL VIER/748-1343
PLAN NAME: CENTRALIA STATION
PLAN NUMBER: 16CP0051
ORIGINAL PLAN DATE: 12/15/15
REVIEW DATE: 3/9/16
LATEST SUBMISSION DATE: 2/29/16
SUBMITTAL NUMBER: 2
STATUS: REVISIONS REQUIRED
TABLE REVIEW: NO
IN REGARD TO YOUR SUBMITTAL OF UTILITIES PLANS FOR THE
ABOVE REFERENCED PROJECT DATED DECEMBER 15, 2015, WITH
THE LATEST REVISION DATED FEBRUARY 26, 2016, WE MAKE THE
FOLLOWING COMMENTS AND RECOMMENDATIONS:
1. A COPY OF VIRGINIA DEPARTMENT OF TRANSPORTATION'S
APPROVAL LETTER REGARDING PAVEMENT REPLACEMENT, METHOD
OF CROSSING, AND ALIGNMENT OF UTILITY WITH STATE RIGHT
OF WAY, AND A COPY OF ENVIRONMENTAL ENGINEERING'S
INITIAL REVIEW LETTER MUST BE SUBMITTED BEFORE REVISED
PLANS ARE SUBMITTED FOR RE-REVIEW.
2. PRIOR TO RELEASING TO THE CONSTRUCTION SECTION, A
COPY OF THE ENVIRONMENTAL ENGINEERING APPROVAL LETTER
AND/OR ALL OTHER APPLICABLE LOCAL STATE AND FEDERAL
AGENCIES' APPROVAL LETTERS MUST BE RECEIVED BY THIS
DEPARTMENT. IN ADDITION, ALL EASEMENTS NOT INCLUDED
WITH THE SUBDIVISION PLAT MUST BE DEDICATED WITH A
SEPARATE PLAT AND AGREEMENT TO THE COUNTY PRIOR TO
RELEASING THE PROJECT TO THE CONSTRUCTION SECTION.
3. REVISE THE WATER SERVICE AND SEWER CONNECTION FOR
LOT NUMBER 5 AS PER OUR TELEPHONE CONVERSATION.
4. PROVIDE A DETAILED PROFILE VIEW OF THE 8" STUB
WATERLINE AT STATION 16 + 65 ± CENTRALIA STATION ROAD
AND THE STORM SEWER CROSSING.
5. PROVIDE SEWER CONNECTIONS FOR EACH OF THE CLEMENTS
AND HOBBS PROPERTIES.
6. LABEL THE 8" WATERLINE IN STUB ROAD AND THE ROAD
NAME AT ALL LOCATIONS IT APPEARS ON THE PLANS.
7. REVISE THE WATER SERVICE FOR LOT NUMBER 73, AS WELL
AS THE WATER SERVICE AND SEWER CONNECTION FOR LOT NUMBER
12 AS PER OUR TELEPHONE CONVERSATION.
8. UTILIZE MANHOLES TO THE GREATEST EXTENT POSSIBLE TO
EXTEND SEWER CONNECTIONS FROM THEM.
9. SHOW EACH STORM/SANITARY SEWER CROSSING IN THE
PROFILE VIEWS AND PROVIDE THE EXACT VERTICAL SEPARATION
DISTANCE AT EACH LOCATION.
10. CHECK ANY SEWER CONNECTION CROSSINGS WITH STORM
PIPES AND WATERLINES FOR THE REQUIRED VERTICAL
SEPARATION, REVISING AS NECESSARY. (IN PARTICULAR, THE
TUNSTALL PROPERTY AND LOT NUMBERS 6, 30, 31 AND 38.)
11. SPECIFY THE TYPE OF DROP CONNECTION (I.E. STANDARD
OR INTERVAL) TO BE UTILIZED AND REFERENCE THE LOCATION
OF THE APPLICABLE DETAIL ON THE PLANS, REVISING THE
PLANS AS NECESSARY.
12. PROVIDE REVISED JOINT RESTRAINT CALCULATIONS
CONSIDERING THE BENDS AS VERTICAL WITH A SAFETY FACTOR
OF 1.5 TO 1 AND A TYPE 3 TRENCH. CLEARLY SHOW THE
DISTANCES PRIOR TO THE FIRST BEND AND FOLLOWING THE LAST
BEND WHERE JOINT RESTRAINT IS REQUIRED.
13. PROVIDE PIPE DIAMETER, MATERIAL, DISTANCE AND SCOPE
FOR THE RUN OF SANITARY SEWER FROM MANHOLE NUMBERS 40 TO
39.
14. PROVIDE "COMPLETE" PROFILE VIEWS (I.E. MANHOLE TO
MANHOLE, WITHOUT MATCH LINES)FOR EACH RUN OF SANITARY
SEWER PROPOSED WITH THIS PROJECT.
15. PROVIDE THE NOTE STATING THAT THE TIE IN MANHOLE IS
TO BE CORE DRILLED AND A KOR-N-SEAL GASKET IS TO BE
INSTALLED AT ALL LOCATIONS IT APPEARS IN THE PROFILE
VIEWS.
16. PROVIDE CONCRETE ENCASEMENT FOR THAT PORTION OF THE
SANITARY SEWER BETWEEN MANHOLE NUMBERS 10 AND 9 WHERE
THE COVER IS LESS THAN OR EQUAL TO 3.5 VF. PROVIDE A
COPY OF THE APPLICABLE DETAIL ON THE PLANS, REFERENCING
ITS LOCATION.
17. AN "ENCROACHMENT AGREEMENT" WITH DOMINION VIRGINIA
POWER WILL BE REQUIRED. CONTACT MR. JOHN W. HARMON,
REAL PROPERTY MANAGER, CHESTERFIELD COUNTY, TO INITIATE
THIS PROCESS.
18. SPECIFY EACH WATER SERVICE GREATER THAN OR EQUAL TO
60 LF AS 1" IN DIAMETER. CLEARLY NOTE THIS CONDITION ON
EACH APPLICABLE LOT IN THE PLAN VIEWS.
19. DUE TO THE NUMBER AND COMPLEXITY OF THE COMMENTS
BEING MADE ON THIS PROJECT, THIS OFFICE RESERVES THE
RIGHT TO MAKE ADDITIONAL COMMENTS, NOT NECESSARILY
CONTAINED HEREIN, ON FUTURE SUBMITTALS OF THIS PROJECT.
20. THOROUGHLY EXAMINE ALL SHEETS TO CORRECT ALL
EXTRANEOUS MARKINGS, OVERLAPPING TEXT, ILLEGIBLE TEXT
AND DRAWING FEATURES, ETC. IN ORDER TO FACILITATE A
CLEAN DRAWING WITH ALL TEXT AND DRAWING FEATURES
COMPLETELY LEGIBLE AND ABUNDANTLY VISIBLE.
21. REVISE THE "MATERIALS LIST" AS NECESSARY.
PLEASE MAKE ALL OF THE SUGGESTED CHANGES PREVIOUSLY
MENTIONED, AND SUBMIT ONE(1) SET OF REVISED PLANS.
THE OWNER MUST ENTER INTO A COUNTY CONTRACT PRIOR TO THE
START OF CONSTRUCTION. PLEASE SEND ME A COPY OF THE
"ACCEPTED" BID PROPOSAL BETWEEN THE DEVELOPER AND THE
CONTRACTOR SO WE MAY PREPARE THE COUNTY CONTRACT. THE
BID PROPOSAL MUST BE BASED ON THE LATEST REVISED
UTILITIES PLANS REFLECTING THE REVIEWER'S STAMP, AND ALL
WORK MUST BE PERFORMED BY AN ACCEPTABLE UTILITIES
CONTRACTOR. IF PLANS ARE REVISED AFTER CONTRACT
PREPARATION DUE TO A CHANGE BECAUSE OF VIRGINIA
DEPARTMENT OF TRANSPORTATION'S AND/OR ENVIRONMENTAL
ENGINEERING DEPARTMENT'S APPROVAL OF THE ROAD, DRAINAGE,
AND EROSION CONTROL DESIGN OR BECAUSE OF STATE AGENCIES'
REVIEW AND APPROVAL OF THE UTILITIES DESIGN, A REVISED
BID PROPOSAL MAY BE NECESSARY TO ACCURATELY REFLECT THE
LATEST UTILITIES DESIGN AND A NEW CONTRACT PREPARATION
MAY BE NECESSARY AND EXECUTED PRIOR TO THE START OF
CONSTRUCTION.
IF YOU HAVE ANY QUESTIONS, DO NOT HESITATE TO CONTACT ME
AT 748-1343.
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
REVIEW DEPARTMENT: UTILITIES
REVIEW/PHONE #: BILL VIER/748-1343
PLAN NAME: CENTRALIA STATION, SECTION 1
PLAN NUMBER: 16CP0051
ORIGINAL PLAN DATE: 12/15/15
REVIEW DATE: 5/2/16
LATEST SUBMISSION DATE: 4/20/16
SUBMITTAL NUMBER: 3
STATUS: REVISIONS REQUIRED
TABLE REVIEW: NO
IN REGARD TO YOUR SUBMITTAL OF UTILITIES PLANS FOR THE
ABOVE REFERENCED PROJECT DATED DECEMBER 15, 2015, WITH
THE LATEST REVISION DATED APRIL 13, 2016, WE MAKE THE
FOLLOWING COMMENTS AND RECOMMENDATIONS:
1. A COPY OF VIRGINIA DEPARTMENT OF TRANSPORTATION'S
APPROVAL LETTER REGARDING PAVEMENT REPLACEMENT, METHOD
OF CROSSING, AND ALIGNMENT OF UTILITY WITH STATE RIGHT
OF WAY, AND A COPY OF ENVIRONMENTAL ENGINEERING'S
INITIAL REVIEW LETTER MUST BE SUBMITTED BEFORE REVISED
PLANS ARE SUBMITTED FOR RE-REVIEW.
2. PRIOR TO RELEASING TO THE CONSTRUCTION SECTION, A
COPY OF THE ENVIRONMENTAL ENGINEERING APPROVAL LETTER
AND/OR ALL OTHER APPLICABLE LOCAL STATE AND FEDERAL
AGENCIES' APPROVAL LETTERS MUST BE RECEIVED BY THIS
DEPARTMENT. IN ADDITION, ALL EASEMENTS NOT INCLUDED
WITH THE SUBDIVISION PLAT MUST BE DEDICATED WITH A
SEPARATE PLAT AND AGREEMENT TO THE COUNTY PRIOR TO
RELEASING THE PROJECT TO THE CONSTRUCTION SECTION.
3. PROVIDE A DETAILED PROFILE VIEW OF THE PROPOSED
WATERLINE FROM THE TIE IN POINT TO THE POINT IT ENTERS
CENTRALIA STATION ROAD. IF THE WATERLINE CROSSING OF
CENTRALIA ROAD IS TO BE ACCOMPLISHED BY BORING, PROVIDE
A COPY OF DETAIL DRAWING NUMBER CAS-4 ON THE PLANS,
REFERENCING ITS LOCATION AND PROCEEDING EXACTLY AS SHOWN
THEREIN.
4. THAT PORTION OF THE WATERLINE IN CENTRALIA STATION
ROAD FROM STATION 10 + 90 ± TO THE TEE CAN BE SPECIFIED
AS 6" IN DIAMETER. REVISE AS NECESSARY TO REFLECT AS
SUCH, INCLUDING ALL VALVES, FITTINGS, ETC.
5. RELOCATE THE WATER SERVICE FOR LOT NUMBER 33 AS PER
OUR TELEPHONE CONVERSATION.
6. SPECIFY ALL DROP CONNECTIONS IN A CONSISTENT
FASHION, REFERENCING THE LOCATION OF THE APPLICABLE
DETAIL ON THE PLANS AND REMOVE ALL NOTES AND PLAN
FEATURES THAT NO LONGER APPLY.
7. IT APPEARS A DROP CONNECTION WILL BE REQUIRED AT
MANHOLE NUMBER 45.
8. AN "ENCROACHMENT AGREEMENT" WITH DOMINION VIRGINIA
POWER WILL BE REQUIRED. CONTACT MR. JOHN W. HARMON,
REAL PROPERTY MANAGER, CHESTERFIELD COUNTY, TO INITIATE
THIS PROCESS.
9. PROVIDE A CONSPICUOUSLY DISPLAYED NOTE STATING THAT
FOR EACH LOT "FRONTING" ON A SIDEWALK, THE "FRONT" SIDE
OF THE METER BOX IS TO BE LOCATED 3 LF FROM THE "HOUSE"
SIDE OF THE SIDEWALK.
10. THE MINIMUM RADIUS FOR AN 8" WATERLINE IS 326.3'.
THOROUGHLY EXAMINE THE WATERLINE ALIGNMENT GIVEN THIS
SPECIFICATION AND PROVIDE BENDS AS REQUIRED.
11. THOROUGHLY EXAMINE ALL SHEETS TO CORRECT ALL
EXTRANEOUS MARKINGS, OVERLAPPING TEXT, ILLEGIBLE TEXT
AND DRAWING FEATURES, ETC. IN ORDER TO FACILITATE A
CLEAN DRAWING WITH ALL TEXT AND DRAWING FEATURES
COMPLETELY LEGIBLE AND ABUNDANTLY VISIBLE.
12. REVISE THE "MATERIALS LIST" AS NECESSARY.
PLEASE MAKE ALL OF THE SUGGESTED CHANGES AND SUBMIT
ONE(1) SET OF REVISED PLANS.
THE OWNER MUST ENTER INTO A COUNTY CONTRACT PRIOR TO THE
START OF CONSTRUCTION. PLEASE SEND ME A COPY OF THE
"ACCEPTED" BID PROPOSAL BETWEEN THE DEVELOPER AND THE
CONTRACTOR SO WE MAY PREPARE THE COUNTY CONTRACT. THE
BID PROPOSAL MUST BE BASED ON THE LATEST REVISED
UTILITIES PLANS REFLECTING THE REVIEWER'S STAMP, AND ALL
WORK MUST BE PERFORMED BY AN ACCEPTABLE UTILITIES
CONTRACTOR. IF PLANS ARE REVISED AFTER CONTRACT
PREPARATION DUE TO A CHANGE BECAUSE OF VIRGINIA
DEPARTMENT OF TRANSPORTATION'S AND/OR ENVIRONMENTAL
ENGINEERING DEPARTMENT'S APPROVAL OF THE ROAD, DRAINAGE,
AND EROSION CONTROL DESIGN OR BECAUSE OF STATE AGENCIES'
REVIEW AND APPROVAL OF THE UTILITIES DESIGN, A REVISED
BID PROPOSAL MAY BE NECESSARY TO ACCURATELY REFLECT THE
LATEST UTILITIES DESIGN AND A NEW CONTRACT PREPARATION
MAY BE NECESSARY AND EXECUTED PRIOR TO THE START OF
CONSTRUCTION.
IF YOU HAVE ANY QUESTIONS, DO NOT HESITATE TO CONTACT ME
AT 748-1343.
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
REVIEW DEPARTMENT: UTILITIES
REVIEW/PHONE #: BILL VIER/748-1343
PLAN NAME: CENTRALIA STATION, SECTION 1
PLAN NUMBER: 16CP0051
ORIGINAL PLAN DATE: 12/15/15
REVIEW DATE: 6/1/16
LATEST SUBMISSION DATE: 5/31/16
SUBMITTAL NUMBER: 4
STATUS: APPROVED
TABLE REVIEW: NO
IN REGARD TO YOUR RECENT SUBMITTAL OF THE REVISED
UTILITIES PLANS ON THE ABOVE REFERENCED PROJECT DATED
DECEMBER 15, 2015, WITH THE LAST REVISION DATED MAY 26,
2016, THIS IS TO INFORM YOU THAT THE PLANS HAVE BEEN
REVIEWED BY THE UTILITIES DEPARTMENT WITH NO EXCEPTIONS
TAKEN. THIS REVIEW IS EFFECTIVE UNTIL JUNE 1, 2021.
PLEASE FORWARD TWO(2) ADDITIONAL SETS OF PLANS ONCE
ALL APPROVALS HAVE BEEN OBTAINED. IF, AFTER ALL OTHER
REVIEWS/APPROVALS HAVE BEEN MADE, THE UTILITY PLANS
REFLECT A LATER REVISION DATE THAN THE LAST REVISION NOTED
ABOVE, PLEASE SUBMIT ONE (1) NEW SET OF UTILITY PLANS FOR
FURTHER REVIEW AND APPROVAL.
YOUR COOPERATION IS GREATLY APPRECIATED. PLEASE CALL ME
AT 748-1343 IF YOU HAVE ANY FURTHER QUESTIONS REGARDING
THIS MATTER.
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
REVIEW DEPARTMENT: CHESTERFIELD TRANSPORTATION DEPARTMENT
REVIEWER/PHONE#: STEVEN E. SIMONSON, P.E. (804)748-1037
NAME OF PLAN: CENTRALIA STATION
CASE NUMBER: 16CP0051
LATEST PLAN DATE: 12/15/15
DEPT. REC'D. DATE: 01/04/2016
SUBMITTAL NUMBER: ONE
REVIEW DATE: 01/21/16
RECOMMENDATION: APPROVED
TABLE REVIEW: YES
REVIEW DEPARTMENT: CHESTERFIELD TRANSPORTATION DEPARTMENT
REVIEWER/PHONE#: STEVEN E. SIMONSON, P.E. (804)748-1037
NAME OF PLAN: CENTRALIA STATION
CASE NUMBER: 16CP0051
LATEST PLAN DATE: 02/26/2015
DEPT. REC'D. DATE: 03/01/2016
SUBMITTAL NUMBER: TWO
REVIEW DATE: 03/14/16
RECOMMENDATION: APPROVED
TABLE REVIEW: YES
NOTE: SHEET 3-22 IS MISLABELED AS C-21.
REVIEW DEPARTMENT: CHESTERFIELD TRANSPORTATION DEPARTMENT
REVIEWER/PHONE#: STEVEN E. SIMONSON, P.E. (804)748-1037
NAME OF PLAN: CENTRALIA STATION
CASE NUMBER: 16CP0051
LATEST PLAN DATE: 04/13/2016
DEPT. REC'D. DATE: 04/22/2016
SUBMITTAL NUMBER: THREE
REVIEW DATE: 04/29/2016
RECOMMENDATION: APPROVED
TABLE REVIEW: YES
************************************************************
REVIEWER / PHONE #--------CHRIS HALE / (804) 717-6042
NAME OF PLAN--------------CENTRALIA STATION
SITE PLAN NUMBER----------16CP0051
ORIGINAL PLAN DATE--------12/15/15
LATEST PLAN DATE----------12/15/15
DEPT. REC'D. DATE---------12/15/15
ACCEPTED FOR REVIEW-------12/30/15
SUBMITTAL NUMBER----------ONE
REVIEW DATE---------------02/02/16
RECOMMENDATION------------REVISION REQUIRED
TABLE REVIEW--------------NO
01. PUT A REVISION DATE ON THE RESUBMITTED PLANS. RESUBMIT
10 FULL SETS TO THE PLANNING DEPARTMENT FOR YOUR NEXT
REVIEW. PROVIDE A COMPLETE RESPONSE TO COMMENTS FOR ALL
DEPARTMENTS TO THE PLANNING DEPARTMENT. BELOW EACH COMMENT
DESCRIBE HOW YOU HAVE ADDRESSED EACH REVIEW COMMENT. BE
SURE TO INDICATE WHICH SHEETS SHOW THE REQUIRED CHANGES.
PROVIDE A TRANSMITTAL LETTER TO DESCRIBE ANY CHANGES TO THE
PLANS NOT CAUSED BY THE STAFF REVIEW COMMENTS.
02. THE FIRST SUBMITTAL SHALL INCLUDE A PLAN DATE (MONTH,
DAY & YEAR), AND EACH REVISED SET OF PLANS SHALL SHOW A
REVISION DATE.
03. PUT THE CHESTERFIELD COUNTY CONSTRUCTION PLAN NUMBER
16CP0051 IN THE LOWER RIGHT CORNER OF EACH SHEET.
04. SHOW FRONT BUILDING LINES ON LOTS 50, 51, 66, 67, 68,
AND 69. LINES ARE TO BE CONTIGUOUS.
05. SHOW ALL BUILDING ENVELOPES AS SHOWN ON THE APPROVED
PRELIMINARY 08TS0264.
06. SHOW THE SMALL SECTION OF 50 FOOT BUFFER ON THE OPEN
SPACE PORTION ACROSS CENTRALIA STATION ROAD.
************************************************************
REVIEWER / PHONE #--------CHRIS HALE / (804) 717-6042
NAME OF PLAN--------------CENTRALIA STATION
SITE PLAN NUMBER----------16CP0051
ORIGINAL PLAN DATE--------12/15/15
LATEST PLAN DATE----------02/26/16
DEPT. REC'D. DATE---------02/26/16
ACCEPTED FOR REVIEW-------02/26/16
SUBMITTAL NUMBER----------TWO
REVIEW DATE---------------03/30/16
RECOMMENDATION------------REVISION REQUIRED
TABLE REVIEW--------------YES
01. PUT A REVISION DATE ON THE RESUBMITTED PLANS. RESUBMIT
10 FULL SETS TO THE PLANNING DEPARTMENT FOR YOUR NEXT
REVIEW. PROVIDE A COMPLETE RESPONSE TO COMMENTS FOR ALL
DEPARTMENTS TO THE PLANNING DEPARTMENT. BELOW EACH COMMENT
DESCRIBE HOW YOU HAVE ADDRESSED EACH REVIEW COMMENT. BE
SURE TO INDICATE WHICH SHEETS SHOW THE REQUIRED CHANGES.
PROVIDE A TRANSMITTAL LETTER TO DESCRIBE ANY CHANGES TO THE
PLANS NOT CAUSED BY THE STAFF REVIEW COMMENTS.
02. THE COUNTY PRESERVATION COMMITTEE AND PLANNING
COMMISSION RECOMMENDED APPROVAL TO REMOVE THE HISTORIC
DESIGNATION FROM THE CLARKE HOUSE PARCEL. THE DESIGNATION
IS TO REMAIN ON THE HOUSE AND A 20 FOOT ZONE SURROUNDING
THE STRUCTURE. NO DISTURBANCE IS TO OCCUR WITHIN THE 20
FOOT ZONE. INDICATE THE 20 FOOT HISTORIC PRESERVATION ZONE
AROUND THE HOUSE.
************************************************************
REVIEWER / PHONE #--------CHRIS HALE / (804) 717-6042
NAME OF PLAN--------------CENTRALIA STATION
SITE PLAN NUMBER----------16CP0051
ORIGINAL PLAN DATE--------12/15/15
LATEST PLAN DATE----------04/13/16
DEPT. REC'D. DATE---------04/14/16
ACCEPTED FOR REVIEW-------04/18/16
SUBMITTAL NUMBER----------THREE
REVIEW DATE---------------05/09/16
RECOMMENDATION------------REVISION REQUIRED
TABLE REVIEW--------------YES
01. PUT A REVISION DATE ON THE RESUBMITTED PLANS. RESUBMIT
10 FULL SETS TO THE PLANNING DEPARTMENT FOR YOUR NEXT
REVIEW. PROVIDE A COMPLETE RESPONSE TO COMMENTS FOR ALL
DEPARTMENTS TO THE PLANNING DEPARTMENT. BELOW EACH COMMENT
DESCRIBE HOW YOU HAVE ADDRESSED EACH REVIEW COMMENT. BE
SURE TO INDICATE WHICH SHEETS SHOW THE REQUIRED CHANGES.
PROVIDE A TRANSMITTAL LETTER TO DESCRIBE ANY CHANGES TO THE
PLANS NOT CAUSED BY THE STAFF REVIEW COMMENTS.
02. THE COUNTY PRESERVATION COMMITTEE AND PLANNING
COMMISSION RECOMMENDED APPROVAL TO REMOVE THE HISTORIC
DESIGNATION FROM THE CLARKE HOUSE PARCEL. THE DESIGNATION
IS TO REMAIN ON THE HOUSE AND A 20 FOOT ZONE SURROUNDING
THE STRUCTURE. NO DISTURBANCE IS TO OCCUR WITHIN THE 20
INDICATE THE 20 FOOT HISTORIC PRESERVATION ZONE
AROUND THE HOUSE ON SHEETS C-13 AND C-17, ALSO SHOWING THE
HOUSE ON C-17.
************************************************************
REVIEW DEPARTMENT: FIRE AND LIFE SAFETY
REVIEWER / PHONE#: KIM LESTER / 748-1489
PLAN NAME: CENTRALIA STATION
PLAN NUMBER: 16CP0051
LATEST REVISION DATE: 12/15/15
REVIEW DATE: 1/13/16
LATEST SUBMISSION DATE: 12/21/15
SUBMITTAL NUMBER: 1ST REVIEW
STATUS: NOT APPROVED
TABLE REVIEW:
THE HYDRANT SPACING EXCEEDS THE AVERAGE SPACING
OF 500 FEET. SEE IFC 2012, APPENDIX C, TABLE C105.1.
PROVIDE A COMPUTER GENERATED WATER FLOW TEST DATA,
ALONG WITH THE NODE MAP THAT IS PROVIDED BY THE
CHESTERFIELD COUNTY UTILITIES DEPARTMENT, VERIFYING
THE REQUIRED WATER FLOW FOR FIRE PROTECTION IS AVAILABLE
AT THE SITE THE WATER FLOW TEST RESULTS AND GRAPH SHALL
BE SHOWN ON THE SUBMITTED PLAN. IFC 2012, SECTION
B105.1
PLACE A NOTE ON THE PLAN THAT INDICATES THAT THE
EMERGENCY ACCESS SHALL BE BUILT PRIOR TO THE 51ST
BUILDING PERMIT.
EMERGENCY ACCESS STANDARDS
DESIGN
THE EMERGENCY ACCESS SHALL HAVE A PAVEMENT WIDTH OF 20
FEET WITH POSSIBLE PAVEMENT WIDTH EXTENSION TO FACILITATE
TWO-WAY TRAFFIC ON LONG ACCESSES OR CURVES AS DETERMINED
BY THE FIRE DEPARTMENT, BASED UPON THE ALIGNMENT AND
TOPOGRAPHY.
AN ADDITIONAL AREA CLEAR OF WOODY VEGETATION THREE BEYOND
THE EDGE OF PAVEMENT SHALL BE PROVIDED; IFC 2003, 503.2.1
PROVIDE A DETAIL ON THE PLANS FOR THE ACCESS ROAD GATES.
ANY ACCESS LONGER THAN 15 FEET SHALL BE GATED AT BOTH ENDS
IMMEDIATELY ADJACENT TO THE RIGHT OF WAY.
PAVEMENT
THE PAVEMENT SHALL BE DESIGNED AND CONSTRUCTED TO
CHESTERFIELD COUNTY SUBDIVISION STREET REQUIREMENTS OR AN
EQUIVALENT DESIGN APPROVED AT TIME OF TENTATIVE REVIEW,
CAPABLE OF SUPPORTING 75,000-POUND VEHICLE IN WEIGHT.
CONSTRUCTION PLANS FOR THE DESIGN OF THE EMERGENCY ACCESS
ROAD SHALL BE SUBMITTED TO THE FIRE DEPARTMENT FOR THEIR
APPROVAL. WITHIN 30 DAYS OF COMPLETION OF THE EMERGENCY
ACCESS, A GEOTECHNICAL ENGINEER'S REPORT SHALL BE SUBMITTED
TO THE FIRE DEPARTMENT VERIFYING THAT THE EMERGENCY ACCESS
HAS BEEN CONSTRUCTED TO THE APPROVED STANDARD. THE SUB-
DIVIDER/DEVELOPER SHALL BE RESPONSIBLE TO CALL FOR THE
INSPECTION.
GATES
THE ACCESS GATE SHALL CONSIST OF TWO PANELS EIGHT FEET WIDE
BY THREE FEET TALL CONSTRUCTED OF PAINTED TWO-INCH TUBULAR
STEEL. THE GATE PANEL SHALL BE PAINTED WITH TWO COATS OF
ENAMEL PAINT MATCHING PMS 186 RED AND SHALL HAVE ONE-
INCH WIDE BY12-INCH LONG WHITE REFLECTIVE STRIPS ON BOTH
SIDES OF THE EXTERIOR AND INTERIOR OF THE MIDDLE VERTICAL
MEMBER. THE GATES SHALL SWING ON NOT LESS THAN TWO PIVOT
PINS. THE GATES SHALL BE SUPPORTED BY A STEEL POST OF SIZE
AND WITH A FOUNDATION CAPABLE OF SUPPORTING THE INDIVIDUAL
GATE PANEL WITH 200-POUND WEIGHT AT THE OPPOSITE END. THE
BOTTOM OF THE GATE SHALL BE 12-INCHES ABOVE THE PAVEMENT.
THE POST SHALL BE FILLED WITH CONCRETE. THE POST SHALL
CONFORM TO THE GATE PAINT SPECIFICATIONS. THE GATE PANEL
SHALL BE DESIGNED, FABRICATED AND INSTALLED TO REMAIN OPEN
AFTER THE CLOSURE CHAIN IS UNDONE; IFC 2003, APPENDIX
D103.5.
THE GATES SHALL BE CLEARLY MARKED WITH REFLECTIVE WHITE
LETTERS ON RED BACKGROUND READING "EMERGENCY ACCESS ONLY".
GATE LOCK
THE DEVELOPER/SUB-DIVIDER SHALL FURNISH A WELDED LINK STEEL
CHAIN AND A PADLOCK AS MANUFACTURED BY KNOX COMPANY
TO SECURE THE GATE PANELS. THE REQUIRED FORMS AND
INSTALLATION INSTRUCTIONS FOR THE KEY BOX CAN BE OBTAINED
FROM CINDY MARSHALL IN THE FIRE AND LIFE SAFETY DIVISION,
AT 768-7963; IFC 2003, SECTION 506.
CONSTRUCTION PLANS
ALL APPLICABLE SUBDIVISION PLAN VIEW AND PROFILE SHEETS
WITH ROAD AND DRAINAGE CONSTRUCTION PLANS OR SITE
CONSTRUCTION PLANS SHALL SHOW THE LOCATION OF THE
EMERGENCY ACCESS. THE SUBDIVIDER/DEVELOPER SHALL SECURE
ANY NECESSARY VDOT PERMITS AND THE ACCESS SHALL MEET
THE VISIBILITY REQUIREMENTS FOR STREETS.
SHOW THE TYPICAL CROSS SECTION FOR THE EMERGENCY ACCESS
AND THE DESIGN FOR THE EMERGENCY ACCESS (I.E. TYPE OF
MATERIAL, PAVEMENT WIDTH AND DEPTH, ADJACENT PARALLEL
DRAINAGE DITCHES IF APPLICABLE AND EASEMENT LIMITS, ETC.)
SHALL BE SHOWN TO SCALE.
MAINTENANCE
PRIOR TO RECORDATION, A COPY OF THE HOMEOWNER'S
ASSOCIATION BY-LAWS SHALL BE SUBMITTED TO THE FIRE
DEPARTMENT FOR REVIEW OF THE LANGUAGE REQUIREMENTS FOR
MAINTENANCE OF THE EMERGENCY ACCESS.
EMERGENCY ACCESS LOCATION, CONSTRUCTION REQUIREMENTS AND
MAINTENANCE RESPONSIBILITY SHALL BE SHOWN ON THE TENTATIVE,
FINAL CHECK AND RECORD PLATS.
IF THE LOCATION OF THE EMERGENCY ACCESS ON CONSTRUCTION
PLANS IS DIFFERENT FROM THE APPROVED TENTATIVE SUBDIVISION
PLAT, THE TENTATIVE SUBDIVISION PLAT SHALL BE RESUBMITTED
AS AN ADUJUSTED TENTATIVE FOR APPROVAL. THE ENVIRONMENTAL
ENGINEERING AND FIRE DEPARTMENTS SHALL BE RESPONSIBLE FOR
INSPECTING THE EMERGENCY ACCESS AND PROVIDING A PUNCH
LIST (IF NECESSARY) TO THE SUB-DIVIDER.
++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
REVIEW DEPARTMENT: FIRE AND LIFE SAFETY
REVIEWER / PHONE#: KIM LESTER / 748-1489
PLAN NAME: CENTRALIA STATION
PLAN NUMBER: 16CP0051
LATEST REVISION DATE: 2/26/16
LATEST SUBMISSION DATE: 3/1/16
SUBMITTAL NUMBER: 2ND REVIEW
STATUS: NOT APPROVED
TABLE REVIEW: NO
THESE COMMENTS ARE BEING MADE DUE TO THE HYDRANT SPACING
NOT BEING MET.
RELOCATE THE HYDRANT AT LOT 88 TO STATION 23+00.
ADD A HYDRANT AT THE INTERSECTION OF CENTRALIA STATION ROAD
AND THE FUTURE ROAD.
RELOCATE THE HYDRANT AT LOT 17 TO THE PROPERTY LINE OF LOT
16 AND THE OPEN SPACE.
ADD A HYDRANT AT THE PROPERTY LINE OF LOT 21 AND 22.
RELOCATE THE HYDRANT ON CENTRALIA STATIN COVE TO STATION
50+10 ON CENTRALIA STATION ROAD.
RELOCATE THE HYDRANT ON LOT 45 TO THE PROPERTY LINE OF LOT
43 AND 44.
ADD A HYDRANT AT THE PROPERTY LINE OF LOT 24 AND 25. THE
WATER METER FOR LOT 24 WILL NEED TO BE RELOCATED TO THE
OTHERSIDE OF THE PROPERTY.
PLACE THE FOLLOWING STANDARDS ON THE PLAN.
EMERGENCY ACCESS STANDARDS
PAVEMENT
THE PAVEMENT SHALL BE DESIGNED AND CONSTRUCTED TO
CHESTERFIELD COUNTY SUBDIVISION STREET REQUIREMENTS OR AN
EQUIVALENT DESIGN APPROVED AT TIME OF TENTATIVE REVIEW,
CAPABLE OF SUPPORTING 75,000-POUND VEHICLE IN WEIGHT.
CONSTRUCTION PLANS FOR THE DESIGN OF THE EMERGENCY ACCESS
ROAD SHALL BE SUBMITTED TO THE FIRE DEPARTMENT FOR THEIR
APPROVAL. WITHIN 30 DAYS OF COMPLETION OF THE EMERGENCY
ACCESS, A GEOTECHNICAL ENGINEER'S REPORT SHALL BE SUBMITTED
TO THE FIRE DEPARTMENT VERIFYING THAT THE EMERGENCY ACCESS
HAS BEEN CONSTRUCTED TO THE APPROVED STANDARD. THE SUB-
DIVIDER/DEVELOPER SHALL BE RESPONSIBLE TO CALL FOR THE
INSPECTION.
GATES
THE ACCESS GATE SHALL CONSIST OF TWO PANELS EIGHT FEET WIDE
BY THREE FEET TALL CONSTRUCTED OF PAINTED TWO-INCH TUBULAR
STEEL. THE GATE PANEL SHALL BE PAINTED WITH TWO COATS OF
ENAMEL PAINT MATCHING PMS 186 RED AND SHALL HAVE ONE-
INCH WIDE BY12-INCH LONG WHITE REFLECTIVE STRIPS ON BOTH
SIDES OF THE EXTERIOR AND INTERIOR OF THE MIDDLE VERTICAL
MEMBER. THE GATES SHALL SWING ON NOT LESS THAN TWO PIVOT
PINS. THE GATES SHALL BE SUPPORTED BY A STEEL POST OF SIZE
AND WITH A FOUNDATION CAPABLE OF SUPPORTING THE INDIVIDUAL
GATE PANEL WITH 200-POUND WEIGHT AT THE OPPOSITE END. THE
BOTTOM OF THE GATE SHALL BE 12-INCHES ABOVE THE PAVEMENT.
THE POST SHALL BE FILLED WITH CONCRETE. THE POST SHALL
CONFORM TO THE GATE PAINT SPECIFICATIONS. THE GATE PANEL
SHALL BE DESIGNED, FABRICATED AND INSTALLED TO REMAIN OPEN
AFTER THE CLOSURE CHAIN IS UNDONE; IFC 2003, APPENDIX
D103.5.
THE GATES SHALL BE CLEARLY MARKED WITH REFLECTIVE WHITE
LETTERS ON RED BACKGROUND READING "EMERGENCY ACCESS ONLY".
GATE LOCK
THE DEVELOPER/SUB-DIVIDER SHALL FURNISH A WELDED LINK STEEL
CHAIN AND A PADLOCK AS MANUFACTURED BY KNOX COMPANY
TO SECURE THE GATE PANELS. THE REQUIRED FORMS AND
INSTALLATION INSTRUCTIONS FOR THE KEY BOX CAN BE OBTAINED
FROM CINDY MARSHALL IN THE FIRE AND LIFE SAFETY DIVISION,
AT 768-7963; IFC 2003, SECTION 506.
CONSTRUCTION PLANS
ALL APPLICABLE SUBDIVISION PLAN VIEW AND PROFILE SHEETS
WITH ROAD AND DRAINAGE CONSTRUCTION PLANS OR SITE
CONSTRUCTION PLANS SHALL SHOW THE LOCATION OF THE
EMERGENCY ACCESS. THE SUBDIVIDER/DEVELOPER SHALL SECURE
ANY NECESSARY VDOT PERMITS AND THE ACCESS SHALL MEET
THE VISIBILITY REQUIREMENTS FOR STREETS.
SHOW THE TYPICAL CROSS SECTION FOR THE EMERGENCY ACCESS
AND THE DESIGN FOR THE EMERGENCY ACCESS (I.E. TYPE OF
MATERIAL, PAVEMENT WIDTH AND DEPTH, ADJACENT PARALLEL
DRAINAGE DITCHES IF APPLICABLE AND EASEMENT LIMITS, ETC.)
SHALL BE SHOWN TO SCALE.
MAINTENANCE
PRIOR TO RECORDATION, A COPY OF THE HOMEOWNER'S
ASSOCIATION BY-LAWS SHALL BE SUBMITTED TO THE FIRE
DEPARTMENT FOR REVIEW OF THE LANGUAGE REQUIREMENTS FOR
MAINTENANCE OF THE EMERGENCY ACCESS.
EMERGENCY ACCESS LOCATION, CONSTRUCTION REQUIREMENTS AND
MAINTENANCE RESPONSIBILITY SHALL BE SHOWN ON THE TENTATIVE,
FINAL CHECK AND RECORD PLATS.
IF THE LOCATION OF THE EMERGENCY ACCESS ON CONSTRUCTION
PLANS IS DIFFERENT FROM THE APPROVED TENTATIVE SUBDIVISION
PLAT, THE TENTATIVE SUBDIVISION PLAT SHALL BE RESUBMITTED AS
AN ADJUSTED TENTATIVE FOR APPROVAL. THE ENVIRONMENTAL
ENGINEERING AND FIRE DEPARTMENTS SHALL BE RESPONSIBLE FOR
INSPECTING THE EMERGENCY ACCESS AND PROVIDING A PUNCH
LIST (IF NECESSARY) TO THE SUB-DIVIDER.
++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
REVIEW DEPARTMENT: FIRE AND LIFE SAFETY
REVIEWER / PHONE#: KIM LESTER / 748-1489
PLAN NAME: CENTRALIA STATION
PLAN NUMBER: 16CP0051
REVIEW DATE: 3/27/16
LATEST REVISION DATE: 4/13/16
LATEST SUBMISSION DATE: 4/18/16
SUBMITTAL NUMBER: 3RD REVIEW
STATUS: APPROVED
TABLE REVIEW: YES
++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
REVIEW DEPARTMENT: FIRE AND LIFE SAFETY
REVIEWER / PHONE#: KIM LESTER / 748-1489
PLAN NAME: CENTRALIA STATION
PLAN NUMBER: 16CP0051
REVIEW DATE: 5/31/16
LATEST REVISION DATE: 5/26/16
LATEST SUBMISSION DATE: 5/31/16
SUBMITTAL NUMBER: 4TH REVIEW
STATUS: APPROVED
TABLE REVIEW: YES
++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
============================================================
============================================================
REVIEW DEPARTMENT : ENVIRONMENTAL ENGINEERING
REVIEWER/PHONE # : MARIA JENKINS/751-2335
NAME OF PLAN : CENTRALIA STATION
SITE PLAN NO. : 16CP0051
LATEST PLAN DATE : 12/15/15
DEPT. REC'D DATE : 12/30/15
SUBMITTAL NUMBER : 1
REVIEW DATE : 02/03/16
RECOMMENDATION : REVISIONS REQUIRED
TABLE REVISION : NO
PLAT PROCESSING : NO
1. IT IS THE RESPONSIBILITY OF THE APPLICANT TO COMPLY
WITH AND/OR ACQUIRE ALL APPLICABLE FEDERAL AND/OR STATE
PERMITS IN RELATIONSHIP TO ENVIRONMENTAL FEATURES INCLUDING
BUT NOT LIMITED TO WETLANDS, SURFACE WATERS (E.G. VSMP
PERMIT FOR CONSTRUCTION SITES, GROUND WATER AND AIR
QUALITY) FINAL APPROVAL OF THESE PLANS WILL NOT RELIEVE YOU
OF YOUR RESPONSIBILITY. WETLANDS DOCUMENTATION MUST BE
RECEIVED BY THIS DEPARTMENT PRIOR TO ISSUANCE OF THE LAND
DISTURBANCE PERMIT.
2. THIS OFFICE RECOGNIZES THAT THE 10-YEAR PRE/10-YEAR POST
REQUIREMENTS FOR FLOOD PROTECTION MAY BE ADDRESSED BY
DISCHARGING INTO THE 100-YEAR FLOODPLAIN.
3. UNTIL THE RPA ISSUE ABOVE/BELOW STRUCTURES 67/91 IS
RESOLVED, A FULL REVIEW CANNOT BE COMPLETED. ADDITIONAL
COMMENTS MAY BE GENERATED WITH THE NEXT SUBMITTAL.
=== EROSION CONTROL ===
1. AN ITEMIZED EROSION CONTROL COST ESTIMATE MUST BE
SUBMITED FOR REVIEW AND/OR APPROVAL.
2. AS A PREREQUISITE TO THE ISSUANCE OF A LAND
DISTURBANCE PERMIT:
A) A COPY OF THE AUTOCAD FILE MUST BE SUBMITTED TO
CAROLE CLIBORNE OF THE ENVIRONMENTAL ENGINEERING. THE
AUTOCAD FILE MUST BE SAVED AS A .DWG OR .DXF IN AUTOCAD
VERSION 2009 OR EARLIER AND REFERENCED DIRECTLY TO THE
VIRGINIA STATE PLANE COORDINATE SYSTEM, SOUTH ZONE IN
THE NAD83 DATUM. THE AUTOCAD FILE MAY BE SUBMITTED ON A
CD, DVD, OR VIA EMAIL AND MUST BE CLEARLY LABELED WITH
THE SUBDIVISION NAME AND SECTION, SUBDIVISION PLAN
NUMBER, ENGINEERING FIRM AND CAD FILE PREPARER'S NAME
AND PHONE NUMBER. THE FILE MUST CONTAIN THE FOLLOWING,
EACH CLEARLY LABELED IN SEPARATE LAYERS:
EDGES OF ROADS TO INCLUDE CURB AND GUTTER; AND
EDGES OF SIDEWALKS;
THE FILE MUST BE APPROVED BY ENVIRONMENTAL ENGINEERING
PRIOR TO ISSUANCE OF THE LAND DISTURBANCE PERMIT.
B) FLAGGING AROUND USACOE JURISDICTIONAL WETLANDS,
BUFFERS, AND SENSITIVE AREAS MUST BE VISIBLE.
C) DOCUMENTATION FROM THE USACOE/DEQ MUST BE RECEIVED
VERIFYING COMPLIANCE TO WETLAND PERMIT REGULATIONS.
D) A COPY OF VDOT LAND USE PERMIT MUST BE RECEIVED.
E) SAFETY FENCE AND/OR SUPER SILT FENCE WITH OPTIC
ORANGE FABRIC MUST BE IN PLACED ALONG THE RPA LIMITS.
F) AN EROSION CONTROL BOND MUST BE POSTED.
G) THE RISER AND BARREL PIPE ASSOCIATED WITH THE
SEDIMENT BASIN MUST BE ON-SITE.
H) TWO ADDITIONAL SETS OF CONSTRUCTION PLANS TO BE
STAMPED "APPROVED FOR CONSTRUCTION" MUST BE RECEIVED.
I) AS APPLICABLE, A SWPPP BOOKLET (3 RING BINDER) MUST
BE PROVIDED.
3. THESE ARE IN REGARDS TO THE MS-19:
A) IT APPEARS THE MS-19 DOWNSTREAM OF BMP#1 CAN BE
ADDRESSED BY 1% RULE. PLEASE PROVIDE AN ADDITIONAL SHEET
THAT SHOWS THE ACREAGE OF CONTRIBUTING DRAINAGE
AREAS/LIMITS THAT DRAINS TO GREAT BRANCH CREEK AT THE
POINT OF ANALYSIS WHERE THIS PROJECT DRAINS. INCLUDE THE
NECESSARY INFORMATION ON THE PLANS SUPPORTING THE 1% RULE
(I.E. DRAINAGE AREAS OF THIS PROJECT VERSUS THE
CONTRIBUTING DRAINAGE AREAS THAT DRAINS TO GREAT BRANCH
CREEK, ETC.) AND BE SURE THE EXISTING CONTOURS ARE BEING
LABELED WITH ELEVATIONS. A FURTHER DISCUSSION MAY BE
HELPFUL.
B) THIS OFFICE WAS NOT ABLE TO LOCATE THE MS-19 X-
SECTIONS A/C/ETC. ANALYSIS WITH SCALED X-SECTIONS, ETC.
WITHIN THE SUBMITTAL PACKAGE FOR FURTHER REVIEW AND/OR
APPROVAL. PLEASE ADDRESS.
IN ADDITION, PLEASE SUBMIT MS-19 VARIANCE REQUEST LETTER
BELLOW THE PLUNGE POOL/BMP#1 SITUATION E FOR APPROVAL AND
DOCUMENTATION.
C) PLEASE REVISE THE ADEQUACY SITUATION AT MS-19 X-
SECTION C TO BE H IN LIEU OF E (SHEET C-12).
IN ADDITION, SUBMIT MS-19 VARIANCE REQUEST LETTER BELOW
STR. 36 SITUATION H FOR DISCHARGING PRIOR TO REACHING THE
CENTERLINE OF THE NATURAL CHANNEL.
D) PLEASE PERFORM MS-19 ANALYSIS AT THE NATURAL
DRAINAGEWAY BELOW STRUCTURES 40/46/78/89/92/ETC. SUBMIT
2/10-YEAR HYDROLOGIC/HYDRAULIC CALCULATIONS, SCALED X-
SECTIONS, SHOW/LABEL THE MS-19 SECTIONS-LOCATIONS, ETC.
ON THE PLANS AND UPDATE THE MS-19 TABLE TO INCLUDE THESE
LOCATIONS.
4. WE OFFER, BUT NOT LIMITED TO, THE FOLLOWING COMMENTS:
A) PLEASE BE SURE TO SHOW THE GENERAL EROSION AND
SEDIMENT CONTROL NOTES AND THE EC LEGEND ON THE EC PLANS
AS OPPOSED TO SHOWING ON THE COVER SHEET. PLEASE
ADDRESS.
B) PLEASE USE THE APPROPRIATE LINE TYPE FOR SILT FENCE
TO BE -X-X- IN LIEU OF -SF-SF-. REFER TO THE FIRST PAGE
OF THE PRACTICE FOUND IN CHAPTER III OF THE VIRGINIA
EROSION AND SEDIMENT CONTROL HANDBOOK. REVISE THE E & S
CONTROL - PHASE I TO REFLECT THE CHANGES.
C) PLEASE BE SURE TO SHOW THE CENTERLINE STATIONING AT
EVERY 100' ALONG THE PROPOSED ROADS. REFLECT THE CHANGES
ON THE EC PHASE I AND PHASE II.
D) PLEASE BE SURE THAT ALL THE EXISTING CONTOURS ARE
BEING LABELED WITH ELEVATIONS. REFLECT THE CHANGES ON
THE EC PHASE I AND PHASE II PLANS.
E) THE LIMITS OF CLEARING MUST BE RESTRICTED TO ONLY
CLEAR THE AREA NECESSARY TO INSTALL THE PHASE I EC
MEASURES. CLEAR HALF OF THE ROAD WIDTH AS OPPOSED
THE ENTIRE ROAD TEMPLATE. PLEASE ADDRESS.
F) PLEASE LABEL THE DIVERSION DIKE AS DD WHERE ARE BEING
SPECIFIED. REFLECT THE CHANGES ON EC PHASE I AND PHASE
II.
G) PLEASE BE SURE TO SHOW/LABEL CHECK DAMS ALONG THE
PROPOSED DITCH SPECIFIED ON THE REAR OF LOTS 32 THRU 35,
AND THE DITCH REQUESTED ON THE REAR OF LOTS 19 THRU 23,
ETC.
H) THESE ARE IN REGARDS TO THE SEDIMENT BASIN 1:
H.1) IT APPEARS AFTER THE INSTALLATION OF THE STORM
SEWER MORE AREA WOULD BE DRAINING TO THIS SEDIMENT BASIN
(SB#1). HOWEVER, THE BASIN WAS ONLY DESIGNED FOR 6
ACRES. PLEASE CLARIFY OR REVISE THE BASIN CALCULATIONS
TO ACCOUNT FOR 10.30 ACRES. REFLECT THE CHANGES ON ALL
APPLICABLE SHEETS.
H.2) PLEASE PROVIDE SAFETY FENCE ALONG THE RPA LIMITS IN
THE PROXIMITY OF BMP#1, ETC. REFLECT THE CHANGES ON THE
EC PHASE I AND PHASE II.
H.3) BASED ON THE SB#1 CALCULATIONS TEMPORARY BAFFLES
ARE REQUIRED. PLEASE SHOW/LABEL THE TEMPORARY BAFFLES ON
THE PLAN VIEWS (SHEETS C-5 AND C-9). IN ADDITION,
PROVIDE A DETAIL OF THE TEMPORARY BAFFLE ON THE EC
PLANS.
H.4) AS A REMINDER, DEQ HAS EXPRESSED SOME CONCERNS
IN THE PAST FOR USING THIS ALTERNATIVE DESIGN/PLYWOOD
WEIR WITH DEWATERING DEVICE.
I) PLEASE BE SURE THAT THE DISTURBED AREAS PERTINENT TO
THE ROAD CONSTRUCTION WOULD DRAIN TO SEDIMENT BASINS
AND/OR TRAPS IN ITS ENTIRETY.
IN ADDITION, IT APPEARS DURING INITIAL PHASES OF THE
EROSION CONTROL, ESPECIALLY BEFORE THE INSTALLATION OF
THE STORM SEWER(S), THE LOOSE SEDIMENTS WILL NOT DRAIN
TO THE PROPOSED SEDIMENT BASIN(S) OR PART OF THE
PROPOSED GRADING FROM THE ROAD WOULD NOT DRAIN TO THESES
SEDIMENT BASINS. PLEASE PROVIDE EC MEASURES SUCH AS
SEDIMENT TRAPS/SILT FENCE/ETC. TO ADDRESS THIS CONCERN.
J) PLEASE BE SURE TO PROVIDE TWO TRAPS ON THE UPSTREAM
SIDE OF STRUCTURES 31, 41, 90, ETC. ON EITHER SIDE OF
THE PIPE AND TWO SEDIMENT TRAPS OF THE DOWNSTREAM SIDE
OF STRUCTURES 33, 46, 92, ETC. ON EITHER SIDE OF THIS
PIPE TO INTERCEPT SEDIMENTS FROM THE ROAD CONSTRUCTION
PRIOR TO REACHING THE WETLAND DRAINAGEWAY.
IN ADDITION, SUPER SILT FENCE/SILT FENCE SHOULD BE
PROVIDED AT THE FUTURE TOE OF FILL. STARTING AT THE HIGH
POINT IN THE PROXIMITY OF STATIONS
23+50/27+00/32+50/36+10/42+50/ETC. ON BOTH SIDES OF THE
ROAD AND CONTINUE THIS SILT FENCE AND/OR SUPER SILT
FENCE UNTIL IT REACHES THE TRAPS PREVIOUSLY REQUESTED.
BE SURE THE SUPER SILT FENCE SURROUNDS THE FILL AREAS OF
THESE TRAPS. A FURTHER DISCUSSION IS RECOMMENDED.
ADDITIONALLY, PLEASE PROVIDE SEDIMENT TRAP DETAIL AND
SEDIMENT TRAP SCHEDULE ON THE EC PLANS.
K) IT APPEARS THE NATURAL DRAINAGEWAY IN THE VICINITY
OF STATION 17+50 IS CONVEYING 19.80 ACRES. THEREFORE A
TEMPORARY CULVERT FOR TEMPORARY STREAM CROSSING OR THE
PERMANENT STORM SEWER STRUCTURES 15 THRU 31 TO TEMPORARY
OUTFALL TO THE WETLAND AREA IN THE VICINITY OF LOT 2
SHOULD BE CONSIDERED. PLEASE INCLUDE ALL NECESSARY
NOTES, DETAILS, ETC. TO ADDRESS THIS CONCERN.
IN ADDITION, IF A TEMPORARY CULVERT WOULD BE SPECIFIED,
MS-19 ANALYSIS SHOULD BE PERFORMED TO ENSURE THE
RECEIVING FACILITY IS ADEQUATE, SINCE IT WOULD BE
DISCHARGING TO OFFSITE PROPERTY. A FURTHER DISCUSSION IS
RECOMMENDED.
FURTHERMORE, BEST-FIT EXCAVATED PIT SHOULD BE PROVIDED
ON THE UPSTREAM AND DOWNSTREAM OF THIS TEMPORARY CULVERT
TO INTERCEPT SEDIMENTS FROM THE ROAD CONSTRUCTIONS.
PROVIDE THE NECESSARY NOTES AND DETAILS ON THE PLANS TO
ADDRESS THIS CONCERN.
IN ADDITION, PROVIDE THE ENCLOSED DETAIL OF THE
EXCAVATED PIT WITH TEMPORARY GRAVEL OUTLET STRUCTURE ON
THE EC PLANS.
L) PLEASE PROVIDE MINIMUM 10' BREAK IN THE LOW AREA OF
THE SILT FENCE IN THE PROXIMITY OF LOT 63. THE BREAK
MUST BE BACKFILLED WITH STONE TO WITHIN THE TOP OF THE
SILT FENCE TO SERVE AS AN OUTLET STRUCTURE.
IN ADDITION, PROVIDE SMALL EXCAVATED PIT ON THE UPSTREAM
SIDE OF THE 10' BREAK. REFLECT THE CHANGES ON THE EC
PHASE II PLAN (SHEET C-8).
M) PLEASE SHOW/LABEL A SUITABLE LOCATION(S) FOR THE
TEMPORARY STOCKPILE SURROUNDED WITH SILT FENCE. REFLECT
THE CHANGES ON THE EC PHASE I AND PHASE II.
N) PLEASE PROVIDE INLET PROTECTION AT STR. 107. REFLECT
THE CHANGES ON THE EC PHASE II.
5. IF TIMBERING IS REQUIRED ON THE PROJECT, IT SHOULD BE
INCORPORATED INTO THE EROSION CONTROL PLAN / NARRATIVE AND
SHOULD NOT BEGIN UNTIL AFTER THE ISSUANCE OF A LAND
DISTURBANCE PERMIT AND THE INSTALLATION OF THE APPROVED
EROSION CONTROL DEVICES.
======= CBPA =======
1. PER RECENT TELEPHONE CONVERSATION WITH ZACKARY, ROBERT
AND MARIA, IT WAS AGREED TO ELIMINATE BMP#2 AND BMP#3.
SINCE BMP#1 PROVIDES THE REQUIRED POLLUTANT REMOVAL. AS
NEEDED, REVISE ALL APPLICABLE SHEETS.
2. PLEASE REVISE THE TOTAL AREA FOR THE SITE IN THE SITE
SUMMARY TO BE 83.81 ACRES AS OPPOSED TO 79.24 ACRES.
IN ADDITION, THE INFORMATION PROVIDED IN THE SITE SUMMARY
(SHEET C-1) FOR THE AREA IN R/W, OPEN SPACE, IN THE LOTS DO
NOT MATCH OF 10.43 AC/25.26 AC/40.88 AC/ETC. WITH THE
INFORMATION INDICATED IN THE APPROVED TENTATIVE PLAN OF
10.45 AC/23.81 AC/49.16 AC/ETC. PLEASE CLARIFY OR REVISE TO
ENSURE THE INFORMATION IS CONSISTENT WITH CONSTRUCTION
PLANS AND TENTATIVE PLANS.
3. PLEASE BE SURE TO INCORPORATE THE REVISED CBPA ANALYSIS
(SHEET C-36) RECEIVED VIA EMAIL ON 01/13/16 IN THE
CONSTRUCTION PLANS WITH THE NEXT PLAN SUBMITTAL.
4. PLEASE REVISE THE RPA SIGN (SHEET C-38) TO SPECIFY THE
POST TO BE "4" X 4" PRE-TREATED POST".
5. PLEASE EXPLAIN WHY THE RPA HAS BEEN OMITTED ENCLOSING
THE WETLANDS CLOVERLEAF ABOVE/BELOW STRUCTURES 39/44 IN THE
CONSTRUCTION PLANS.
======= SWM/BMP =======
1. IN LIEU OF OUTLET PROTECTION LOCATED AT THE OF THE
CONCRETE CHANNEL/PRINCIPAL SPILLWAY, PLEASE PROVIDE PLUNGE
POOL WITH MINIMUM 18" DEPTH. INCLUDE THE PERTINENT
INFORMATION/DETAILS ON THE PLANS AND PROFILES.
2. PLEASE INCLUDE THE SEDIMENT FOREBAY DETAIL ON THE
SWM/BMP PLAN SHEET.
3. THESE ARE IN REGARDS TO THE SWM/BMP PROFILE BMP#1 (SHEET
C-21):
A) SHOW ARMORED WITH RIPRAP THE SEDIMENT FOREBAY AND BE
SURE THE TOP OF THE EMBANKMENT OF THE FOREBAY IS 6"
BELOW THE NORMAL WATER SURFACE ELEVATION.
B) PLEASE SHOW/LABEL THE PLUNGE POOL WITH PERTINENT
INFORMATION.
C) PLEASE BE SURE TO SHOW/LABEL THE 100-YEAR FEMA
FLOODPLAIN LIMITS AND THE LIMITS OF THE RPA ON THIS
PROFILE.
4. THESE ARE IN REGARDS TO THE SWM/BMP GRADING PLAN (SHEET
C-21):
A) PLEASE LABEL THE SWM/BMP EASEMENT ON THE WESTERN SIDE
AND EASTERN SIDE OF THIS EASEMENT AND BE SURE TO USE A
LEADER LINE TO INDICATE THIS EASEMENT.
B) BE SURE THE PLUNGE POOL IS WITHIN THE SWM/BMP
EASEMENT.
C) PLEASE SHOW/LABEL THE RIPRAP PATTERN ARMORING THE
SEDIMENT FOREBAY WITH PERTINENT INFORMATION.
D) PLEASE EXTEND THE PROPOSED DITCH SPECIFIED ON THE
REAR OF LOTS 32 THRU 35 TO THE BOTTOM OF THE SWM/BMP
WETPOND AND PROVIDE OUTLET PROTECTION AT THE END OF THIS
DITCH IMPROVEMENT WITH PERTINENT INFORMATION. REFLECT
THE CHANGES ON THE PLANS AND PROFILES.
E) PLEASE CLEARLY SHOW/LABEL THE 50' VEGETATIVE
PERIMETER YARD SETBACK.
F) PLEASE SHOW/LABEL THE 12' BMP GRAVEL ACCESS ROAD. IN
ADDITION, SHOW THE GRAVEL PATTERN ALONG THE BMP GRAVEL
ACCESS ROAD. REFLECT THE CHANGES ON ALL APPLICABLE
SHEETS.
G) PLEASE BE SURE TO USE LEADER LINES TO INDICATE THE
APPROPRIATE LABELING (I.E. 20'BMP ACCESS EASEMENT,
VARIABLE WIDTH SWM/BMP EASEMENT, ETC.) TO THE LIMITS OF
THE CORRESPONDING EASEMENTS.
H) PLEASE LABEL THE 16' DRAINAGE EASEMENT THAT IS
ENCLOSING STRUCTURES 140/141.
I) PLEASE SHOW/LABEL THE REMOVAL BOLLARDS OR GATE AT THE
ENTRANCE OF THE BMP ACCESS ROAD. INCLUDE A DETAIL OF THE
REMOVAL BOLLARDS OR GATE ON THE SWM/BMP PLANS.
J) PLEASE SHOW/LABEL THE AUTHORIZED ONLY VEHICLE SIGN
WITHIN THE ENTRANCE OF THE BMP ACCESS ROAD. INCLUDE THE
PERTINENT DETAIL ON THE SWM/BMP PLANS.
K) PLEASE DEPICT ON THE PLAN VIEW THE SECTIONS LINE B-B
PERTINENT TO THE CONCRETE WALL.
L) PLEASE INDICATE THE APPROXIMATE LIMITS OF THE
IMPERMEABLE CLAY CORE SPECIFIED WITHIN THE FILL SECTION
OF THE EMBANKMENT ON THE PLAN VIEW.
M) IN LIEU OF 18", PLEASE SPECIFY A MINIMUM 3'
PROJECTION INTO THE EMBANKMENT AS NOTED IN SECTION A-A.
5. PLEASE PROVIDE THE STANDARD DETAIL OF THE BMP ACCESS
ROAD ON THE SWM/BMP PLANS.
6. PLEASE REVISE THE ELEVATION OF 254.00 IN SECTION A - A
(SHEET C-21), WHICH APPEARS TO BE 127.00. IN ADDITION,
PLEASE SPECIFY THE BOTTOM ELEVATION OF THIS TRAPEZOIDAL
DITCH.
7. PLEASE SPECIFY MINIMUM 18" CURTAIN WALL AT THE END OF
THE TRAPEZOIDAL CONCRETE DITCH. REVISE SECTION B-B TO
DEPICT THE END OF THIS DITCH IMPROVEMENT.
IN ADDITION, SUBMIT 10/100-YEAR DITCH CALCULATIONS FOR THE
OUTFALL CONCRETE DITCH FOR FURTHER REVIEW AND/OR APPROVAL.
8. PLEASE REVISE SECTION B-B TO SPECIFY THE TOP/BOTTOM
ELEVATION(S) OF THE CONCRETE WALL AND THE HEIGHT OF THE
WALL.
9. PLEASE ADD TENTATIVE CONDITIONS #13, #14 AND #15 ON THE
SWM/BMP PLANS, WHICH STATES,
"TC#13: THE DESIGN AND CONSTRUCTION OF THE SWM/BMPS THAT
WILL BE A COUNTY MAINTAINED FACILITY WOULD BE SUBJECT TO
INDEPENDENTLY DOCUMENTED GEOTECHNICAL APPROVAL. THE
SERVICES THAT MUST BE PROVIDED BY INDEPENDENT GEOTECHNICAL
ENGINEERING FIRM SHALL INCLUDE FULL-TIME GEOTECHNICAL
INSPECTION PAID FOR BY THE DEVELOPER. THAT FULL-TIME
INSPECTION SHALL INCLUDE BY NOT BE LIMITED TO THE
FOLLOWING:
A) PARTICIPATION/INPUT INTO THE DESIGN PROCESS AS NECESSARY
TO FACILITATE THE APPROVAL PROCESS OF THE INDEPENDENT
GEOTECHNICAL CONSULTANT. OBSERVATION, TESTING AND
DOCUMENTATION OF:
I. SUITABLE SUBGRADES TO RECEIVE COMPACTED STRUCTURAL
FILL FOR EARTH DAM CONSTRUCTION.
II. THE CU-OFF TRENCH, SPILLWAY PIPE, DRAINAGE BLANKET,
RISER STRUCTURE, AND CONCRETE CHUTE SPILLWAY SUB-GRADES
AS APPLICABLE TO EVALUATE WHETHER SUITABLE SOIL IS
PRESENT AT BEARING GRADE TO VERIFY PROPER INSTALLATION.
III. REINFORCE STEEL, IF REQUIRED, TO EVALUATE ITS
CONFORMANCE WITH THE PROJECT PLANS AND SPECIFICATIONS.
TC#14: THE FACILITY CERTIFICATION PROCESS SHALL BE
PERFORMED BY AN ENGINEERING/SURVEYING PROFESSIONAL AT
THE OWNER'S EXPENSE.
TC#15: THE NAME OF THE GEOTECHNICAL PROFESSIONAL WHO
WILL PROVIDE THE GEOTECHNICAL APPROVAL ON THE DAM WILL
BE FURNISHED PRIOR TO THE ISSUANCE OF THE LAND
DISTURBANCE PERMIT."
10. A NO-RISE CERTIFICATE SIGNED/SEALED BY A LICENSED
PROFESSIONAL ENGINEER MUST BE PROVIDED WITH SUPPORTING
TECHNICAL DATA THAT PROPOSED DETENTION BASIN/FILL GRADING
ACTIVITY WILL NOT IMPACT THE FEMA FLOODPLAIN.
11. PLEASE LABEL THE BMP#1 ON THE ROAD PLANS, GRADING PLANS,
HYDRAULIC ANALYSIS PLANS, OVERALL HYDRAULIC ANALYSIS PLANS,
FLOODPLAIN ANALYSIS PLANS, ETC.
12. BAFFLES APPEAR TO BE REQUIRED FOR THIS BASIN, PLEASE
PROVIDE AN ENLARGED SCALED DETAIL OF THE PERMANENT BAFFLE
WITH DIMENSIONS/MATERIALS ON THE SWM/BMP PLANS.
======= ROAD AND DRAINAGE =======
1. DUE TO THE ABSENCE OF CENTERLINE STAKING AND HEAVY
VEGETATION, OUR CONCERNS ARE BASED ON THE INFORMATION SHOWN
IN THE CONSTRUCTION PLANS. THE RESPONSIBILITY FOR
IDENTIFYING CRITICAL AREAS IS PLACED ON THE PROFESSIONAL
ENGINEER WHO SEALS THE CONSTRUCTION PLANS APPROVED. WE
RESERVE THE RIGHT TO INSPECT CONVEYANCE SYSTEMS PRIOR TO
PLAT RECORDATION AND/OR STATE ACCEPTANCE TO DETERMINE IF
ADDITIONAL IMPROVEMENTS ARE REQUIRED.
2. IT APPEARS THE TEXT IN THE COPY PERTINENT TO POLLUTION
PREVENTION PLAN (SHEET C-40) IS VERY UNCLEAR AND
HARDLY READABLE. PLEASE PROVIDE A BETTER COPY SO THE
TEXT IS LEGIBLE AND EASY TO READ.
3. PLEASE REVISE THE LATITUDE AND LONGITUDE COORDINATES
(SHEET C-1) TO BE SHOWN IN DECIMAL DEGREES AS OPPOSED TO
DMS (DEGREE, MINUTES, SECONDS).
4. PLEASE INCLUDE ONE MORE ITEM IN THE INFORMATION PROVIDED
FOR PLANE COORDINATE, RECEIVING WATERS, HYDROLOGIC UNIT,
ETC. (SHEET C-1) STATING, "D. FEMA ZONE AE W/FLOODWAY PANEL
327 DATED 12-18-12."
5. THE ADJACENT PROPERTY OWNERS: SPRUILL, P. AT 4401
CHIPPOKE RD., STANEART, R. AT 4407 CHIPPOKE RD., STANDEFER,
E. AT 4413 CHIPPOKE RD., BANKS, K. AT 4419 CHIPPOKE RD.,
FINKLEA, C. AT 4501 CHIPPOKE RD., HOBBS, R. AT 4421
CENTRALIA RD., TAYLOR, H. AT 10221 CENTRALIA STATION,
CLEMENTS, L. AT 10210 CENTRALIA STATION, TUNSTALL, J. AT
10300 CENTRALIA STATION, ETC. SHOULD BE NOTIFIED OF THE
IMPEDING CONSTRUCTION ACTIVITY NEAR THEIR PROPERTIES. THE
NOTIFICATION SHOULD BE VIA U.S. POSTAL CERTIFIED MAIL,
SIGNED RETURN RECEIVED REQUEST. THIS CONCERN MUST BE
ADDRESSED PRIOR TO PLAN APPROVAL PER TENTATIVE CONDITION
#16.INCLUDE AN 8½ X 11 COPY OF THE PROPOSED CONSTRUCTION
ACTIVITY ADJACENT TO THEIR PROPERTIES.
6. PER TENTATIVE CONDITION #11, WHICH STATES, "APPROVAL OF
THE ROAD AND DRAINAGE PLANS BY DOMINION VIRGINIA POWER IN
RELATION TO ITS EASEMENT AND FACILITIES THEREIN IS A
PREREQUISITE TO CONSTRUCTION PLAN APPROVAL BY THE
ENVIRONMENTAL ENGINEERING DEPARTMENT. A QUITCLAIM TO VDOT
OR A SATISFACTORY COMMITMENT THEREOF BY DOMINION VIRGINIA
POWER FOR THE LOCATIONS WHERE CENTRALIA STATION ROAD,
RIGHT-OF-WAY WILL CROSS THE DOMINION VIRGINIA POWER
EASEMENT SHALL BE A PREREQUISITE TO SUBDIVISION PLAT
RECORDATION."
7. PLEASE SHOW DIMENSIONING BUILDING ENVELOPES ON LOTS 27,
43, 44, 47, ETC.
8. PLEASE DEPICT ON THE PLANS THE EXISTING POWERLINE
POLE(S) THAT RUN PARALLEL TO CENTRALIA ROAD WITHIN THE
LIMITS OF THIS PROJECT ON THE PLANS AND PROVIDE A NOTE THAT
THESE EXISTING POLES WOULD BE RELOCATED AS SHOWN ON THE
PLANS.
IN ADDITION, CLEARLY SHOW/LABEL THE NEW LOCATIONS OF THESE
POWERLINE POLES ON THE PLANS WITH PERTINENT INFORMATION.
REFLECT THE CHANGES ON THE EC PLANS AND LAYOUT PLANS.
9. IT APPEARS A CG-9 DRIVEWAY ENTRANCE TO THE EXISTING
DRIVE ON TAYLOR'S PROPERTY SHOULD BE PROVIDED. REFLECT THE
CHANGES ON ALL APPLICABLE SHEETS.
10. PLEASE PROVIDE SIDEWALK DETAIL ON THE PLANS.
11. PLEASE CLARIFY IF THE EXISTING CENTRALIA STATION STREET
RIGHT-OF-WAY WOULD REMAIN ON LOT 1.
IN ADDITION, IF THIS EXISTING R/W IS GOING TO BE VACATED AND
BE PART OF LOT 1, IT SHOULD BE CLEARLY INDICATED ON THE
PLANS WITH APPROPRIATE NOTES. PLEASE ADDRESS.
FURTHERMORE, AS APPLICABLE, PROVIDE A NOTE FOR THE REMOVAL
OF THE EXISTING ROAD AND PROVIDE PROPOSED GRADING TO CREATE
POSITIVE DRAINAGE. PERHAPS A SWALE SHOULD BE PROVIDED NEAR
THE LIMITS OF THE PROPERTY LINE PERTINENT TO LOT 1 OR WITHIN
THE 16' DRAINAGE EASEMENT PERTINENT TO STRUCTURES 5/6 AND
CONTINUE THIS SWALE UNTIL REACHES THE PROPOSED ROAD
(CENTRALIA STATION ROAD). A DI-6 AND DI-3 WITH REAR SLOT
OPENING SHOULD BE CONSIDERED TO INTERCEPT THIS PROPOSED
SWALE. A FURTHER DISCUSSION IS RECOMMENDED. REFLECT THE
CHANGES ON ALL APPLICABLE SHEETS.
12. PER CHESTERFIELD COUNTY ATTORNEY RESOLUTION EMAIL DATED
01/14/16 REGARDING IF THIS PROJECT COULD BE WAIVED TO
DISREGARD THE LATEST RPA ASSESSMENT CONFIRMED IN 2012. THE
COUNTY ATTORNEY HAS CONFIRMED THAT THIS PROJECT WOULD NOT BE
VESTED UNDER MCELFISH POLICY AND THE PLANS SHOULD REFLECT
THE LATEST RPA ASSESSMENT DATED 2012.
THEREFORE, REVISE THE PLANS TO ESTABLISH THE LIMITS OF THE
RPA ALONG THE WETLAND AREA LOCATED IN THE VICINITY OF LOTS
11/12, 50 THRU 52, 56 THRU 62, 66 THRU 68. REFER TO THE 2012
RPAD ASSESSMENT.
AS A RESULT, SOME LOTS WITHIN THE RPA AREA MAY BE ELIMINATED
(I.E. LOTS 12, 51, 60, 61, ETC.) AND THE WORKSHEET A
CALCULATIONS SHOULD BE SUBMITTED FOR FURTHER REVIEW AND/OR
APPROVAL. REFLECT THE CHANGES ON ALL APPLICABLE SHEETS.
IN ADDITION, SHOW/LABEL THE 25' BUILDING SETBACK OFF THE RPA
LIMITS ON LOTS 50, 51, 56, 62,66 THRU 69 AND SHOW THE
BUILDABLE LOT AREA ON LOTS 51, 59, 67 THRU 69, ETC. ON THE
PLANS.
ADDITIONALLY, SHOW/LABEL ALONG THE RPA LIMITS THE TYPICAL
RPA SIGN AT MINIMUM EVERY OTHER LOT.
13. PLEASE CORRECT THE LOT NUMBERING, IT APPEARS NUMBER 53
HAS BEEN SHOWN TWICE. REVISE ALL APPLICABLE SHEETS TO
REFLECT THE CHANGES.
14. THESE ARE IN REGARDS TO THE EMERGENCY ACCESS ROAD:
A) PLEASE PROVIDE A ROAD DESIGN PAVEMENT/TYPICAL ROADWAY
SECTION/SHOULDER WIDTH/ETC. FOR THE EMERGENCY ACCESS ROAD ON
THE PLANS.
B) BE SURE TO SHOW THE PROPOSED ROAD WITH STIPPLE
PATTERN ON ALL APPLICABLE SHEETS.
C) PLEASE PROVIDE CG-9 DRIVEWAY ENTRANCE TO ACCESS THE
EMERGENCY ACCESS FROM CENTRALIA STATION ROAD AND PROVIDE
DRIVEWAY ENTRANCE STANDARD DETAIL TO ACCESS THE EMERGENCY
ACCESS ROAD FROM CHIPPOKE ROAD.
IN ADDITION, SHOW/LABEL PROPOSED GATE AT THE ENTRANCE FROM
CHIPPOKE ROAD.
D) PLEASE PROVIDE GATE DETAIL ON THE PLANS.
E) A PROFILE OF THIS EMERGENCY ACCESS ROAD WITH
APPLICABLE ROAD DESIGN DATA SHOULD BE PROVIDED ON THE PLANS.
BE SURE STATIONING CENTERLINE PROFILE AGREES WITH STATIONS
SHOWN ON THE PLANS.
F) BASED ON A FIELD INSPECTION A TOE DITCH ALONG
EMERGENCY ACCESS ROAD SHOULD BE PROVIDED ON THE WESTERN SIDE
OF THIS ROAD. THIS DITCH SHOULD CONTINUE BEHIND LOT 32 THRU
34 AND EXTEND THE 16' DRAINAGE EASEMENT TO INCLUDE A PORTION
OF THIS DITCH BEHIND LOTS 32 THRU 33.
BE SURE TO PROVIDE THE RADIUS AT THE TURN(S) OF THIS
PROPOSED DITCH.
IN ADDITION, INCLUDE 10/100-YEAR DITCH CALCULATIONS, PROFILE
OF THIS DITCH WITH PERTINENT INFORMATION (I.E. TYPICAL DITCH
SECTION, LINING, %SLOPE, DEPTH, ETC.) ON THE PLANS.
G) PROVIDE 10-YEAR ENTRANCE CULVERT WITH SUPPORT
CALCULATIONS ON STANDARD VDOT FORM. BE SURE 10-YEAR HW/D<1.
IN ADDITION, REFLECT THIS INFORMATION ON THE PLANS.
H) SHOW/LABEL THE EXISTING AND PROPOSED CONTOURS WITH
ELEVATIONS. BE SURE TO INCLUDE ENOUGH AREA OF THE CONTOURED
TOPOGRAPHY TO VERIFY DRAINAGE BREAKS/DRAINAGE PATTERN
ONSITE/OFFSITE.
I) PLEASE LABEL THE RECORDED EASEMENT ALONG THE PROPOSED
EMERGENCY ACCESS ROAD AS, "PB:208 PG:87 DRAINAGE, UTILITY
AND EMERGENCY ACCESS EASEMENT AREA=0.375 AC."
15. PLEASE REVISE THE DRAINAGE STRUCTURE SUMMARY TABLE
(SHEET C-20) TO SPECIFY THE SLOT OPENING ORIENTATION (I.E.
N, E, S, W) WITH MINIMUM 2' CONCRETE GUTTER AT STRUCTURES 1,
7, 9, 17, 70, 79, 107, 112, 125, ETC.
IN ADDITION, IT APPEARS SOME STRUCTURES HAVE BEEN DESIGNATED
AS #REF IN THE DRAINAGE STRUCTURE SUMMARY (SHEET C-20).
PLEASE CLARIFY OR REVISE ACCORDINGLY TO ELIMINATE ANY TYPO
FROM TABLE.
16. PRECAST MANHOLE TEE'S AND ELBOWS ARE REQUIRED WHERE PIPE
DIAMETERS ARE GREATER THAN OR EQUAL TO 30" AND SHALL
QUALIFY FOR 50% REDUCTION IN JUNCTION LOSSES. PLEASE
SPECIFY AT THOSE APPLICABLE STRUCTURES TO BE PRECAST IN THE
DRAINAGE STRUCTURE TABLE (SHEET C-20).
17. PLEASE CLARIFY THE SYMBOLS SHOW ALONG THE OVERHEAD POWER
LINE ARE POLES OR TOWERS. BE SURE TO LABEL THIS FEATURE
ACCORDINGLY ON THE PLANS AND SHOW THIS FEATURE POLES OR
TOWERS ON ALL APPLICABLE SHEETS (I.E. SHEETS C-27, C-37B,
ETC.).
18. PLEASE REMOVE THE ROAD NAME FOR THE STUB ROAD OF
CALLISTO LANE. IN ADDITION, PROVIDE 10' TEMPORARY
CONSTRUCTION EASEMENT(S) ALONG BOTH SIDES OF THE STUB ROAD
RIGHT-OF-WAY. REFLECT THE CHANGES ON ALL APPLICABLE VIEWS.
19. THESE ARE IN REGARDS TO THE HYDRAULIC ANALYSIS (SHEETS
C-25 THRU C-29):
A) PLEASE REVISE THE RUNOFF COEFFICIENT PERTINENT TO
DRAINAGE AREAS 7, 13, 17, 19, ETC. TO BE AROUND 0.50 AS
THESE AREAS ARE ZONED R-7. REVISE THE PLANS, 10/100-YEAR
STORM SEWER/HGL CALCULATIONS, ETC. TO REFLECT THE CHANGES.
IN ADDITION, PLEASE DEPICT ON THE PLANS AND/OR IN THE
DRAINAGE TABLE THE INCREMENTAL DRAINAGE AREAS WITH NUMBER
ACRES PERTINENT TO DA 13, 17, ETC. REVISE ACCORDINGLY.
B) PLEASE SHOW/LABEL CENTERLINE STATIONING AT EVERY 100'
ALONG THE PROPOSED ROADS. REFLECT THE CHANGES ALL APPLICABLE
SHEETS (I.E. SHEETS C-25 THRU C-29).
C) PLEASE PROVIDE DRAINAGE AREA/RUNOFF COEFFICIENT TABLE
ON EACH SHEET OR SPECIFY ON THE PLAN VIEWS THE INCREMENTAL
DRAINAGE AREA IN ACREAGE/RUNOFF COEFFICIENT FOR EACH
STRUCTURES.
D) PLEASE REVISE THE LIMITS OF DRAINAGE AREAS PERTINENT
TO DA-41/DA-43/DA-48/DA-50/ETC. TO INCLUDE THE DRAINAGE
BREAKS IN THE PROXIMITY OF 170.00 CONTOUR-ELEVATION. REFER
TO THE OVERALL HYDRAULIC ANALYSIS (SHEET C-29). A FURTHER
DISCUSSION IS RECOMMENDED. REVISE THE PLANS, PROFILES AND
COMPUTATION SHEETS TO REFLECT THE CHANGES.
E) PLEASE BE SURE TO SHOW THE EXISTING CONTOURED GRADING
WITH ELEVATIONS WITHIN THE TUNSTALL, J. AND JENKINS
PROPERTIES (SHEET C-25).
F) PLEASE IDENTIFY THE LINES WITH ARROWS <-<-<- THAT IS
GOING ALONG THE MATCHING LINE SHEETS 26/27 (SHEET C-27) AND
THEN TURNS TO CROSS THE OFFSITE LOTS OF WELLINGTON FARMS.
REVISE AS APPLICABLE.
G) PLEASE LABEL THE EXISTING LOTS WITH NUMBERS (I.E. 18
THRU 22) PERTINENT TO WELLINGTON FARMS SECTION E.
H) PLEASE REVISE THE LABELING OF DA-95 THAT IS SHOWING
IN THE PROXIMITY OF LOT 17 (SHEET C-27) TO BE DA-99. IN
ADDITION, REVISE THE RUNOFF COEFFICIENT TO USE AROUND 0.45
OR HIGHER TO CONSIDER THE ROAD. REVISE THE PLANS, PROFILES
AND COMPUTATION SHEETS TO REFLECT THE CHANGES.
I) PLEASE REVISE THE RUNOFF COEFFICIENT AT STRUCTURES
25, 27, ETC. TO USE A HIGHER RUNOFF IN THE RANGE OF 0.40 TO
0.45. REVISE THE PLANS, PROFILES AND COMPUTATION SHEETS TO
REFLECT THE CHANGES.
20. THESE ARE IN REGARDS TO THE 100-YEAR STORM SEWER/HGL
CALCULATIONS:
A) IT APPEARS THE 100-YEAR STORM IS ESCAPING ON SEVERAL
STRUCTURES (I.E. 9/17/31/37/48/50/52/56/58/70/103/105/107/
115/117/ETC. PLEASE CONSIDER, BUT NOT LIMITED, TO THE
FOLLOWING:
A.1) PLEASE PROVIDE AN OVERFLOW GRASS SWALE WITHIN
THE 16' DRAINAGE EASEMENT BETWEEN LOTS 73/74. THIS WOULD
ADDRESS RUNOFF ESCAPING FROM STRUCTURES 56/58, WHICH
ULTIMATELY THE RUNOFF SURCHARGE WOULD DRAIN TO THE ROAD SAG
AND THEN TO THE OVERFLOW SWALE.
IN ADDITION, LABEL THIS 5:1 SIDE SLOPES GRASS SWALE ON THE
PLANS AS "100-YEAR OVERFLOW GRASS SWALE." REFLECT THE
CHANGES ON ALL APPLICABLE SHEETS.
A.2) THE 100-YEAR STORM APPEARS TO ESCAPE AT
STRUCTURES 48/50/52. PLEASE ESTABLISH THE 100-YEAR OVERFLOW
LIMITS IN THE PROXIMITY OF LOT 82 FOR PROPERTY PROTECTION.
SPECIFY MFF AND 25' BUILDING SETBACK OF THE 100-YEAR
OVERFLOW LIMITS. OR CONSIDER INCREASING THE PIPE SIZE.
REVISE ALL APPLICABLE SHEETS TO REFLECT THE CHANGES.
A.3) SIMILARLY, THE 100-YEAR STORM IS ESCAPING AT
STRUCTURES 17/27. IT APPEARS THE 100-YEAR SURCHARGE POST-
DEVELOPED WOULD EXCEED THE 100-YEAR PRE-DEVELOPED FLOW AT
THE POINT OF ANALYSIS/STR. 27, SINCE IS DIVERTING/CARRYING
ADDITIONAL 19.80 ACRES.
AS A RESULT, PLEASE PROVIDE A COMPREHENSIVE ANALYSIS TO SHOW
THE 100-YEAR OVERFLOW LIMITS AND EXPLORE THE POSSIBILITY OF
AN ADEQUATE CONVEYANCE CHANNEL DOWNSTREAM OF STR. 23 TO
CARRY THE ADDITIONAL FLOW. OTHERWISE THE SIZE OF THE PIPE
SHOULD BE INCREASED TO ENSURE THE 100-YEAR WOULD STAY WITHIN
THE SYSTEM. A FURTHER DISCUSSION IS RECOMMENDED.
21. PLEASE PROVIDE LOT FILLING AND GRADING ON LOT 74 TO
ELIMINATE THE NATURAL LOW IN THE VICINITY OF 125.00 CONTOUR-
ELEVATION.
IN ADDITION, BASED ON THE PROPOSED GRADING LOTS 74 AND 75
SHOULD SPECIFY MINIMUM CRAWL SPACE. PLEASE ANNOTATE THESE
LOTS WITH MCS. REFLECT THE CHANGES ON ALL APPLICABLE SHEETS.
ADDITIONALLY, SPECIFY A GRASS SWALE BETWEEN LOTS 74/75 TO
SERVE AS SURFACE RELIEF AND EARMARK THESE LOTS WITH "NBP".
22. PLEASE SHOW/LABEL THE EXISTING CULVERT(S) ALONG THE
RAILROAD TRACK WITH PERTINENT INFORMATION (I.E. INVERTS,
MATERIAL, DIAMETER, LENGTH, ETC.) ON ALL APPLICABLE SHEETS.
ADDITIONAL EROSION CONTROL MEASURES MAY BE NEEDED.
IN ADDITION, THIS OFFICE WAS NOT ABLE TO LOCATE THE 10/100-
YEAR CULVERT CALCULATIONS PERTINENT TO THESE EXISTING
CULVERTS WITHIN THE SUBMITTAL PACKAGE. PLEASE ADDRESS.
FURTHERMORE, PLEASE SHOW/LABEL THE APPROVED 100-YEAR FEMA
BACKWATER LIMITS/ELEVATION ON THE UPSTREAM SIDE OF THE
EXISTING CULVERT UNDER THE RAILROAD TRACK WHERE GREAT BRANCH
CREEK DRAINS TO. INCLUDE PERTINENT INFORMATION OF THIS
CULVERT ON THE PLANS (I.E. INVERTS, DIAMETER, MATERIAL,
LENGTH, ETC.). REFLECT THE CHANGES ON ALL APPLICABLE SHEETS.
22. SIMILARLY THIS OFFICE WAS NOT ABLE TO LOCATE THE 10/100-
YEAR CULVERT CALCULATIONS AT STRUCTURES 39/41/90/ETC. FOR
FURTHER REVIEW AND/OR APPROVAL. PLEASE ADDRESS.
23. PLEASE PROVIDE THE MINIMUM FINISH FLOOR (MFF)
DESIGNATION SUCH AS: FLOODPLAIN (FP), BACKWATER (BW), ROAD
SAG (SAG), ETC. TO ALL THE LOTS WHERE MFF HAS BEEN
SPECIFIED.
IN ADDITION, PLEASE REMOVE THE MFF ON LOTS 57 THRU 59, 67
THRU 69, SINCE THE 100-YEAR FLOODPLAIN LIMITS DO NOT
ENCROACH INTO THESE LOTS.
24. PLEASE REVISE THE MFF ON LOT 3. IT APPEARS THE ROAD SAG
IS MOST RESTRICTIVE OF 139.80. MFF SHOULD BE ESTABLISHED 1'
ABOVE THE ROAD SAG OF MFF(SAG)=140.80. REFLECT THE CHANGES
ON ALL APPLICABLE SHEETS.
25. A SIMILAR SITUATION EXISTS ON LOTS 11 AND 12. MFF SHOULD
BE BASED ON THE ROAD SAG [MFF(SAG)=135.90]. REVISE
ACCORDINGLY.
26. IT APPEARS PROVIDING A DI-6 AT STR. 17 WOULD CREATE A
HIGHER BACKWATER THAN PROVIDING A PIPE/HEADWALL ENTRANCE.
PLEASE SUBMIT SUPPORT 10/100-YEAR CALCULATIONS TO ENSURE THE
HEAD ELEVATION DURING THE 10-YEAR STORM DOES NOT EXCEED AN
ELEVATION THAT IS 18" BELOW THE EDGE OF THE ROAD SHOULDER.
IN ADDITION, PLEASE ESTABLISH THE 100-YEAR FLOODPLAIN ON THE
UPSTREAM SIDE OF STR. 17 TO VERIFY THAT THE 100-YEAR
BACKWATER ELEVATION IS AT OR BELOW THE 100-YEAR FLOODPLAIN.
PROVIDE HYDROLOGIC/HYDRAULIC CALCULATIONS, SCALED X-SECTIONS
AND SHOW/LABEL THE 100-YEAR FLOODPLAIN SECTIONS-LOCATIONS
WITH ELEVATIONS ON THE PLANS. REFLECT THE CHANGES ON THE EC
PLANS, ROAD PLANS, GRADING PLANS, HYDRAULIC ANALYSIS PLANS,
ETC.
IF THE 100-YEAR BACKWATER AT STR. 17 IS HIGHER THAN THE 100-
YEAR FLOODPLAIN, 100-YEAR BACKWATER EASEMENT SHOULD BE
RECORDED. A FURTHER DISCUSSION IS RECOMMENDED.
FURTHERMORE, PLEASE EXTEND THE 16' DRAINAGE EASEMENT THAT IS
ENCLOSING STRUCTURE 17 TO THE PROPERTY LINE WITH TEMPORARY
CONSTRUCTION EASEMENT. REFLECT THE CHANGES ON ALL APPLICABLE
SHEETS.
27. PLEASE PROVIDE SCALED X-SECTIONS OF THE PROPOSED ROAD
PERTINENT TO CENTRALIA STATION ROAD BETWEEN STATIONS 14+50
TO 22+00. INCLUDE, THE PROPOSED GRADE TYING BACK TO THE
EXISTING GRADE, CLEARLY LABEL THE RIGHT-OF-WAY LIMITS,
PROPERTY LINE, ETC. TO VERIFY IF TEMPORARY CONSTRUCTION
EASEMENT MAY BE REQUIRED.
28. PLEASE BE SURE TO SPECIFY EC-1 RIPRAP AT THE BEGINNING
OF STRUCTURES 39, 41, 90, ETC. AND INCLUDE DIMENSIONS OF
THIS PROPOSED EC-1 RIPRAP (I.E. WIDTH, LENGTH AND 24" THICK
LAYER OF RIPRAP OVER FILTER FABRIC) ON THE PLANS AND
PROFILES. IN ADDITION, BE SURE THAT THIS EC-1 RIPRAP IS
INCLUDED IN THE VARIABLE WIDTH SLOPE & DRAINAGE EASEMENT FOR
VDOT MAINTENANCE.
29. PLEASE SPECIFY OUTLET PROTECTION AT THE OUTFALL PIPE
STR. 37 AND INCLUDE DIMENSIONS OF THIS OUTLET PROTECTION ON
THE PLANS AND PROFILES.
30. IT APPEARS THE PROPOSED DITCH SPECIFIED ON THE REAR OF
LOTS 42 THRU 76 WOULD NOT BE NEEDED, SINCE BMP#3 WOULD NO
LONGER REQUIRE IT. AS APPLICABLE, REVISE THE PLANS, PROFILES
AND COMPUTATION SHEETS TO REFLECT THE CHANGES.
31. PLEASE REVISE THE LABELING OF THE PROPOSED EASEMENT(S)
ENCLOSING PART OF THE FILL SLOPE AND STRUCTURES 39/40,
41/46, 90/92, ETC. IN A VARIABLE WIDTH SLOPE AND DRAINAGE
EASEMENT FOR VDOT MAINTENANCE. REFLECT THE CHANGES ON ALL
APPLICABLE SHEETS.
32. PLEASE LABEL THE EASEMENT THAT IS ENCLOSING STRUCTURES
29 THRU 31/52 THRU 54/103 THRU 105/111 THRU 119/117 THRU
119/ETC. AS VARIABLE WIDTH DRAINAGE EASEMENT FOR VDOT
MAINTENANCE. REFLECT THE CHANGES ON ALL APPLICABLE SHEETS.
33. PLEASE ENCLOSE STRUCTURES 107 IN A 16' DRAINAGE
EASEMENT.
34. PLEASE ENCLOSE THE PROPOSED DITCH AND STRUCTURES 125
THRU 127 IN A 16' DRAINAGE EASEMENT.
IN ADDITION, INCLUDE A PROFILE OF THIS PROPOSED DITCH WITH
PERTINENT INFORMATION (I.E. TYPICAL DITCH, 10-YEAR DESIGN
DEPTH, LINING, ETC.) AND SUBMIT 10/100-YEAR DITCH
CALCULATIONS FOR FURTHER REVIEW AND/OR APPROVAL.
FURTHERMORE, THIS PROPOSED DITCH SHOULD BE PAVED (PG-2A) FOR
THE PORTION RELATIVE TO THE HOME SITE. A FURTHER DISCUSSION
IS RECOMMENDED.
35. PLEASE PROVIDE A DITCH OF 3:1 SIDE SLOPES TO BE LOCATED
ON THE REAR OF LOTS 19 THRU 23 AS OPPOSED TO GRASS SWALE. IN
ADDITION, RELOCATE STR. 97 TO INTERCEPT THIS DITCH. A
MODIFIED DI-3 WITH BACK OPENING MIN. 2' CONCRETE SLOT SHOULD
BE SPECIFIED AT STR. 97 AND INCLUDE A DETAIL OF THIS
MODIFIED DI-3 WITH BACK OPENING ON THE PLANS.
BE SURE TO ENCLOSE THIS DITCH IMPROVEMENT IN A 16' DRAINAGE
EASEMENT. REFLECT THE CHANGES ON ALL APPLICABLE SHEETS.
IN ADDITION, INCLUDE 10/100-YEAR DITCH CALCULATIONS,
PROFILES, DITCH DESIGN INFORMATION, ETC. ON THE PLANS.
36. PLEASE ENCLOSE THE PROPOSED DITCH SPECIFIED ON THE REAR
OF LOTS 79 THRU 81 IN A 16' DRAINAGE EASEMENT. INCLUDE A
PROFILE OF THIS DITCH WITH PERTINENT DESIGN INFORMATION
(I.E. LINING, %SLOPE, DEPTH, ETC.) AND SUBMIT 10/100-YEAR
DITCH CALCULATIONS FOR FURTHER REVIEW AND/OR APPROVAL.
37. IN LIEU OF A MH AT STR. 76, PLEASE SPECIFY A DI-6 AND
PROVIDE A GRASS SWALE BETWEEN LOTS 68/69. REFLECT THE
CHANGES ON THE PLANS, PROFILES AND COMPUTATION SHEETS.
38. PLEASE SPECIFY A SWALE 5'OFF THE PROPERTY LINE ON THE
NORTHERN SIDE OF LOT 61 AND CONTINUE THIS SWALE IN A RADIUS
TURN TO CONTINUE ON THE REAR OF 61 5' OFF THE PROPERTY LINE
UNTIL IT REACHES STR. 72. REFLECT THE CHANGES ON ALL
APPLICABLE SHEETS.
39. PLEASE SPECIFY A GRASS SWALE 5' OFF THE PROPERTY LINE ON
THE NORTHERN SIDE OF LOT 11.
IN ADDITION, PROVIDE A NOTE IN BOLD PRINT STATING, "PROPOSED
SWALES SHOULD START AT GRADE, INCREASE IN DEPTH AND FLATTEN
THE SIDE SLOPES TO ENCOURAGE SHEET FLOW PRIOR REACHING THE
LIMITS RIGHT-OF-WAY, WETLANDS/OPEN SPACE." REFLECT THIS NOTE
ON ALL APPLICABLE SHEETS.
40. A GRASS SWALE SHOULD BE SPECIFIED ON THE REAR OF LOT 25
AND 5' OFF THE PROPERTY LINE AND CONTINUE THIS SWALE ON THE
WESTERN SIDE OF LOT 25 UNTIL REACHES THE LIMITS OF THE
RIGHT-OF-WAY.
FURTHERMORE, ANNOTATE LOT 25 WITH "NBP". REFLECT THE CHANGES
ON ALL APPLICABLE SHEETS.
41. PLEASE SPECIFY A GRASS SWALE TO START AT GRADE ON THE
REAR OF LOT 15 AND 5' OFF THE PROPERTY LINE AND CONTINUE
THIS SWALE ON A RADIUS TURN WITHIN LOT 15 UNTIL IT REACHES
LIMITS OF THE RIGHT-OF-WAY.
42. PLEASE ADD A NOTE IN BOLD PRINT STATING, "IF UNABLE
TO ACHIEVE SUITABLE STAND OF GRASS VEGETATION OR FAILS TO
PROVIDE POSITIVE DRAINAGE OR SECTIONS NOT MAINTAINED,
UP TO 1 YEAR AFTER THE STATE ACCEPTANCE OF THE ROAD EE
MAY REQUIRE THE DITCH TO BE PAVED (PG-2A)." ADD THIS NOTE
ON ALL APPLICABLE SHEETS (I.E. ROAD PLANS, GRADING PLANS, EC
PLANS, ETC.).
43. PLEASE PROVIDE LOT FILLING/GRADING ON LOTS 35/36, 33,
56, ETC. TO ELIMINATE THE LOW DEPRESSION WITHIN THE FUTURE
HOME SITE. IN ADDITION, ANNOTATE THESE LOTS WITH "NBP" AND
REFLECT THE CHANGES ON ALL APPLICABLE SHEETS.
44. THESE ARE IN REGARDS TO THE FLOODPLAIN ANALYSIS (SHEETS
C-37, C-37A, C-37B):
A) PLEASE REVISE THE BAR SCALE ON SHEET C-37, WHICH
APPEARS TO BE 1" = 200' AS OPPOSED TO 1" = 50'. REVISE
ACCORDINGLY.
B) PLEASE SHOW/LABEL ALL THE EXISTING CONTOURS WITH
ELEVATIONS AND BE SURE THE ELEVATIONS ARE LEGIBLE. REFLECT
THE CHANGES ON SHEETS C-37 THRU C-37B.
C) PLEASE SHOW THE CONTOURED TOPOGRAPHY WITHIN THE
OFFSITE DRAINAGE AREAS, WHICH HAVE BEEN OMITTED FROM THE
PLAN VIEWS (SHEETS C-37, C-37A, ETC.) TO VERIFY DRAINAGE
BREAKS.
D) PLEASE INCREASE THE LETTER SIZE PERTINENT TO DRAINAGE
AREAS/RUNOFF COEFFICIENTS/FLOODPLAIN SECTION-LOCATIONS 1
THRU 25 ON SHEET C-37 TO BE MORE LEGIBLE, WHICH IS VERY HARD
TO BE READ ON THE PLANS.
E) PLEASE REVISE X-SECTION 17 TO USE THE APPROVED
ACCUMULATED C X A OF 27.60, Q100=172.50 CFS FOR THE OFFSITE
DRAINAGE AREAS PLUS THE ADDITIONAL INCREMENTAL DRAINAGE AREA
FROM ONSITE.
F) PLEASE LABEL THE PROPOSED LOTS WITH NUMBERS (SHEETS
C-37 THRU C-37B).
G) PLEASE REVISE THE RUNOFF COEFFICIENT(S) AT X-SECTIONS
1 THRU 25 TO USE A HIGHER AVERAGE RUNOFF COEFFICIENT FOR
ULTIMATE DEVELOPED CONDITIONS (I.E. LOT AREA R-9 C=0.45, 1.5
ACRE/LOT C=0.25 OR SOIL GROUP C=0.30, NATURAL WOODED AREA
UNDISTURBED C=0.25 OR SOIL GROUP C=0.30, GRADED AREAS
C=0.35, ETC.). SUBMIT REVISED CALCULATIONS AND REFLECT THE
CHANGES ON ALL APPLICABLE SHEETS.
H) THIS OFFICE WAS NOT ABLE TO LOCATE THE 100-YEAR
FLOODPLAIN SCALED X-SECTIONS PERTINENT TO X-SECTIONS 1 THRU
25 WITHIN THE SUBMITTAL PACKAGE TO VERIFY THE INPUT DATA
(I.E. DISCHARGE, MANNING ROUGHNESS COEFFICIENT, SLOPE,
ETC.). PLEASE ADDRESS.
I) PLEASE SHOW/LABEL THE 100-YEAR FLOODPLAIN SECTIONS-
LOCATIONS WITH ELEVATIONS ON SHEETS C-13 THRU C-15, C-17
THRU C-19, ETC.).
J) PLEASE PROVIDE THE 100-YEAR FLOODPLAIN TABLE ON
SHEETS 37A AND 37B.
45. THESE ARE IN REGARDS TO THE 100-YEAR FEMA FLOODPLAIN:
A) PLEASE SHOW THE 100-YEAR FEMA FLOODPLAIN SECTIONS-
LOCATIONS WITH ELEVATIONS ALONG THE GREAT BRANCH CREEK.
B) PLEASE REVISE THE LABELING OF 100-YEAR FLOODPLAIN
ALONG THE GREAT BRANCH CREEK TO BE "100-YEAR FEMA
FLOODPLAIN". REFLECT THE CHANGES ON ALL APPLICABLE SHEETS.
C) PLEASE INCORPORATE THE WORDING "FEMA" WITHIN THE
LIMITS OF THE 100-YEAR FEMA FLOODPLAIN. REFLECT THE CHANGES
ON ALL APPLICABLE SHEETS.
D) BE SURE TO LABEL THE GREAT BRANCH CREEK ALONG THE
CENTERLINE OF THIS CREEK. IN ADDITION, INDICATE WITH ARROWS
THE DIRECTION OF FLOW ALONG THE FLOWLINE OF THIS CREEK AND
NATURAL DRAINAGEWAY/WETLAND AREAS. REFLECT THE CHANGES ON
ALL APPLICABLE SHEETS.
E) PLEASE PROVIDE AN ASTERISK ON LOTS AFFECTED BY THE
100-YEAR FEMA FLOODPLAIN (I.E. LOTS 37 THRU 48, ETC.) AND
PROVIDE A NOTE STATING, "ELEVATION CERTIFICATE(S) ARE
REQUIRED PRIOR TO THE CERTIFICATES OF OCCUPANCY (CO).
REFLECT THIS NOTE ON ALL APPLICABLE SHEETS.
46. THESE ARE IN REGARDS TO THE 100-YEAR DAM FAILURE:
A) THIS OFFICE WAS NOT ABLE TO LOCATE THE 100-YEAR DAM
FAILURE ANALYSIS. ONLY THE SCALED X-SECTIONS AND CULVERT
ANALYSIS WERE PROVIDED. PLEASE SUBMIT SUPPORT CALCULATIONS
FOR FURTHER REVIEW AND/OR APPROVAL.
B) PLEASE SHOW/LABEL THE 100-YEAR DAM FAILURE SECTIONS-
LOCATIONS WITH ELEVATIONS ON THE PLANS (SHEETS C-13, C-17,
C-25, ETC.).
C) BASED ON THE CULVERT ANALYSIS, IT APPEARS THE 100-
YEAR DAM FAILURE OVERTOPS THE ROAD. PLEASE SHOW THE LIMITS
OF THE 100-YEAR DAM FAILURE OVERTOPPING THE ROAD. REFLECT
THE CHANGES ON ALL APPLICABLE SHEETS.
D) THIS OFFICE MUST RECEIVE A LETTER FROM A LICENSE
PROFESSIONAL ENGINEER CERTIFYING THE ANALYSIS.
47. PLEASE REVISE THE DI-6A DETAIL (SHEET C-10) TO SPECIFY
MIN. 2' CONCRETE GUTTER AS OPPOSED TO 8'-0" CONCRETE
GUTTER.
48. PLEASE PROVIDE A DETAIL OF THE MODIFIED DI-3B WITH
OPENING IN THE BACK ON THE PLANS.
49. PLEASE PROVIDE ONE STREETLIGHT PER MAIN INTERSECTION TO
BE COUNTY STREETLIGHT. REVISE ACCORDINGLY.
50. THESE ARE IN REGARDS TO THE PROFILES:
A) PLEASE BE SURE TO SHOW/LABEL THE 100-YEAR FLOODPLAIN,
100-YEAR BACKWATER, ROW, WETLANDS LIMITS, RPA LIMITS,
ETC. ON ALL PROFILES.
B) PLEASE REVISE STORM 31-37 PROFILE (SHEET C-34) TO
SHOW COVER OVER THE OUTFALL PIPE STR. 36 AND SPECIFY OUTLET
PROTECTION AT 0% SLOPE WITH PERTINENT INFORMATION (I.E.
WIDTH, LENGTH AND 24" THICK LAYER OF RIPRAP OVER FILTER
FABRIC) ON THE DOWNSTREAM SIDE OF STR. 36. REFLECT THE
CHANGES ON THE PLAN VIEWS AND PROFILES.
IN ADDITION, EXTEND THE PROFILE ON THE DOWNSTREAM SIDE OF
STR. 36 TO VERIFY THAT THE DRAINAGE IMPROVEMENTS ARE ENDING
INTO AN ADEQUATE RECEIVING CHANNEL.
C) PLEASE REVISE STORM 15-19 PROFILE (SHEET C-34) TO
SHOW THE PROPOSED GRADING TYING BACK TO THE EXISTING GROUND
AT STRUCTURES 15 AND 17. IN ADDITION, SHOW/LABEL THE LIMITS
OF THE PROPERTY LINE, RIGHT-OF-WAY, 100-YEAR BACKWATER, ETC.
ON THIS PROFILE.
D) PLEASE REVISE STORM 38-40 PROFILE AND STORM 41-47
PROFILE (SHEET C-34) TO SHOW EC-1 RIPRAP AT THE BEGINNING OF
STRUCTURES 38/41 AND THE OUTLET PROTECTION ON THE DOWNSTREAM
SIDE OF STRUCTURES 40/47 AT 0% SLOPE WITH PERTINENT
INFORMATION. BE SURE TO SHOW THE PROPOSED GRADE TYING BACK
TO THE EXISTING GROUND.
IN ADDITION, SHOW/LABEL THE LIMITS OF: THE 100-YEAR
BACKWATER, 100-YEAR FLOODPLAIN, RIGH-OF-WAY, WETLANDS, ETC.
ON THESE PROFILES.
E) PLEASE REVISE CENTRALIA STATION COVE PROFILE (SHEET
C-32) TO INCLUDE THE CURB & GUTTER AT THE END OF ROAD AND
PROPOSED GRADE TYING BACK TO THE EXISTING GROUND.
F) A SIMILAR SITUATION EXISTS WITH GANYMEDE DRIVE
PROFILE, GANYMDE COURT PROFILE, ETC. (SHEET C-32) TO SHOW
THE CURB & GUTTER AT THE END OF THE ROAD CONSTRUCTION AND BE
SURE TO SHOW PROPOSED GRADE TYING BACK TO THE EXISTING
GROUND. REVISE ACCORDINGLY.
G) PLEASE REVISE THE CENTRALIA STATION ROAD PROFILE
(SHEET C-30) TO SHOW/LABEL STREET INTERSECTION (I.E.
CENTRALIA ROAD) WITH PERTINENT STATIONING AND LABEL THE
BEGINNING OF CONSTRUCTION/STATIONS ON THIS PROFILE.
51. AS A PREREQUISITE TO SUBDIVISION PLAT RECORDATION:
A) THE $100/LOT BMP MAINTENANCE FEE MUST BE RECEIVED.
B) APPROVED BONDING AND RECORDED EASEMENTS WITH DEED
BOOK AND PAGE NUMBER FOR THE SWM/BMP WETPOND MUST BE
PROVIDED.
C) A QUITCLAIM TO VDOT OR A SATISFACTORY COMMITMENT
THEREOF BY DOMINION VIRGINIA POWER FOR THE LOCATIONS WHERE
CENTRALIA STATION ROAD, RIGHT-F-WAY WILL CROSS THE DOMINION
VIRGINIA POWER EASEMENT SHALL BE A PREREQUISITE TO
SUBDIVISION PLAT RECORDATION. REFER TO TENTATIVE CONDITION
#11.
==================== END OF COMMENTS =======================
============================================================
============================================================
REVIEW DEPARTMENT : ENVIRONMENTAL ENGINEERING
REVIEWER/PHONE # : MARIA JENKINS/751-2335
NAME OF PLAN : CENTRALIA STATION
SITE PLAN NO. : 16CP0051
LATEST PLAN DATE : 02/26/16
DEPT. REC'D DATE : 02/29/16
SUBMITTAL NUMBER : 2
REVIEW DATE : 03/21/16
RECOMMENDATION : REVISIONS REQUIRED
TABLE REVISION : NO
PLAT PROCESSING : NO
1. IT IS THE RESPONSIBILITY OF THE APPLICANT TO COMPLY
WITH AND/OR ACQUIRE ALL APPLICABLE FEDERAL AND/OR STATE
PERMITS IN RELATIONSHIP TO ENVIRONMENTAL FEATURES INCLUDING
BUT NOT LIMITED TO WETLANDS, SURFACE WATERS (E.G. VSMP
PERMIT FOR CONSTRUCTION SITES, GROUND WATER AND AIR
QUALITY) FINAL APPROVAL OF THESE PLANS WILL NOT RELIEVE YOU
OF YOUR RESPONSIBILITY. WETLANDS DOCUMENTATION MUST BE
RECEIVED BY THIS DEPARTMENT PRIOR TO ISSUANCE OF THE LAND
DISTURBANCE PERMIT.
2. THIS OFFICE RECOGNIZES THAT THE 10-YEAR PRE/10-YEAR POST
REQUIREMENTS FOR FLOOD PROTECTION MAY BE ADDRESSED BY
DISCHARGING INTO THE 100-YEAR FLOODPLAIN.
=== EROSION CONTROL ===
1. AN ITEMIZED EROSION CONTROL COST ESTIMATE MUST BE
SUBMITED FOR REVIEW AND/OR APPROVAL.
2. AS A PREREQUISITE TO THE ISSUANCE OF A LAND
DISTURBANCE PERMIT:
A) A COPY OF THE AUTOCAD FILE MUST BE SUBMITTED TO
CAROLE CLIBORNE OF THE ENVIRONMENTAL ENGINEERING. THE
AUTOCAD FILE MUST BE SAVED AS A .DWG OR .DXF IN AUTOCAD
VERSION 2009 OR EARLIER AND REFERENCED DIRECTLY TO THE
VIRGINIA STATE PLANE COORDINATE SYSTEM, SOUTH ZONE IN
THE NAD83 DATUM. THE AUTOCAD FILE MAY BE SUBMITTED ON A
CD, DVD, OR VIA EMAIL AND MUST BE CLEARLY LABELED WITH
THE SUBDIVISION NAME AND SECTION, SUBDIVISION PLAN
NUMBER, ENGINEERING FIRM AND CAD FILE PREPARER'S NAME
AND PHONE NUMBER. THE FILE MUST CONTAIN THE FOLLOWING,
EACH CLEARLY LABELED IN SEPARATE LAYERS:
EDGES OF ROADS TO INCLUDE CURB AND GUTTER; AND
EDGES OF SIDEWALKS;
THE FILE MUST BE APPROVED BY ENVIRONMENTAL ENGINEERING
PRIOR TO ISSUANCE OF THE LAND DISTURBANCE PERMIT.
B) FLAGGING AROUND USACOE JURISDICTIONAL WETLANDS,
BUFFERS, AND SENSITIVE AREAS MUST BE VISIBLE.
C) DOCUMENTATION FROM THE USACOE/DEQ MUST BE RECEIVED
VERIFYING COMPLIANCE TO WETLAND PERMIT REGULATIONS.
D) A COPY OF VDOT LAND USE PERMIT MUST BE RECEIVED.
E) SAFETY FENCE AND/OR SUPER SILT FENCE WITH OPTIC
ORANGE FABRIC MUST BE IN PLACED ALONG THE RPA LIMITS.
F) AN EROSION CONTROL BOND MUST BE POSTED.
G) THE RISER AND BARREL PIPE ASSOCIATED WITH THE
SEDIMENT BASIN MUST BE ON-SITE.
H) TWO ADDITIONAL SETS OF CONSTRUCTION PLANS TO BE
STAMPED "APPROVED FOR CONSTRUCTION" MUST BE RECEIVED.
I) AS APPLICABLE, A SWPPP BOOKLET (3 RING BINDER) MUST
BE PROVIDED.
3. THESE ARE IN REGARDS TO THE MS-19:
A) PLEASE REVISE THE SCALE OF THE OFFSITE DRAINAGE AREAS
PERTINENT TO THE DA=1,896 ACRES (SHEET C-29) TO BE SHOWN ON
A SCALE MORE LEGIBLE. IN A SCALE OF 1"=2,000' IS VERY
HARD TO READ THE EXISTING CONTOURS AND VERIFY DRAINAGE
BREAKS. THE EXISTING ROAD SHOULD BE SHOWN ON THIS OFFSITE
DRAINAGE AREA AND THE EXISTING CONTOURS SHOULD BE CLEARLY
LABELED WITH ELEVATIONS.
IN ADDITION, PART OF THE EXISTING CONTOURS HAS BEEN CUTOFF
WITHIN THE DRAINAGE LIMITS. REVISE ACCORDINGLY. A COPY OF
THE OVERALL DRAINAGE AREAS ADDRESSING THE MS-19 BY 1% RULE
WAS PROVIDEDTO YOU BY EMAIL ON 3/15/16 TO USE AS A
REFERENCE.
B) PLEASE REVISE MS-19 X-SECTION A TO ANALYZE THE
NATURAL DRAINAGEWAY AS OPPOSED TO THE PLUNGE POOL/RIPRAP
PROTECTION. IN ADDITION, REVISE THE MS-19 SECTION A-LOCATION
TO BE SHOWN AT THE NATURAL DRAINAGEWAY, SUBMIT REVISED
SCALED X-SECTION AND REVISE THE MS-19 TABLE TO REFLECT THE
CHANGES.
C) SIMILARLY, PLEASE REVISE THE MS-19 X-SECTION D-1 TO
ANALYZE THE NATURAL DRAINAGEWAY IN LIEU OF THE OUTLET
PROTECTION. REVISE THE MS-19 SECTION D-1-LOCATION ON THE
PLANS, SUBMIT REVISED MS-19 SECTION D-1 CALCULATIONS AND
UPDATE THE MS-19 TABLE TO REFLECT THE CHANGES.
D) IT APPEARS THE MS-19 SECTIONS B-1/C-1/ETC. ANALYSIS
WERE TAKEN WITHIN THE OUTLET PROTECTION INSTEAD OF ANALYZING
THE BANKS OF THE NATURAL CHANNEL. PLEASE SUBMIT REVISED
SCALED X-SECTIONS B-1/C-1/H-1 TO BE TAKEN ALONG THE NATURAL
DRAINAGEWAY, AND REVISE THE MS-19 TABLE AT THOSE LOCATIONS
TO REFLECT THE CHANGES, ETC.
4. WE OFFER, BUT NOT LIMITED TO, THE FOLLOWING COMMENTS:
A) AS PREVIOUSLY REQUESTED, PLEASE BE SURE TO SHOW THE
GENERAL EROSION AND SEDIMENT CONTROL NOTES AND THE EC
LEGEND ON THE EC PLANS AS OPPOSED TO SHOWING ON THE
COVER SHEET. PLEASE ADDRESS.
B) PLEASE PROVIDE SAFETY FENCE ALONG THE RPA ON THE
NORTHERN SIDE OF LOTS 80/81. REFLECT THE CHANGES ON THE
EC PHASE I/PHASE II.
C) PLEASE ANNOTATE WITH "SSF WITH OPTIC ORANGE FABRIC
FENCE" TO THE SUPER SILT FENCE SPECIFIED ALONG THE
PERIMETER OF THE EROSION CONTROL DEVICES AND STORM
SEWER(S) LOCATED WITHIN THE RPA AREA. REFLECT THE
CHANGES ON THE EC PHASE I AND PHASE II.
D) PLEASE PROVIDE SAFETY FENCE ALONG THE UPSTREAM SIDE
THE STORM SEWER STRUCTURES 34 THRU 37. BE SURE THE
SAFETY FENCE IS LOCATED WITHIN THE 16' DRAINAGE
EASEMENT. REFLECT THE CHANGES ON THE EC PHASE I AND
PHASE II.
E) PLEASE LABEL THE STORM STRUCTURES 13-37, 38-48, 41-
47, 90-92, ETC. ON THE EC PHASE I PLANS.
F) IN ADDITION TO THE DIVERSION DIKE SPECIFIED IN THE
PROXIMITY OF STATIONS 14+00 TO 17+80 ON THE LEFT SIDE OF
CENTRALIA STATION ROAD, PLEASE PROVIDE SILT FENCE ALONG
THE DOWNSTREAM OF THE DIVERSION DIKE. REFLECT THE
CHANGES ON THE EC PHASE I AND PHASE II.
G) PLEASE PROVIDE RIGHT-OF-WAY DIVERSION IN THE
PROXIMITY OF STATION 14+00 ON CENTRALIA STATION ROAD TO
DIVERT UPSTREAM AREA FROM THE ROAD CONSTRUCTION TO ST1.
H) BE SURE THAT THE PROPOSED CONTOURS PERTINENT TO THE
SEDIMENT TRAPS AND BASINS HAVE BEEN LABELED WITH
ELEVATIONS REFLECT THE CHANGES ON THE EC PHASE I/PHASE
II.
I) PLEASE REVISE THE EC PHASE II TO PROVIDE SUPER SILT
FENCE WITH OPTIC ORANGE FABRIC FENCE ON THE RIGHT SIDE
OF THE PROPOSED SANITARY SEWER IN THE PROXIMITY OF
STATIONS 10+50 THRU 14+00 AND FROM STATIONS 14+00 THRU
18+00 ON BOTH SIDES OF THE SANITARY SEWER SUPER SILT
FENCE WITH OPTIC ORANGE FENCE SHOULD BE PROVIDED.
FOR THE REMAINING OF THE SANITARY SEWER LINE FROM
STATIONS 18+00 THRU 33+02.94, SILT FENCING SHOULD BE
PROVIDED ON THE LEFT SIDE OF THE SANITARY SEWER.
HOWEVER, FOR THE AREAS WHERE THE SANITARY SEWER CROSSES
THE WETLANDS SUPER SILT FENCE SHOULD BE PROVIDED ON BOTH
SIDES OF THE SANITARY SEWER (I.E. IN THE PROXIMITY OF
STATIONS 25+00 THRU 27+00, ETC.). REFLECT THE CHANGES ON
THE EC PHASE II PLANS.
J) PLEASE DEPICT THE EXISTING CULVERTS #1 THRU #3 UNDER
THE RAILROAD AND PROVIDE CULVERT INLET PROTECTION FOR
THE EXISTING CULVERTS #1 AND #2. REFLECT THE CHANGES ON
THE EC PHASE I/PHASE II.
K) PLEASE PROVIDE DIMENSIONS OF THE BEST FIT TRAP
LOCATED IN THE PROXIMITY OF STATION 18+00 ON CENTRALIA
STATION ROAD. THE REQUIRED/PROVIDED WET/DRY VOLUME
SHOULD BE PROVIDED ON THE PLANS. IN ADDITION, SUBMIT A
VARIANCE REQUEST FOR THIS BEST FIT TRAP FOR NOT MEETING
THE REQUIRED VOLUME TO THIS OFFICE FOR APPROVAL AND
DOCUMENTATION.
IT SHOULD STATE IN THE VARIANCE REQUEST LETTER THAT THE
MODIFIED TRAP IS BEING STRATEGICALLY LOCATED AT THE LOW
AREAS OF THE FUTURE ROAD TEMPLATE TO DETAIN SEDIMENT
DURING ROAD CONSTRUCTION PRIOR TO REACHING OFFSITE
PROPERTY. THIS AREA IS CONSTRAINED WITHIN THE PROPOSED
RIGHT-OF-WAY SURROUNDING WITH PARCELS NON-OWNED BY THE
ONSITE PROPERTY.
L) PLEASE PROVIDE DIVERSION DIKE ON THE RIGHT SIDE OF
CENTRALIA STATION ROAD FROM STATION 17+50 AND CONTINUE
THIS DIVERSION DIKE ALONG THE PERIMETER OF THE STORM
SEWER STRUCTURES 29 THRU 35 AND CONTINUE TO SURROUND THE
DOWNSTREAM OF ST3. THIS IS TO ENSURE DIVERTING CLEAN
WATER TO STRUCTURES 13 AND 39. REFLECT THE CHANGES ON
THE EC PHASE I/PHASE II.
M) IT APPEARS ST1 SHOULD BE DIMENSIONED TO INCLUDE THE
AREA FROM LOT 5. SINCE THIS AREA APPEARS TO BE DRAINING
IN THAT DIRECTION.
IN ADDITION, THE DIVERSION DIKE SPECIFIED ON THE LEFT
SIDE ON CENTRALIA STATION ROAD IN THE PROXIMITY OF
STATION 10+50 TO 14+00 CAN BE ELIMINATED AND THE SILT
FENCE SPECIFIED ON CENTRALIA ROAD IN THE PROXIMITY OF
STATION 15+80 CAN BE EXTENDED TO SURROUND THE FILL AREAS
ON THE LEFT SIDE OF CENTRALIA STATION ROAD TO END IN THE
VICINITY OF STATION 11+00.
A RIGHT-OF-WAY DIVERSION CAN BE SPECIFIED IN THE
VICINITY OF STA. 14+00 ON CENTRALIA STATION ROAD TO
DIRECT SEDIMENTS TO THE ST1.
AS APPLICABLE, REVISE THE EC PLANS, ST1, SEDIMENT TRAP
SCHEDULE, ETC. TO REFLECT THE CHANGES.
N) PLEASE BE SURE THE DIVERSION DIKE SPECIFIED ON THE
LEFT SIDE ON CENTRALIA STATION ROAD IN THE VICINITY OF
STATION 14+00 SHOULD END AT THE ST1. REFLECT THE CHANGES
ON THE EC PHASE I AND PHASE II.
O) PLEASE PROVIDE SILT FENCING TO SURROUND THE GRADING
SPECIFIED ON LOT 5 AND CONTINUE THIS SILT FENCING TO END
AT THE ST1.
P) THESE ARE IN REGARDS TO THE SEDIMENT BASIN 1:
P.1) PLEASE REVISE THE SAFETY FENCE SPECIFIED ALONG THE
RPA LIMITS IN THE PROXIMITY OF SB#1 TO SURROUND ALONG
THE PERIMETER OF THE PLUNGE POOL AS OPPOSED TO BE
DELINEATED TO CROSS OVER THE PLUNGE POOL. REFLECT THE
CHANGES ON THE EC PHASE I/PHASE II.
P.2) PLEASE REVISE THE LABELING ON THIS BASIN TO BE SB#1
IN LIEU OF BMP#1. REFLECT THE CHANGES ON THE EC PHASE I
AND PHASE II.
P.3) PLEASE PROVIDE TEMPORARY BAFFLES WHILE THE BASIN IS
WORKING AS SEDIMENT BASIN. SINCE, THIS BASIN MUST BE
REGRADED AND CLEANED OUT FROM SEDIMENTS PRIOR TO THE
CONVERSION TO SWM/BMP. INCLUDE A DETAIL FOR TEMPORARY
BAFFLES PLATE 3.14-6 FROM THE VIRGINIA EROSION AND
SEDIMENT CONTROL HANDBOOK ON SHEET C-12.
IN ADDITION, REVISE THE LABELING FOR THE BAFFLES LOCATED
WITHIN THE SB#1 (SHEETS C-5 AND C-9) TO REFER TO SHEET
C-12 AS OPPOSED TO SHEET C-39A. REFLECT THE CHANGES ON
ALL APPLICABLE SHEETS.
P.4) AS A REMINDER, DEQ HAS EXPRESSED SOME CONCERNS
IN THE PAST FOR USING THIS ALTERNATIVE DESIGN/PLYWOOD
WEIR WITH DEWATERING DEVICE.
R) THESE ARE IN REGARDS TO THE SB#2:
R.1) PLEASE LABEL THIS BASIN AS SB#2 WITHIN THE BASIN
AREA. REFLECT THE CHANGES ON SHEETS C-6 AND C-10.
R.2) PLEASE PROVIDE SUPER SILT FENCE AT THE TOE OF THE
FILL DAM SECTION. REFLECT THE CHANGES ON THE EC PHASE
I/PHASE II.
R.3) PLEASE LABEL THE PROPOSED CONTOURS PERTINENT TO
THIS BASIN WITH ELEVATIONS.
R.4) IT APPEARS A SECTION FOR THE INNER SIDE OF THE
EMBANKMENT TO BE 6:1/10:1 AS OPPOSED TO BE 3:1 IN ITS
ENTIRETY. PLEASE CLARIFY.
R.5) BASED ON AN IN-HOUSE CHECK THE DRY VOLUME REQUIRED
IS NOT PROVIDED WHEN SUBTRACTING THE WET VOLUME PROVIDED
FROM THE TOTAL VOLUME PROVIDED OF 1821.00 CY - 937.00 CY
= 884.00 CY, WHICH IS LESS THE DRY VOLUME REQUIRED OF
898 CY. PLEASE ADDRESS.
R.6) PLEASE REVISE THE SEDIMENT BASIN SCHEMATIC DETAIL
FOR SB#2 (SHEET C-12) TO REFLECT THE INFORMATION FOR THE
SB#2 (I.E. WET/DRY VOLUME ELEVATION, TOP DAM ELEVATION,
ETC.). IN ADDITION, REVISE TITLE TO BE LABELED AS SB#2
AS OPPOSED TO BASIN #1, #2 & #3.
R.7) BASED IN THE SEDIMENT BASIN SCHEMATIC DETAIL FOR
SB#2, IT APPEARS CONCRETE CRADLE WOULD BE PROVIDED ALONG
THE 27 CMP BARREL. PLEASE CLARIFY AND SHOW/LABEL THE
APPROXIMATE LOCATION OF THESE CONCRETE CRADLES IN THE
SB#2 SCHEMATIC DETAIL.
R.8. PLEASE INCLUDE ANTI-VORTEX DEVICE DETAIL WITH
PERTINENT INFORMATION AND DEWATERING DEVICE DETAIL ON
SHEET C-12.
R.9) PLEASE REVISE THE SB#2 IN THE TEMPORARY SEDIMENT
BASIN TABLE (SHEET C-12) TO SPECIFY THE DIAMETER OF THE
RISER, WHICH APPEARS TO BE 30" CMP. REVISE ACCORDINGLY.
R.10) PLEASE REVISE THE LABELING FOR THE BARREL PIPE
(SHEET C-6) TO BE 27" CMP 73 L.F. BARREL. REFLECT THE
CHANGES ON ALL APPLICABLE SHEETS.
R.11) PLEASE ADD A NOTE FOR THE REMOVAL OF THIS BASIN
SB#2 STATING, "UNSUITABLE/SATURATED SOILS FROM THE BASIN
BOTTOM SHALL BE REMOVED PRIOR TO PLACEMENT FILL
MATERIAL. THE AREA SHALL BE REGRADED TO AN ADEQUATE
CONVEYANCE SYSTEM."
AFTER THE REMOVAL OF THE SB-2 ADEQUATE CONVEYANCE SYSTEM
SHOULD BE PROVIDED FROM THE OUTFALL PIPE STR. 131 UNTIL
IT REACHES TO AN ADEQUATE RECEIVING FACILITY/EXISTING
NATURAL DRAINAGEWAY. A FURTHER DISCUSSION IS
RECOMMENDED.
THE MS-19 H-1 AND H-2 SHOULD BE REVISED TO ANALYZE THE
NATURAL DRAINAGEWAY BELOW THE DRAINAGE IMPROVEMENTS.
S) PLEASE PROVIDE A DETAIL/MANUFACTURED WITH PERTINENT
INFORMATION (I.E. DIMENSIONS, MATERIALS, ETC.) FOR THE
IMPERMEABLE PLASTIC FENCE.
IN ADDITION, PROVIDE A NOTE IN BOLD PRINT TO THE
IMPERMEABLE PLASTIC FENCE STATING, "IMPERMEABLE PLASTIC
FENCE SHOULD REMAIN IN PLACE UNTIL THE SB1 HAS BEEN
CONVERTED TO SWM/BMP WETPOND." REFLECT THIS NOTE ON
SHEETS C-5 AND C-9.
T) PLEASE PROVIDE SILT FENCE ALONG THE SOUTHERN SIDE OF
THE EMERGENCY ACCESS ROAD TO BE WITHIN THE EMERGENCY
ACCESS ROAD EASEMENT. REFLECT THE CHANGES ON THE EC
PHASE I AND PHASE II.
IN ADDITION, REVISE THE EC PHASE II TO SHOW THE ROADSIDE
DITCH ALONG THE EMERGENCY ACCESS ROAD AND PROVIDE CHECK
DAMS WITHIN THE FLOWLINE OF THE DITCH.
U) PLEASE PROVIDE INLET PROTECTION AT STR. 9B. REFLECT
THE CHANGES ON THE EC PHASE II.
V) CHECK DAMS SHOULD BE PROVIDED ALONG THE SWALE
SPECIFIED ON LOT 5. REFLECT THE CHANGES ON EC PHASE II.
W) ALTHOUGH NOT PREVIOUSLY REQUESTED, PLEASE PROVIDE
TEMPORARY CULVERT CROSSING DETAIL ON THE EC PLANS.
X) PLEASE REVISE THE EC PHASE I TO SHOW/LABEL THE OUTLET
PROTECTION PERTINENT TO STR. 37.
5. IF TIMBERING IS REQUIRED ON THE PROJECT, IT SHOULD BE
INCORPORATED INTO THE EROSION CONTROL PLAN / NARRATIVE AND
SHOULD NOT BEGIN UNTIL AFTER THE ISSUANCE OF A LAND
DISTURBANCE PERMIT AND THE INSTALLATION OF THE APPROVED
EROSION CONTROL DEVICES.
======= CBPA =======
1. THERE APPEARS TO BE A DISCREPANCY WHEN COMPARING THE
NUMBER OF LOTS WITH THE CONSTRUCTION PLANS AND TENTATIVE
PLAN. IN THE TENTATIVE PLAN LOT 7 HAS BEEN ENLARGED TO
INCLUDE LOT 8 SINCE THE RPA TAKES THE ENTIRE FRONT AREA OF
THIS LOT. AS A RESULT, THIS LOT IS NO LONGER BUILDABLE.
PLEASE REVISE THE PLANS TO MATCH THE TENTATIVE PLAN.
IN ADDITION, REVISE THE WORKSHEET A CALCULATIONS, THE
IMPERVIOUS AREA CALCULATIONS TABLE, ETC. TO REFLECT THE
CHANGES.
2. PRIOR TO PLAN APPROVAL, CENTRALIA STATION PHASE II
TENTATIVE MUST BE APPROVED.
3. PRIOR TO PLAN APPROVAL THE REVISED OVERALL CBPA
TENTATIVE PLAN MUST BE APPROVED.
======= SWM/BMP =======
1. THESE ARE IN REGARDS TO THE SWM/BMP PROFILE BMP#1 (SHEET
C-21):
A) IT APPEARS THE SEDIMENT FOREBAY IS BEING DELINEATED
1' BELOW THE NWSE. PLEASE BE SURE IT IS DRAWN 6" BELOW
THE NWSE.
B) PLEASE REVISE THE LABELING OF THE 100-YEAR FLOODPLAIN
SHOWN ON THIS PROFILE TO BE LABELED AS "100-YEAR FEMA
FLOODPLAIN LIMITS".
C) AS PREVIOUSLY REQUESTED, PLEASE BE SURE TO
SHOW/LABEL THE 100-YEAR FEMA FLOODPLAIN LIMITS AND THE
LIMITS OF THE RPA ON THIS PROFILE.
2. IT APPEARS THE DETAIL FOR THE BMP ACCESS ROAD TO BE
PAVED ROAD. PLEASE DEPICT THE STIPPLE PATTERN INSTEAD OF
GRAVEL FOR THE PROPOSED BMP ACCESS ROAD. OTHERWISE, REVISE
THE DETAIL TO BE GRAVEL AS OPPOSED TO PAVED. REFLECT THE
CHANGES ON ALL APPLICABLE SHEETS.
3. PLEASE REMOVE THE NOTE LOCATED NEXT TO THE SECTION A-A
SWM/BMP1 WEIR DETAIL THAT STATES, "POND 1 CAUSES NO
REDUCTION IN FLOODPLAIN VOLUME. THE INSTALLATION OF THE
POND 1 RESULTS IN A NET CUT OF 1547 CY WITH THE 100-YEAR
FLOODPLAIN."
4. PLEASE REVISE THE NO-RISE CERTIFICATE LETTER DATED
02/26/16 TO INCLUDE IN THE FIRST SENTENCE AFTER FEMA "ZONE
AE 100-YEAR FLOODPLAIN, SHOWN PANEL ___ FOR CHESTERFIELD
COUNTY, DATED DECEMBER 18, 2012."
BE SURE TO SPECIFY THE PANEL WHERE THIS PROJECT IS LOCATED
IN THE BLANK SPACE.
SUBMIT THE REVISED LETTER TO THIS OFFICE FOR APPROVAL AND
DOCUMENTATION.
5. PLEASE REVISE THE BAFFLE DETAIL TO BE CONCRETE AS
OPPOSED TO GABIONS. THE JERSEY BARRIER HAS BEEN USED IN THE
PAST FOR OTHER PROJECTS (I.E. THE HEIGHT OF THE JERSEY WALL
AND WIDTH SHOULD BE PROVIDED IN THE DETAIL.). A FURTHER
DISCUSSION IS RECOMMENDED.
BE SURE TO SPECIFY IN THE CONCRETE BAFFLE DETAIL THAT THE
WALL SHOULD BE 6" ABOVE THE NWSE AND THE DETAIL SHOULD BE
SHOWN SHEET C-23 AS OPPOSED TO SHEET C-39A.
6. THESE ARE IN REGARDS TO LANDSCAPE FOR BMP#1 (SHEET C-
24):
A) PLEASE REVISE THE TITLE IN THE TITLE BOX TO STATE,
"CBPA COMPLIANCE & BMP LANDSCAPE". BE SURE THE REVISED
TITTLE IS REFLECTED IN THE INDEX SHEET (SHEET C-1).
B) THE RPA ESTABLISHMENT PLAN TABLE SHOULD BE RELOCATED
TO THE EC DETAIL SHEET (SHEET C-11).
C) PLEASE INCREASE THE SCALE IN THE PLAN VIEW TO
APPROXIMATE 1"=10' TO CLEARLY SHOW THE ARRANGEMENT FOR
EACH GROUP OF PLANT TYPE. USUALLY, IT IS DENOTED BY
DIFFERENT TYPE OF LINE PATTERN ASSIGNED FOR EACH TYPE OF
PLANTING. REFER TO THE ENCLOSED COPY.
BE SURE THAT EACH AREA OF THE GROUP PER PLANT TYPE IS
LABELED BY USING ABBREVIATED DESIGNATION ON THE PLAN
VIEW AS SHOWN IN THE ENCLOSED COPY.
D) PROVIDE AQUATIC BENCH PLANT SCHEDULE AS SHOWN IN THE
ENCLOSED COPY.
E) THE NUMBER OF PLANTS MAY VARY BASED ON THE SIZE OF
THE WETPOND. IT SHOULD BE SPECIFIED IN THE PLANT
SCHEDULE.
F) PLEASE LABEL/DIMENSION 10' PLANTED AQUATIC BENCH IN
THE PLAN VIEW.
G) PLEASE SHOW/LABEL A SUITABLE LOCATION FOR THE TYPICAL
PLANTED AQUATIC BENCH SIGN IN THE BMP GRADING PLAN
(SHEET C-23). IT SHOULD BE LOCATED WITHIN THE 10'
PLANTED AQUATIC BENCH NEAR THE BMP MAINTENANCE CORRIDOR.
======= ROAD AND DRAINAGE =======
1. DUE TO THE ABSENCE OF CENTERLINE STAKING AND HEAVY
VEGETATION, OUR CONCERNS ARE BASED ON THE INFORMATION SHOWN
IN THE CONSTRUCTION PLANS. THE RESPONSIBILITY FOR
IDENTIFYING CRITICAL AREAS IS PLACED ON THE PROFESSIONAL
ENGINEER WHO SEALS THE CONSTRUCTION PLANS APPROVED. WE
RESERVE THE RIGHT TO INSPECT CONVEYANCE SYSTEMS PRIOR TO
PLAT RECORDATION AND/OR STATE ACCEPTANCE TO DETERMINE IF
ADDITIONAL IMPROVEMENTS ARE REQUIRED.
2. PLEASE BE SURE TO REFLECT LOT 5 AS OPPOSED TO LOT 1 IN
THE LABELING OF "AREA OUTSIDE OF PROPOSED CENTRALIA STATION
ROAD R/W TO BE INCORPORATED AS PART OF LOT 1 IF EXISTING
CENTRALIA ROAD IS ABANDONED.
3. PLEASE REVISE THE LATITUDE AND LONGITUDE TO REMOVE THE
N/W DESIGNATION AND ADD THE DEGREE SYMBOL AT THE END OF THE
DATA AND NEGATIVE SYMBOL TO THE LONGITUDE DATA. IT SHOULD
BE LABELED AS LATITUDE: 37.3722°, LONGITUDE: -77.4500°.
4. PLEASE RELOCATE THE DRIVEWAY ENTRANCE SPECIFIED ON LOT 8
TO BE OUTSIDE THE RPA AREA AND BE SURE IT IS LOCATED
OUTSIDE THE 25' BUILDING SETBACK. REFLECT THE CHANGES ALL
ON APPLICABLE SHEETS.
5. PLEASE RELOCATE THE DRIVEWAY ENTRANCE ON LOT 80 TO BE
CLOSER TO THE BUILDING ENVELOPED.
6. PLEASE REMOVE THE ANNOTATION OF MFF ON LOT 60 AND
INSTEAD ANNOTATE THIS LOT WITH MCS. REFLECT THE CHANGES ON
ALL APPLICABLE SHEETS.
7. PLEASE BE SURE TO ANNOTATE LOTS 78 AND 79 WITH MCS ONLY.
REMOVE ELEVATION SPECIFIED FOR MCS. REFLECT THE CHANGES ON
ALL APPLICABLE SHEETS.
IN ADDITION, ANNOTATE LOTS 78/79 WITH "NBP". REFLECT THE
CHANGES ON ALL APPLICABLE SHEETS.
8. PLEASE REMOVE THE ANNOTATION FOR MCS ON LOT 75. REFLECT
THE CHANGES ON ALL APPLICABLE SHEETS.
9. PLEASE REMOVE THE ANNOTATION FOR MFF=132.3 ON LOT 70,
SINCE THE LIMITS OF THE 100-YEAR FP ARE NOT ENCROACHING
.INTO THIS LOT. REFLECT THE CHANGES ON ALL APPLICABLE.
10. PLEASE REMOVE THE PROPOSED GRADING SPECIFIED WITHIN THE
OPEN SPACE AREA NEAR THE PROPOSED CULVERT STR. 90.
11. PLEASE SHOW/LABEL THE LIMITS OF THE SETBACK OFF THE 100-
YEAR FLOODPLAIN LIMITS, 100-YEAR FEMA FLOODPLAIN, RPA,
WETLANDS, ETC. ON THE GRADING PLANS (I.E. SHEETS C-17 THRU
C-20).
12. PLEASE ENCLOSE STRUCTURES 115/116 IN A VARIABLE WIDTH
DRAINAGE EASEMENT AS OPPOSED TO BEING ENCLOSED IN A VARIABLE
WIDTH DRAINAGE EASEMENT FOR VDOT MAINTENANCE. VDOT WILL NOT
MAINTAIN DI-6 INLET.
13. PLEASE BE SURE TO LABEL THE EASEMENT ENCLOSING THE
PROPOSED DITCH/STRUCTURES 125 THRU 127 AS 16' DRAINAGE
EASEMENT. REFLECT THE CHANGES ON ALL APPLICABLE SHEETS.
14. PLEASE REMOVE THE GRASS SWALE ON LOT 83. IT DOES NOT
APPEAR TO INTERCEPT CROSS LOT DRAINAGE.
15. PLEASE SHOW/LABEL THE TYP. 5' DIMENSION PERTINENT TO THE
LOCATION OF THE PROPOSED SWALES. REFLECT THE CHANGES ON ALL
APPLICABLE SHEETS.
16. THE ADJACENT PROPERTY OWNERS: SPRUILL, P. AT 4401
CHIPPOKE RD., STANEART, R. AT 4407 CHIPPOKE RD., STANDEFER,
E. AT 4413 CHIPPOKE RD., BANKS, K. AT 4419 CHIPPOKE RD.,
FINKLEA, C. AT 4501 CHIPPOKE RD., HOBBS, R. AT 4421
CENTRALIA RD., TAYLOR, H. AT 10221 CENTRALIA STATION,
CLEMENTS, L. AT 10210 CENTRALIA STATION, TUNSTALL, J. AT
10300 CENTRALIA STATION, ETC. SHOULD BE NOTIFIED OF THE
IMPEDING CONSTRUCTION ACTIVITY NEAR THEIR PROPERTIES. THE
NOTIFICATION SHOULD BE VIA U.S. POSTAL CERTIFIED MAIL,
SIGNED RETURN RECEIVED REQUEST. THIS CONCERN MUST BE
ADDRESSED PRIOR TO PLAN APPROVAL PER TENTATIVE CONDITION
#16.INCLUDE AN 8½ X 11 COPY OF THE PROPOSED CONSTRUCTION
ACTIVITY ADJACENT TO THEIR PROPERTIES.
17. PER TENTATIVE CONDITION #11, WHICH STATES, "APPROVAL OF
THE ROAD AND DRAINAGE PLANS BY DOMINION VIRGINIA POWER IN
RELATION TO ITS EASEMENT AND FACILITIES THEREIN IS A
PREREQUISITE TO CONSTRUCTION PLAN APPROVAL BY THE
ENVIRONMENTAL ENGINEERING DEPARTMENT. A QUITCLAIM TO VDOT
OR A SATISFACTORY COMMITMENT THEREOF BY DOMINION VIRGINIA
POWER FOR THE LOCATIONS WHERE CENTRALIA STATION ROAD,
RIGHT-OF-WAY WILL CROSS THE DOMINION VIRGINIA POWER
EASEMENT SHALL BE A PREREQUISITE TO SUBDIVISION PLAT
RECORDATION."
18. AS PREVIOUSLY REQUESTED, PLEASE SHOW DIMENSIONING
BUILDING ENVELOPES ON LOTS 31 (PREVIOUSLY LOT 27), ETC.
19. AS PREVIOUSLY REQUESTED, PLEASE PROVIDE SIDEWALK DETAIL
ON THE PLANS.
20. PLEASE LABEL STR. 9A ON THE PLAN VIEWS AND PROFILES.
21. THESE ARE IN REGARDS TO THE EMERGENCY ACCESS ROAD:
A) PLEASE CONSIDER PROVIDING ONE ROADSIDE DITCH ALONG
THE SOUTHERN SIDE OF THIS EMERGENCY ACCESS ROAD AND
GRADE THE ROAD TO DRAIN TOWARDS THIS ROADSIDE DITCH TO
ELIMINATE THE NEED FOR A CULVERT NEAR THE CUL-DE-SAC
PERTINENT TO CENTRALIA STATION ROAD. REVISE THE PLANS,
PROFILES, THE TYPICAL EMERGENCY ACCESS ROAD DETAIL, ETC.
TO REFLECT THE CHANGES.
IN ADDITION, CONTINUE THIS ROADSIDE DITCH UNTIL IT
CONNECTS TO THE PROPOSED DITCH SPECIFIED ON THE REAR OF
LOTS 36 THRU 40. BE SURE TO SPECIFY THE RADIUS AT THE
TURN(S) OF THIS DITCH.
AS PREVIOUSLY REQUESTED, INCLUDE 10/100-YEAR ROADSIDE
DITCH CALCULATIONS, A PROFILE OF THIS ROADSIDE DITCH
SHOULD BE DEPICTED IN THE EMERGENCY ACCESS ROAD PROFILE,
ETC.
B) AS PREVIOUSLY REQUESTED, PROVIDE DRIVEWAY ENTRANCE
STANDARD DETAIL TO ACCESS THE EMERGENCY ACCESS ROAD FROM
CHIPPOKE ROAD.
C) AS PREVIOUSLY REQUESTED, A PROFILE OF THIS EMERGENCY
ACCESS ROAD WITH APPLICABLE ROAD DESIGN DATA SHOULD BE
PROVIDED ON THE PLANS. BE SURE STATIONING CENTERLINE
PROFILE AGREES WITH STATIONS SHOWN ON THE PLANS.
D) AS PREVIOUSLY REQUESTED, PROVIDE 10-YEAR ENTRANCE
CULVERT WITH SUPPORT CALCULATIONS ON STANDARD VDOT FORM.
BE SURE 10-YEAR HW/D<1. IN ADDITION, REFLECT THIS
INFORMATION ON THE PLANS.
E) AS PREVIOUSLY REQUESTED, SHOW/LABEL THE EXISTING AND
PROPOSED CONTOURS WITH ELEVATIONS. BE SURE TO INCLUDE
ENOUGH AREA OF THE CONTOURED TOPOGRAPHY TO VERIFY
DRAINAGE BREAKS/DRAINAGE PATTERN ONSITE/OFFSITE.
22. AS PREVIOUSLY REQUESTED, PLEASE SHOW/LABEL THE EXISTING
CULVERT(S). ONLY THE PERTINENT INFORMATION WERE PROVIDED.
REFLECT THE CHANGES ON ALL APPLICABLE SHEETS. ADDITIONAL
EROSION CONTROL MEASURES MAY BE NEEDED.
23. AS PREVIOUSLY REQUESTED, PLEASE SHOW/LABEL THE APPROVED
100-YEAR FEMA BACKWATER LIMITS/ELEVATION ON THE UPSTREAM
SIDE OF THE EXISTING CULVERT UNDER THE RAILROAD TRACK WHERE
GREAT BRANCH CREEK DRAINS TO. INCLUDE PERTINENT INFORMATION
OF THIS CULVERT ON THE PLANS (I.E. INVERTS, DIAMETER,
MATERIAL, LENGTH, ETC.). REFLECT THE CHANGES ON ALL
APPLICABLE SHEETS.
23. PLEASE REVISE THE ANNOTATION FOR MFF'S ON ALL
APPLICATION LOTS. THE LABELING SHOULD BE AS FOLLOW: FOR
EXAMPLE, ON LOT 54 THE BACKWATER IS MORE RESTRICTIVE AND IT
SHOULD BE LABELED AS MFF(BW)=121.50, ON LOTS 41 THRU 51 THE
100-YEAR FEMA FLOODPLAIN IS MORE RESTRICTIVE AND THOSE LOTS
SHOULD BE LABELED AS, MFF(FP)=130.00,ETC. REFLECT THE
CHANGES ON ALL APPLICABLE SHEETS.
25. PLEASE REMOVE THE ANNOTATION FOR MFF ON LOTS 82 THRU 84.
THE LIMITS OF THE 100-YEAR ARE NOT ENCROACHING INTO THESE
LOTS. REFLECT THE CHANGES ON ALL APPLICABLE SHEETS.
26. IF THE SAG AT THE RAILROAD IS MORE RESTRICTIVE THAN THE
100-YEAR BACKWATER, MMF SHOULD BE REVISED AND NOTED AS
MFF(SAG) ON LOTS 54 THRU 56, 80, 81, ETC. PLEASE DEPICT ON
THE PLANS FIELD SPOT ELEVATIONS IN THE PROXIMITY OF THE
EXISTING CULVERTS UNDER THE RAILROAD TRACK TO ADDRESS THIS
CONCERN.
27. THIS OFFICE WAS NOT ABLE TO LOCATE THE SCALED X-SECTIONS
OR FP X-SECTION 26 FOR FURTHER REVIEW AND/OR APPROVAL. IN
ADDITION, BE SURE TO SHOW X-SECTION 26 WITH PERTINENT
INFORMATION IN THE 100-YEAR FLOODPLAIN LIMITS TABLE (SHEETS
C-17, C-37, C-37A, C-37B, ETC.).
28. IT APPEARS THE SCALED X-SECTIONS FROM 14+50 THRU 17+00
OF THE PROPOSED ROAD PERTINENT TO CENTRALIA STATION ROAD
WERE OMITTED IN THE CONSTRUCTION PLANS. PLEASE ADDRESS.
29. PLEASE BE SURE TO SPECIFY EC-1 RIPRAP AT THE BEGINNING
OF STRUCTURES 17, ETC. AND INCLUDE DIMENSIONS OF
THIS PROPOSED EC-1 RIPRAP (I.E. WIDTH, LENGTH AND 24" THICK
LAYER OF RIPRAP OVER FILTER FABRIC) ON THE PLANS AND
PROFILES.
IN ADDITION, REVISE THE PROPOSED EASEMENT THAT IS ENCLOSING
STR. 17 TO BE IN A VARIABLE WIDTH DRAINAGE EASEMENT FOR VDOT
MAINTENANCE.
30. PLEASE REVISE THE OUTFALL PIPE STRUCTURES 35 THRU 37 TO
BE DELINEATED CLOSER TO THE LIMITS OF THE WETLANDS. IN
ADDITION, EXTEND THE OUTLET PROTECTION TO THE LIMITS OF
WETLANDS TO ENSURE DAYLIGHT AND ENSURE THESE IMPROVEMENTS
ARE IN THE 16' DRAINAGE EASEMENT. AS APPLICABLE, REVISE THE
PLANS, PROFILES AND COMPUTATION SHEETS.
31. PLEASE RELOCATE STR.97 TO BE LOCATED WITHIN THE
CENTERLINE OF THE PROPOSED DITCH LOCATED ON THE REAR OF LOTS
23 THRU 26. REVISE THE PLANS, PROFILES AND COMPUTATION
SHEETS TO REFLECT THE CHANGES.
IN ADDITION, REVISE THE GRADING PERTINENT TO THIS DITCH TO
SHOW CONTAINMENT UNTIL IT REACHES THE LIMITS OF THE RIGHT-
OF-WAY. REFLECT THE CHANGES ON ALL APPLICABLE SHEETS.
32. PLEASE ENCLOSE THE PROPOSED DITCH SPECIFIED ON THE REAR
OF LOTS 36 THRU 38 IN A 16' DRAINAGE EASEMENT. REFLECT THE
CHANGES ON ALL APPLICABLE SHEETS.
33. PLEASE LABEL THE TYPICAL DITCH (SHEET C-17) AS GRASS
DITCH AS OPPOSED AS EARTH DITCH. IN ADDITION, ADD A NOTE TO
THIS TYPICAL GRASS DITCH STATING, "PROPOSED DITCHES ARE
LOCATED ON THE REAR OF LOTS 2 THRU 4, 23 THRU 26, 36 THRU
38, BETWEEN LOTS 58/59, ETC.
34. PLEASE SUBMIT 10/100-YEAR DITCH CALCULATIONS FOR THE
PROPOSED DITCH LOCATED ON THE REAR OF LOTS 2 THRU 4 AND
PROVIDE A PROFILE OF THIS DITCH.
35. THESE ARE IN REGARDS TO THE FLOODPLAIN ANALYSIS (SHEETS
C-37, C-37A, C-37B):
A) AS PREVIOUSLY REQUESTED, PLEASE SHOW/LABEL ALL THE
EXISTING CONTOURS WITH ELEVATIONS AND BE SURE THE
ELEVATIONS ARE LEGIBLE. REFLECT THE CHANGES ON SHEET C-
37B.
B) AS PREVIOUSLY REQUESTED, PLEASE SHOW THE CONTOURED
TOPOGRAPHY WITHIN THE OFFSITE DRAINAGE AREAS, WHICH HAVE
BEEN OMITTED FROM THE PLAN VIEWS (SHEETS C-37, C-37A,
ETC.) TO VERIFY DRAINAGE BREAKS.
C) AS PREVIOUSLY REQUESTED, PLEASE INCREASE THE LETTER
SIZE PERTINENT TO DRAINAGE AREAS/RUNOFF
COEFFICIENTS/FLOODPLAIN SECTION-LOCATIONS 1 THRU 26 ON
SHEET C-37 TO BE MORE LEGIBLE, WHICH IS VERY HARD TO BE
READ ON THE PLANS.
36. THESE ARE IN REGARDS TO THE 100-YEAR FEMA FLOODPLAIN:
A) AS PREVIOUSLY REQUESTED, PLEASE SHOW THE 100-YEAR
FEMA FLOODPLAIN SECTIONS-LOCATIONS WITH ELEVATIONS ALONG
THE GREAT BRANCH CREEK.
B) AS PREVIOUSLY REQUESTED, PLEASE INCORPORATE THE
WORDING "FEMA" WITHIN THE LIMITS OF THE 100-YEAR FEMA
FLOODPLAIN. REFLECT THE CHANGES ON ALL APPLICABLE
SHEETS.
C) AS PREVIOUSLY REQUESTED, PLEASE INDICATE WITH ARROWS
THE DIRECTION OF FLOW ALONG THE FLOWLINE OF THIS CREEK
AND NATURAL DRAINAGEWAY/WETLAND AREAS. REFLECT THE
CHANGES ON ALL APPLICABLE SHEETS.
D) PLEASE SHOW THE ASTERISK TO THE LOTS REQUIRING
ELEVATION CERTIFICATE ON LOTS 41 THRU 51 ON THE GRADING
PLANS (I.E. SHEETS C-19, C-20, ETC.).
37. IT APPEARS LOTS 1 THRU 4 DO NOT CONSIDERED THE FUTURE
SECTION/CUL-DE-SAG. PLEASE CLARIFY.
38. BASED ON THE OVERALL TENTATIVE THIS SECTION SHOULD BE
LABELED AS SECTION 1. PLEASE ADDRESS.
39. THESE ARE IN REGARDS TO THE PROFILES:
A) AS PREVIOUSLY REQUESTED, PLEASE BE SURE TO SHOW/LABEL
THE 100-YEAR FLOODPLAIN, 100-YEAR BACKWATER, ROW,
WETLANDS LIMITS, RPA LIMITS, ETC. ON ALL PROFILES (I.E.
STORM 41-47 PROFILE, STORM 15-19 PROFILE, STORM 38-40
PROFILE, STROM 90-91 PROFILE, ETC.).
B) PLEASE REVISE THE STORM 62-66 PROFILE (SHEET C-34) TO
SHOW COVER OVER THE PIPE STRUCTURES 65/66. IN ADDITION,
EXTEND THE PROFILE WITH SUFFICIENT LENGTH TO INCLUDE THE
LIMITS OF THE 100-YEAR FLOODPLAIN AND WETLANDS. REFLECT
THE CHANGES ON THE PLANS AND PROFILES.
C) PLEASE REVISE THE STORM 90-91 TO EXTEND THE PROPOSED
GRADING/EC-1 RIPRAP ON THE UPSTREAM SIDE OF STR. 90 TO
TYING BACK TO THE EXISTING GRADE. REFLECT THE CHANGES ON
ALL APPLICABLE SHEETS.
D) PLEASE SHOW ON PROFILE VIEW THE STORM SEWER
STRUCTURES 7/9A/9B/9/11/13/ETC. WITH PERTINENT
INFORMATION.
40. PLEASE EXTEND THE PROPOSED 16' DRAINAGE EASEMENT THAT IS
ENCLOSING STR. 17 TO THE PROPERTY LINE. REFLECT THE CHANGES
ON ALL APPLICABLE SHEET.
41. AS A PREREQUISITE TO SUBDIVISION PLAT RECORDATION:
A) THE $100/LOT BMP MAINTENANCE FEE MUST BE RECEIVED.
B) APPROVED BONDING AND RECORDED EASEMENTS WITH DEED
BOOK AND PAGE NUMBER FOR THE SWM/BMP WETPOND MUST BE
PROVIDED.
C) A QUITCLAIM TO VDOT OR A SATISFACTORY COMMITMENT
THEREOF BY DOMINION VIRGINIA POWER FOR THE LOCATIONS
WHERE CENTRALIA STATION ROAD, RIGHT-F-WAY WILL CROSS THE
DOMINION VIRGINIA POWER EASEMENT SHALL BE A PREREQUISITE
TO SUBDIVISION PLAT RECORDATION. REFER TO TENTATIVE
CONDITION #11.
==================== END OF COMMENTS =======================
============================================================
============================================================
REVIEW DEPARTMENT : ENVIRONMENTAL ENGINEERING
REVIEWER/PHONE # : MARIA JENKINS/751-2335
NAME OF PLAN : CENTRALIA STATION
SITE PLAN NO. : 16CP0051
LATEST PLAN DATE : 04/13/16
DEPT. REC'D DATE : 04/20/16
SUBMITTAL NUMBER : 3
REVIEW DATE : 05/09/16
RECOMMENDATION : REVISIONS REQUIRED
TABLE REVISION : NO
PLAT PROCESSING : NO
1. IT IS THE RESPONSIBILITY OF THE APPLICANT TO COMPLY
WITH AND/OR ACQUIRE ALL APPLICABLE FEDERAL AND/OR STATE
PERMITS IN RELATIONSHIP TO ENVIRONMENTAL FEATURES INCLUDING
BUT NOT LIMITED TO WETLANDS, SURFACE WATERS (E.G. VSMP
PERMIT FOR CONSTRUCTION SITES, GROUND WATER AND AIR
QUALITY) FINAL APPROVAL OF THESE PLANS WILL NOT RELIEVE YOU
OF YOUR RESPONSIBILITY. WETLANDS DOCUMENTATION MUST BE
RECEIVED BY THIS DEPARTMENT PRIOR TO ISSUANCE OF THE LAND
DISTURBANCE PERMIT.
2. THIS OFFICE RECOGNIZES THAT THE 10-YEAR PRE/10-YEAR POST
REQUIREMENTS FOR FLOOD PROTECTION MAY BE ADDRESSED BY
DISCHARGING INTO THE 100-YEAR FLOODPLAIN.
=== EROSION CONTROL ===
1. AN ITEMIZED EROSION CONTROL COST ESTIMATE MUST BE
SUBMITED FOR REVIEW AND/OR APPROVAL.
2. AS A PREREQUISITE TO THE ISSUANCE OF A LAND
DISTURBANCE PERMIT:
A) A COPY OF THE AUTOCAD FILE MUST BE SUBMITTED TO
CAROLE CLIBORNE OF THE ENVIRONMENTAL ENGINEERING. THE
AUTOCAD FILE MUST BE SAVED AS A .DWG OR .DXF IN AUTOCAD
VERSION 2009 OR EARLIER AND REFERENCED DIRECTLY TO THE
VIRGINIA STATE PLANE COORDINATE SYSTEM, SOUTH ZONE IN
THE NAD83 DATUM. THE AUTOCAD FILE MAY BE SUBMITTED ON A
CD, DVD, OR VIA EMAIL AND MUST BE CLEARLY LABELED WITH
THE SUBDIVISION NAME AND SECTION, SUBDIVISION PLAN
NUMBER, ENGINEERING FIRM AND CAD FILE PREPARER'S NAME
AND PHONE NUMBER. THE FILE MUST CONTAIN THE FOLLOWING,
EACH CLEARLY LABELED IN SEPARATE LAYERS:
EDGES OF ROADS TO INCLUDE CURB AND GUTTER; AND
EDGES OF SIDEWALKS;
THE FILE MUST BE APPROVED BY ENVIRONMENTAL ENGINEERING
PRIOR TO ISSUANCE OF THE LAND DISTURBANCE PERMIT.
B) FLAGGING AROUND USACOE JURISDICTIONAL WETLANDS,
BUFFERS, AND SENSITIVE AREAS MUST BE VISIBLE.
C) DOCUMENTATION FROM THE USACOE/DEQ MUST BE RECEIVED
VERIFYING COMPLIANCE TO WETLAND PERMIT REGULATIONS.
D) A COPY OF VDOT LAND USE PERMIT MUST BE RECEIVED.
E) SAFETY FENCE AND/OR SUPER SILT FENCE WITH OPTIC
ORANGE FABRIC MUST BE IN PLACED ALONG THE RPA LIMITS.
F) AN EROSION CONTROL BOND MUST BE POSTED.
G) THE RISER AND BARREL PIPE ASSOCIATED WITH THE
SEDIMENT BASIN MUST BE ON-SITE.
H) TWO ADDITIONAL SETS OF CONSTRUCTION PLANS TO BE
STAMPED "APPROVED FOR CONSTRUCTION" MUST BE RECEIVED.
I) AS APPLICABLE, A SWPPP BOOKLET (3 RING BINDER) MUST
BE PROVIDED.
3. THESE ARE IN REGARDS TO THE MS-19:
A) ALTHOUGH NOT PREVIOUSLY REQUESTED, PLEASE PERFORM MS-
19 AT THE EXISTING ROADSIDE DITCH PERTINENT TO RAILROAD
NEAR THE OUTFALL STR. 131. INCLUDE 2/10-YEAR DITCH
CALCULATIONS WITH SCALED X-SECTIONS, SHOW/LABEL THE MS-19
SECTIONS-LOCATIONS ON THE PLANS AND UPDATE THE MS-19
TABLE TO INCLUDE THIS LOCATION.
IN ADDITION, PLEASE EXTEND THE EXISTING CONTOURS TO
INCLUDE THE ROADSIDE DITCH FROM THE POINT OF ANALYSIS TO
THE EXISTING 144" CMP WITH SUFFICIENT DISTANCE TO INCLUDE
DRAINAGE BREAKS/DRAINAGE AREAS. A FURTHER DISCUSSION IS
RECOMMENDED.
4. WE OFFER, BUT NOT LIMITED TO, THE FOLLOWING COMMENTS:
A) AS PREVIOUSLY REQUESTED, PLEASE BE SURE TO SHOW THE
GENERAL EROSION AND SEDIMENT CONTROL NOTES AND THE EC
LEGEND ON THE EC PLANS AS OPPOSED TO SHOWING ON THE
COVER SHEET. PLEASE ADDRESS.
B) ALTHOUGH NOT PREVIOUSLY REQUESTED, PLEASE BE SURE TO
PROVIDE SUPER SILT FENCE WITH OPTIC ORANGE FABRIC IN A
HORSESHOE CONFIGURATION TO BE LOCATED TO SURROUND THE
PLUNGE POOL /OUTLET PROTECTION PERTINENT TO STRUCTURES
37/89. (REQUESTED IN COMMENT#8 UNDER ROAD AND DRAINAGE).
IN ADDITION, PROVIDE SAFETY FENCE ON THE WESTERN SIDE OF
THE PLUNGE POOL/STR. 37 WITHIN THE LIMITS OF THE
PROPOSED VARIABLE WIDTH DRAINAGE EASEMENT. REFLECT THE
CHANGES ON THE EC PHASE I AND PHASE II.
SIMILARLY, PLEASE PROVIDE SAFETY FENCE WITHIN THE 16'
DRAINAGE EASEMENT/RPA PRIOR TO THE INSTALLATION OF THE
OUTFALL STRUCTURES 88/89. THE SAFETY FENCE SHOULD BE
LOCATED ALONG THE WESTERN AND EASTERN SIDE OF THE
OUTFALL STRUCTURES 88/89. REFLECT THE CHANGES ON THE EC
PHASE II.
C) PLEASE SHOW/LABEL THE NUMBER OF ACRES INTERCEPTED BY
THE BEST FIT SEDIMENT TRAP ON THE EC PHASE I AND PHASE
II. IN ADDITION, INCLUDE THE REQUIRED/PROVIDED WET/DRY
VOLUME AND DIMENSIONS OF THIS TRAP IN THE SEDIMENT TRAP
SCHEDULE TABLE. IF THIS TRAP DOES NOT MEET THE REQUIRED
WET/DRY VOLUME, REFER THE REVIEW COMMENTS DATED 03/21/16
ITEM 4.K UNDER EROSION CONTROL. A FURTHER DISCUSSION IS
RECOMMENDED.
D) PLEASE REVISE THE LIMITS OF DRAINAGE AREAS PERTINENT
TO THE ST1. BASED ON THE EXISTING TOPO (SHEET C-3), IT
APPEARS TO BE AN EXISTING DIRT ROAD WITH ROADSIDE
DITCH(ES) ALONG THIS ROAD LOCATED ON THE NORTHERN SIDE
OF ST1, THE LIMITS OF DRAINAGE AREAS SHOULD INCLUDE THIS
AREA. AS APPLICABLE, REVISE THE EC PHASE I/II, ST1
DIMENSIONS, ETC. TO REFLECT THE CHANGES.
E) THESE ARE IN REGARDS TO THE SEDIMENT BASIN 1:
E.1) PLEASE SHOW THE PLUNGE POOL ON THE EC PHASE I
PLANS.
E.2) AS A REMINDER, DEQ HAS EXPRESSED SOME CONCERNS
IN THE PAST FOR USING THIS ALTERNATIVE DESIGN/PLYWOOD
WEIR WITH DEWATERING DEVICE.
F) THESE ARE IN REGARDS TO THE SB#2:
F.1) IT APPEARS ANTI-SEEP COLLARS ARE REQUIRED ALONG THE
BARREL GREATER THE 10" IN DIAMETER. PLEASE REFER TO THE
VIRGINIA EROSION AND SEDIMENT CONTROL HANDBOOK CHAPTER
3.14 FOR SEDIMENT BASIN. AS APPLICABLE, INCLUDE ANTI-
SEEP COLLAR DETAILS, THE REQUIRE NUMBER OF ANTI-SEEP
COLLAR/SPACING ALONG THE BARREL IN THE SEDIMENT BASIN
SCHEMATIC DETAIL (SHEET C-12).
F.2) PLEASE REVISE THE SEDIMENT BASIN SCHEMATIC DETAIL
FOR SB#2 (SHEET C-12) TO REFLECT THE INFORMATION FOR THE
BARREL (I.E. INVERTS IN/OUT, MATERIAL, DIAMETER, LENGTH,
ETC.).
F.3) PLEASE REFER COMMENT #3 UNDER ROAD AND DRAINAGE
FOR ADDITIONAL COMMENTS REGARDING THE REMOVAL OF THIS
SB#2 AND DRAINAGE IMPROVEMENTS.
5. IF TIMBERING IS REQUIRED ON THE PROJECT, IT SHOULD BE
INCORPORATED INTO THE EROSION CONTROL PLAN / NARRATIVE AND
SHOULD NOT BEGIN UNTIL AFTER THE ISSUANCE OF A LAND
DISTURBANCE PERMIT AND THE INSTALLATION OF THE APPROVED
EROSION CONTROL DEVICES.
======= CBPA =======
1. PRIOR TO PLAN APPROVAL, CENTRALIA STATION PHASE II
TENTATIVE MUST BE APPROVED.
2. PRIOR TO PLAN APPROVAL THE REVISED OVERALL CBPA
TENTATIVE PLAN MUST BE APPROVED.
======= SWM/BMP =======
1. IT APPEARS TO BE A TYPO IN THE BAFFLE CONCRETE DETAIL
(SHEET C-23) FOR THE TOP ELEVATION OF 124.5.50 TO BE
124.50. REVISE ACCORDINGLY.
2. PLEASE REMOVE THE PLUNGE POOL DETAIL SHOWN ON SHEET C-
39A, SINCE THE DIMENSIONS SHOWN DO NOT MATCH WITH COUNTY
DIMENSIONS OF HAVING 18" DEPTH WITH 24" THICK LAYER OF
RIPRAP.
3. THESE ARE IN REGARDS TO LANDSCAPE FOR BMP#1 (SHEET C-
24):
A) IT APPEARS SOME SPECIES OF PLANTS WERE OMITTED IN THE
PLANTING SCHEDULE AND ON THE PLAN VIEWS (I.E. SWEETFLAG,
FRINGE SEDGE, WOODGRASS, ETC.). REVISE THE PLAN VIEWS
AND PLANTING SCHEDULE TO INCLUDE THESE SPECIES.
IN ADDITION, PLEASE REMOVE THE RICE CUTGRASS AND DUCK
POTATO FROM THE PLANTING SCHEDULE AND PLAN VIEW AS THESE
SPECIES ARE NOT IN THE APPROVED PLANTING SCHEDULE.
ADDITIONALLY, RICE CUTGRASS CANNOT BE PLANTING
INUNDATION OVER 3". THE AQUATIC BENCH PROVIDE
INUNDATIONS OF 12". REVISE ACCORDINGLY.
======= ROAD AND DRAINAGE =======
1. DUE TO THE ABSENCE OF CENTERLINE STAKING AND HEAVY
VEGETATION, OUR CONCERNS ARE BASED ON THE INFORMATION SHOWN
IN THE CONSTRUCTION PLANS. THE RESPONSIBILITY FOR
IDENTIFYING CRITICAL AREAS IS PLACED ON THE PROFESSIONAL
ENGINEER WHO SEALS THE CONSTRUCTION PLANS APPROVED. WE
RESERVE THE RIGHT TO INSPECT CONVEYANCE SYSTEMS PRIOR TO
PLAT RECORDATION AND/OR STATE ACCEPTANCE TO DETERMINE IF
ADDITIONAL IMPROVEMENTS ARE REQUIRED.
2. ALTHOUGH NOT PREVIOUSLY REQUESTED, PLEASE PROVIDE
DRIVEWAY ENTRANCE ON LOT 21. REFLECT THE CHANGES ON ALL
APPLICABLE SHEETS.
3. IT APPEARS THE STORM SEWER STR. 131 HAS BEEN EXTENDED,
(ALTHOUGH ADDITIONAL MEASURES WERE NOT SUGGESTED, SINCE
THIS OFFICE PRESUMED THAT A PROPOSED DITCH WAS GOING TO BE
PROVIDED).
IN THIS CASE, PLEASE SHOW THE PROPOSED FILL GRADING ON THE
GRADING PLAN (SHEET 20) REFLECTING TO FILL THE SEDIMENT
BASING FROM 117.00 CONTOUR-ELEVATION.
IN ADDITION, PROVIDE A NOTE IN THE GRADING PLAN (SHEETS C-
10 AND 20), SINCE NOW COMPACTED FILL MATERIAL IS REQUIRED
PRIOR TO THE INSTALLATION OF THE STORM SEWER PIPE FOR
STABILITY, STATING "UNSUITABLE/SATURATED SOILS FROM THE
BOTTOM OF THE BASIN SHOULD BE REMOVED PRIOR TO THE
PLACEMENT OF STRUCTURAL FILL MATERIAL. THE AREA SHALL BE
RECLAIMED TO MATCH EXISTING GRADE BEING SURE TO CREATE
POSITIVE DRAINAGE. FILL SHALL BE COMPACTED AND TESTED IN 6"
LIFT."
FURTHERMORE, PLEASE ENCLOSE THE STORM SEWER STR. 131 IN A
16' DRAINAGE EASEMENT. REFLECT THE CHANGES ON ALL
APPLICABLE SHEETS.
4. PER RECENT TELEPHONE CONVERSATION ON 05/05/16, IF A
PROPOSED DITCH IS GOING TO BE PROVIDED INSTEAD OF THE
EXTENSION OF THE STORM SEWER STR. 131, PLEASE SEE THE
FOLLOWING SUGGESTIONS:
A) PLEASE REVISE THE GRADING PLAN TO SHOW THE PROPOSED
GRADING FOR THE FILL AREAS AND THE GRADING PERTINENT TO
THIS PROPOSED DITCH. IN ADDITION, PROVIDE AN ENERGY
DISSIPATER PIT AT 0% SLOPE AT THE END OF THIS DITCH
IMPROVEMENT. BE SURE TO ENCLOSE THIS DITCH
IMPROVEMENTS/ENERGY DISSIPATER PIT IN A 16' DRAINAGE
EASEMENT. REFLECT THE CHANGES ON ALL APPLICABLE SHEETS.
B) SUBMIT 10/100-YEAR DITCH CALCULATIONS FOR FURTHER
REVIEW AND/OR APPROVAL.
C) PROVIDE A PROFILE OF THIS DITCH WITH PERTINENT
INFORMATION (I.E. TYPICAL DITCH DESIGN OF 3:1 SIDE
SLOPE, DESIGN DEPTH, %SLOPE, LINING, ETC.).
4. THE ADJACENT PROPERTY OWNERS: SPRUILL, P. AT 4401
CHIPPOKE RD., STANEART, R. AT 4407 CHIPPOKE RD., STANDEFER,
E. AT 4413 CHIPPOKE RD., BANKS, K. AT 4419 CHIPPOKE RD.,
FINKLEA, C. AT 4501 CHIPPOKE RD., HOBBS, R. AT 4421
CENTRALIA RD., TAYLOR, H. AT 10221 CENTRALIA STATION,
CLEMENTS, L. AT 10210 CENTRALIA STATION, TUNSTALL, J. AT
10300 CENTRALIA STATION, ETC. SHOULD BE NOTIFIED OF THE
IMPEDING CONSTRUCTION ACTIVITY NEAR THEIR PROPERTIES. THE
NOTIFICATION SHOULD BE VIA U.S. POSTAL CERTIFIED MAIL,
SIGNED RETURN RECEIVED REQUEST. THIS CONCERN MUST BE
ADDRESSED PRIOR TO PLAN APPROVAL PER TENTATIVE CONDITION
#16.INCLUDE AN 8½ X 11 COPY OF THE PROPOSED CONSTRUCTION
ACTIVITY ADJACENT TO THEIR PROPERTIES.
5. PER TENTATIVE CONDITION #11, WHICH STATES, "APPROVAL OF
THE ROAD AND DRAINAGE PLANS BY DOMINION VIRGINIA POWER IN
RELATION TO ITS EASEMENT AND FACILITIES THEREIN IS A
PREREQUISITE TO CONSTRUCTION PLAN APPROVAL BY THE
ENVIRONMENTAL ENGINEERING DEPARTMENT. A QUITCLAIM TO VDOT
OR A SATISFACTORY COMMITMENT THEREOF BY DOMINION VIRGINIA
POWER FOR THE LOCATIONS WHERE CENTRALIA STATION ROAD,
RIGHT-OF-WAY WILL CROSS THE DOMINION VIRGINIA POWER
EASEMENT SHALL BE A PREREQUISITE TO SUBDIVISION PLAT
RECORDATION."
6. PLEASE REVISE THE PROPOSED 16' DRAINAGE EASEMENT THAT IS
ENCLOSING THE STORM SEWER STRUCTURES 7 THRU 9 TO INCLUDE
THE STORM SEWER STRUCTURES 10/10A. IN ADDITION, REMOVE A
PORTION OF THIS EASEMENT BELOW STR. 9, SINCE IT IS NO
LONGER APPLICABLE. REFLECT THE CHANGES ON ALL APPLICABLE
SHEETS.
7. THESE ARE IN REGARDS TO THE EMERGENCY ACCESS ROAD:
A) AS PREVIOUSLY REQUESTED, PLEASE CONSIDER PROVIDING
ONE ROADSIDE DITCH ALONG THE SOUTHERN SIDE OF THIS
EMERGENCY ACCESS ROAD AND GRADE THE ROAD TO DRAIN
TOWARDS THIS ROADSIDE DITCH TO ELIMINATE THE NEED FOR A
CULVERT NEAR THE CUL-DE-SAC PERTINENT TO CENTRALIA
STATION ROAD. REVISE THE PLANS, PROFILES, THE TYPICAL
EMERGENCY ACCESS ROAD DETAIL, ETC. TO REFLECT THE
CHANGES.
IN ADDITION, CONTINUE THIS ROADSIDE DITCH UNTIL IT
CONNECTS TO THE PROPOSED DITCH SPECIFIED ON THE REAR OF
LOTS 36 THRU 40. BE SURE TO SPECIFY THE RADIUS AT THE
TURN(S) OF THIS DITCH.
ADDITIONALLY, REVISE THE TYPICAL EMERGENCY ACCESS ROAD
DETAIL TO SHOW ONE ROADSIDE DITCH AS OPPOSED TO TWO AND
SHOW THE PROPOSED GRADE TYING BACK TO THE EXISTING GRADE
WHERE THERE WON'T BE A ROADSIDE DITCH.
B) THIS OFFICE WAS NOT ABLE TO VERIFY THE INCREMENTAL
DRAINAGE AREAS ALONG THE PROPOSED ROADSIDE DITCH
SPECIFIED ALONG THE SOUTHERN SIDE OF THE EMERGENCY
ACCESS ROAD, SINCE THE LIMITS OF DRAINAGE AREAS/ACREAGE
WERE OMITTED ON SHEET C-27.
IN ADDITION, BE SURE TO SHOW/LABEL THE EXISTING CONTOURS
WITH ELEVATIONS WITH SUFFICIENT DISTANCE TO INCLUDE
DRAINAGE BREAKS WITHIN THE AREAS DRAINING TO THE
EMERGENCY ACCESS ROAD ON SHEET C-27.
C) AS PREVIOUSLY REQUESTED, SHOW/LABEL THE CENTERLINE
STATIONING AT EVERY 100' ALONG THIS EMERGENCY ACCESS
ROAD ON SHEET C-27 AND BE SURE THE STATIONING SHOWN ON
THE PLAN VIEW/PROFILE VIEWS MATCH.
D) AS PREVIOUSLY REQUESTED, PLEASE SHOW THE ROADSIDE
DITCH IN THE EMERGENCY ACCESS ROAD PROFILE (SHEET C-33A)
WITH PERTINENT INFORMATION (I.E. TYPICAL DITCH, LINING,
DEPTH, %SLOPE, ETC.).
E) AS PREVIOUSLY REQUESTED, PROVIDE 10-YEAR ENTRANCE
CULVERT WITH SUPPORT CALCULATIONS ON STANDARD VDOT FORM.
BE SURE 10-YEAR HW/D<1. BE SURE TO SHOW THE INCREMENTAL
DRAINAGE AREAS, ETC. ON THE PLANS.
IN ADDITION, BE SURE TO SHOW THE PERTINENT INFORMATION
OF THIS PIPE ON THE PLANS (I.E. 20' MINIMUM LENGTH, RCP
CLASS III, DIAMETER, ETC.).
F) AS PREVIOUSLY REQUESTED, SHOW/LABEL THE EXISTING AND
PROPOSED CONTOURS WITH ELEVATIONS. BE SURE TO INCLUDE
ENOUGH AREA OF THE CONTOURED TOPOGRAPHY TO VERIFY
DRAINAGE BREAKS/DRAINAGE PATTERN ONSITE/OFFSITE.
8. THERE APPEARS TO BE A DISCREPANCY REGARDING THE EXISTING
GRADING LOCATED DOWNSTREAM OF THE OUTFALL PIPE STR. 37 WHEN
COMPARING THE STORM 31 - 37 PROFILE WITH THE SANITARY 8 -
EX PROFILE. IN THE 31-37 PROFILE SHOW THE EXISTING GRADING
TO BE AROUND 116.45 ELEVATION AND IN THE SANITARY 8 - EX
PROFILE IN THE PROXIMITY OF STATION 15+00 SHOW AROUND
119.00 ELEVATION.
ASSUMING IF THE SANITARY 8 - EX PROFILE IS CORRECT, THEN
THERE IS NO DAYLIGHT AT THE OUTFALL PIPE STR. 37/OUTLET
PROTECTION.
IF THAT IS THE CASE, PLEASE REVISE THE EXISTING GRADING
DOWNSTREAM OF STR. 37 IN THE 31 - 37 PROFILE TO BE AROUND
119.00 AND CONSIDER PROVIDING AN 18" DEPTH PLUNGE POOL AS
OPPOSED TO OUTLET PROTECTION TO ALLOW THE OUTFALL PIPE TO
BE PARTIALLY SUBMERGED.
ADDITIONALLY, REVISE THE PLAN VIEWS TO CLEARLY SHOW 1'
PROPOSED CONTOURS FROM THE OUTFALL PIPE/WITHIN THE PLUNGE
POOL AREA TO THE LIMITS OF THE WETLANDS. BE SURE THESE
IMPROVEMENTS ARE WITHIN THE VARIABLE WIDTH DRAINAGE
EASEMENT. A FURTHER DISCUSSION IS RECOMMENDED. A BLOWOUT
DETAIL DRAWN TO SCALE MAY BE NEEDED.
9. PLEASE BE SURE THE INFORMATION FOR THE STORM SEWER(S)
SHOWN ON PROFILES (I.E. STR. 37 INVERT-OUT=116.45, ETC.),
COMPUTATIONS SHEETS (I.E. STR. 37 INVERT-OUT=116.00),
DRAINAGE DESCRIPTION SCHEDULE, ETC. IS ACCURATE.
10. BASED ON THE PROFILES STORM 62 - 63 (SHEET C-34), STORM
87 - 89 (SHEET C-35), ETC. FILL OVER THE PIPE HAS BEEN
SPECIFIED BE SURE TO SHOW PROPOSED GRADING ON THE GRADING
PLAN. ADDITIONAL EROSION CONTROL MEASURES MAY BE REQUIRED
(I.E. SUPER SILT FENCE, ETC.).
11. THESE ARE IN REGARDS TO THE 100-YEAR FEMA FLOODPLAIN:
A) AS PREVIOUSLY REQUESTED, PLEASE SHOW THE 100-YEAR
FEMA FLOODPLAIN SECTIONS-LOCATIONS WITH ELEVATIONS ALONG
THE GREAT BRANCH CREEK.
12. THESE ARE IN REGARDS TO THE PROFILES:
A) AS PREVIOUSLY REQUESTED, PLEASE BE SURE TO SHOW/LABEL
THE LIMITS OF THE 100-YEAR FLOODPLAIN, 100-YEAR
BACKWATER, 100-YEAR FEMA FLOOD PLAIN, RPA, ETC. ON ALL
APPLICABLE PROFILES (I.E. STORM 41-47 PROFILE, STORM 15-
19 PROFILE, STORM 38-40 PROFILE, STROM 90-91 PROFILE,
125-131 PROFILE, ETC.).
THE LIMITS OF THE PROPERTY LINE SHOULD BE SHOWN ON THE
STROM 15-19 PROFILE TO ENSURE THE DRAINAGE IMPROVEMENTS
ARE WITHIN THE LIMITS OF THIS SECTION.
13. AS A PREREQUISITE TO SUBDIVISION PLAT RECORDATION:
A) THE $100/LOT BMP MAINTENANCE FEE MUST BE RECEIVED.
B) APPROVED BONDING AND RECORDED EASEMENTS WITH DEED
BOOK AND PAGE NUMBER FOR THE SWM/BMP WETPOND MUST BE
PROVIDED.
C) A QUITCLAIM TO VDOT OR A SATISFACTORY COMMITMENT
THEREOF BY DOMINION VIRGINIA POWER FOR THE LOCATIONS
WHERE CENTRALIA STATION ROAD, RIGHT-F-WAY WILL CROSS THE
DOMINION VIRGINIA POWER EASEMENT SHALL BE A PREREQUISITE
TO SUBDIVISION PLAT RECORDATION. REFER TO TENTATIVE
CONDITION #11.
==================== END OF COMMENTS =======================
============================================================
============================================================
REVIEW DEPARTMENT : ENVIRONMENTAL ENGINEERING
REVIEWER/PHONE # : MARIA JENKINS/751-2335
NAME OF PLAN : CENTRALIA STATION
SITE PLAN NO. : 16CP0051
LATEST PLAN DATE : 05/26/16
DEPT. REC'D DATE : 06/01/16
SUBMITTAL NUMBER : 4
REVIEW DATE : 06/01/16
RECOMMENDATION : NOT APPROVED PER TENTATIVE CONDITION
#11. PLEASE PROVIDE A COPY OF THE
APPROVAL LETTER FROM DOMINION POWER.
TABLE REVISION : NO
PLAT PROCESSING : NO
1. IT IS THE RESPONSIBILITY OF THE APPLICANT TO COMPLY
WITH AND/OR ACQUIRE ALL APPLICABLE FEDERAL AND/OR STATE
PERMITS IN RELATIONSHIP TO ENVIRONMENTAL FEATURES INCLUDING
BUT NOT LIMITED TO WETLANDS, SURFACE WATERS (E.G. VSMP
PERMIT FOR CONSTRUCTION SITES, GROUND WATER AND AIR
QUALITY) FINAL APPROVAL OF THESE PLANS WILL NOT RELIEVE YOU
OF YOUR RESPONSIBILITY. WETLANDS DOCUMENTATION MUST BE
RECEIVED BY THIS DEPARTMENT PRIOR TO ISSUANCE OF THE LAND
DISTURBANCE PERMIT.
2. THIS OFFICE RECOGNIZES THAT THE 10-YEAR PRE/10-YEAR POST
REQUIREMENTS FOR FLOOD PROTECTION MAY BE ADDRESSED BY
DISCHARGING INTO THE 100-YEAR FLOODPLAIN.
=== EROSION CONTROL ===
1. AN ITEMIZED EROSION CONTROL COST ESTIMATE MUST BE
SUBMITED FOR REVIEW AND/OR APPROVAL.
2. AS A PREREQUISITE TO THE ISSUANCE OF A LAND
DISTURBANCE PERMIT:
A) A COPY OF THE AUTOCAD FILE MUST BE SUBMITTED TO
CAROLE CLIBORNE OF THE ENVIRONMENTAL ENGINEERING. THE
AUTOCAD FILE MUST BE SAVED AS A .DWG OR .DXF IN AUTOCAD
VERSION 2009 OR EARLIER AND REFERENCED DIRECTLY TO THE
VIRGINIA STATE PLANE COORDINATE SYSTEM, SOUTH ZONE IN
THE NAD83 DATUM. THE AUTOCAD FILE MAY BE SUBMITTED ON A
CD, DVD, OR VIA EMAIL AND MUST BE CLEARLY LABELED WITH
THE SUBDIVISION NAME AND SECTION, SUBDIVISION PLAN
NUMBER, ENGINEERING FIRM AND CAD FILE PREPARER'S NAME
AND PHONE NUMBER. THE FILE MUST CONTAIN THE FOLLOWING,
EACH CLEARLY LABELED IN SEPARATE LAYERS:
EDGES OF ROADS TO INCLUDE CURB AND GUTTER; AND
EDGES OF SIDEWALKS;
THE FILE MUST BE APPROVED BY ENVIRONMENTAL ENGINEERING
PRIOR TO ISSUANCE OF THE LAND DISTURBANCE PERMIT.
B) FLAGGING AROUND USACOE JURISDICTIONAL WETLANDS,
BUFFERS, AND SENSITIVE AREAS MUST BE VISIBLE.
C) DOCUMENTATION FROM THE USACOE/DEQ MUST BE RECEIVED
VERIFYING COMPLIANCE TO WETLAND PERMIT REGULATIONS.
D) A COPY OF VDOT LAND USE PERMIT MUST BE RECEIVED.
E) SAFETY FENCE AND/OR SUPER SILT FENCE WITH OPTIC
ORANGE FABRIC MUST BE IN PLACED ALONG THE RPA LIMITS.
F) AN EROSION CONTROL BOND MUST BE POSTED.
G) THE RISER AND BARREL PIPE ASSOCIATED WITH THE
SEDIMENT BASIN MUST BE ON-SITE.
H) TWO ADDITIONAL SETS OF CONSTRUCTION PLANS TO BE
STAMPED "APPROVED FOR CONSTRUCTION" MUST BE RECEIVED.
I) AS APPLICABLE, A SWPPP BOOKLET (3 RING BINDER) MUST
BE PROVIDED.
4. WE OFFER, BUT NOT LIMITED TO, THE FOLLOWING COMMENTS:
E) THESE ARE IN REGARDS TO THE SEDIMENT BASIN 1:
E.1) AS A REMINDER, DEQ HAS EXPRESSED SOME CONCERNS
IN THE PAST FOR USING THIS ALTERNATIVE DESIGN/PLYWOOD
WEIR WITH DEWATERING DEVICE.
======= ROAD AND DRAINAGE =======
1. DUE TO THE ABSENCE OF CENTERLINE STAKING AND HEAVY
VEGETATION, OUR CONCERNS ARE BASED ON THE INFORMATION SHOWN
IN THE CONSTRUCTION PLANS. THE RESPONSIBILITY FOR
IDENTIFYING CRITICAL AREAS IS PLACED ON THE PROFESSIONAL
ENGINEER WHO SEALS THE CONSTRUCTION PLANS APPROVED. WE
RESERVE THE RIGHT TO INSPECT CONVEYANCE SYSTEMS PRIOR TO
PLAT RECORDATION AND/OR STATE ACCEPTANCE TO DETERMINE IF
ADDITIONAL IMPROVEMENTS ARE REQUIRED.
2. PER TENTATIVE CONDITION #11, WHICH STATES, "APPROVAL OF
THE ROAD AND DRAINAGE PLANS BY DOMINION VIRGINIA POWER IN
RELATION TO ITS EASEMENT AND FACILITIES THEREIN IS A
PREREQUISITE TO CONSTRUCTION PLAN APPROVAL BY THE
ENVIRONMENTAL ENGINEERING DEPARTMENT. A QUITCLAIM TO VDOT
OR A SATISFACTORY COMMITMENT THEREOF BY DOMINION VIRGINIA
POWER FOR THE LOCATIONS WHERE CENTRALIA STATION ROAD,
RIGHT-OF-WAY WILL CROSS THE DOMINION VIRGINIA POWER
EASEMENT SHALL BE A PREREQUISITE TO SUBDIVISION PLAT
RECORDATION."
3. AS A PREREQUISITE TO SUBDIVISION PLAT RECORDATION:
A) THE $100/LOT BMP MAINTENANCE FEE MUST BE RECEIVED.
B) APPROVED BONDING AND RECORDED EASEMENTS WITH DEED
BOOK AND PAGE NUMBER FOR THE SWM/BMP WETPOND MUST BE
PROVIDED.
C) A QUITCLAIM TO VDOT OR A SATISFACTORY COMMITMENT
THEREOF BY DOMINION VIRGINIA POWER FOR THE LOCATIONS
WHERE CENTRALIA STATION ROAD, RIGHT-F-WAY WILL CROSS THE
DOMINION VIRGINIA POWER EASEMENT SHALL BE A PREREQUISITE
TO SUBDIVISION PLAT RECORDATION. REFER TO TENTATIVE
CONDITION #11.
==================== END OF COMMENTS =======================
============================================================
============================================================
REVIEW DEPARTMENT : ENVIRONMENTAL ENGINEERING
REVIEWER/PHONE # : MARIA JENKINS/751-2335
NAME OF PLAN : CENTRALIA STATION
SITE PLAN NO. : 16CP0051
LATEST PLAN DATE : 05/26/16
DEPT. REC'D DATE : 06/01/16
SUBMITTAL NUMBER : 4
REVIEW DATE : 06/02/16
RECOMMENDATION : APPROVED
TABLE REVISION : YES
PLAT PROCESSING : NO
1. IT IS THE RESPONSIBILITY OF THE APPLICANT TO COMPLY
WITH AND/OR ACQUIRE ALL APPLICABLE FEDERAL AND/OR STATE
PERMITS IN RELATIONSHIP TO ENVIRONMENTAL FEATURES INCLUDING
BUT NOT LIMITED TO WETLANDS, SURFACE WATERS (E.G. VSMP
PERMIT FOR CONSTRUCTION SITES, GROUND WATER AND AIR
QUALITY) FINAL APPROVAL OF THESE PLANS WILL NOT RELIEVE YOU
OF YOUR RESPONSIBILITY. WETLANDS DOCUMENTATION MUST BE
RECEIVED BY THIS DEPARTMENT PRIOR TO ISSUANCE OF THE LAND
DISTURBANCE PERMIT.
2. THIS OFFICE RECOGNIZES THAT THE 10-YEAR PRE/10-YEAR POST
REQUIREMENTS FOR FLOOD PROTECTION MAY BE ADDRESSED BY
DISCHARGING INTO THE 100-YEAR FLOODPLAIN.
=== EROSION CONTROL ===
1. AN ITEMIZED EROSION CONTROL COST ESTIMATE MUST BE
SUBMITED FOR REVIEW AND/OR APPROVAL.
2. AS A PREREQUISITE TO THE ISSUANCE OF A LAND
DISTURBANCE PERMIT:
A) A COPY OF THE AUTOCAD FILE MUST BE SUBMITTED TO
CAROLE CLIBORNE OF THE ENVIRONMENTAL ENGINEERING. THE
AUTOCAD FILE MUST BE SAVED AS A .DWG OR .DXF IN AUTOCAD
VERSION 2009 OR EARLIER AND REFERENCED DIRECTLY TO THE
VIRGINIA STATE PLANE COORDINATE SYSTEM, SOUTH ZONE IN
THE NAD83 DATUM. THE AUTOCAD FILE MAY BE SUBMITTED ON A
CD, DVD, OR VIA EMAIL AND MUST BE CLEARLY LABELED WITH
THE SUBDIVISION NAME AND SECTION, SUBDIVISION PLAN
NUMBER, ENGINEERING FIRM AND CAD FILE PREPARER'S NAME
AND PHONE NUMBER. THE FILE MUST CONTAIN THE FOLLOWING,
EACH CLEARLY LABELED IN SEPARATE LAYERS:
EDGES OF ROADS TO INCLUDE CURB AND GUTTER; AND
EDGES OF SIDEWALKS;
THE FILE MUST BE APPROVED BY ENVIRONMENTAL ENGINEERING
PRIOR TO ISSUANCE OF THE LAND DISTURBANCE PERMIT.
B) FLAGGING AROUND USACOE JURISDICTIONAL WETLANDS,
BUFFERS, AND SENSITIVE AREAS MUST BE VISIBLE.
C) DOCUMENTATION FROM THE USACOE/DEQ MUST BE RECEIVED
VERIFYING COMPLIANCE TO WETLAND PERMIT REGULATIONS.
D) A COPY OF VDOT LAND USE PERMIT MUST BE RECEIVED.
E) SAFETY FENCE AND/OR SUPER SILT FENCE WITH OPTIC
ORANGE FABRIC MUST BE IN PLACED ALONG THE RPA LIMITS.
F) AN EROSION CONTROL BOND MUST BE POSTED.
G) THE RISER AND BARREL PIPE ASSOCIATED WITH THE
SEDIMENT BASIN MUST BE ON-SITE.
H) TWO ADDITIONAL SETS OF CONSTRUCTION PLANS TO BE
STAMPED "APPROVED FOR CONSTRUCTION" MUST BE RECEIVED.
I) AS APPLICABLE, A SWPPP BOOKLET (3 RING BINDER) MUST
BE PROVIDED.
3. THE MS-19 VARIANCE REQUEST LETTER DATED 02/26/16 FOR MS-
19 SECTIONS A THRU D HAVE BEEN APPROVED.
4. WE OFFER, BUT NOT LIMITED TO, THE FOLLOWING COMMENTS:
E) THESE ARE IN REGARDS TO THE SEDIMENT BASIN 1:
E.1) AS A REMINDER, DEQ HAS EXPRESSED SOME CONCERNS
IN THE PAST FOR USING THIS ALTERNATIVE DESIGN/PLYWOOD
WEIR WITH DEWATERING DEVICE.
======= ROAD AND DRAINAGE =======
1. DUE TO THE ABSENCE OF CENTERLINE STAKING AND HEAVY
VEGETATION, OUR CONCERNS ARE BASED ON THE INFORMATION SHOWN
IN THE CONSTRUCTION PLANS. THE RESPONSIBILITY FOR
IDENTIFYING CRITICAL AREAS IS PLACED ON THE PROFESSIONAL
ENGINEER WHO SEALS THE CONSTRUCTION PLANS APPROVED. WE
RESERVE THE RIGHT TO INSPECT CONVEYANCE SYSTEMS PRIOR TO
PLAT RECORDATION AND/OR STATE ACCEPTANCE TO DETERMINE IF
ADDITIONAL IMPROVEMENTS ARE REQUIRED.
2. AS A PREREQUISITE TO SUBDIVISION PLAT RECORDATION:
A) THE $100/LOT BMP MAINTENANCE FEE MUST BE RECEIVED.
B) APPROVED BONDING AND RECORDED EASEMENTS WITH DEED
BOOK AND PAGE NUMBER FOR THE SWM/BMP WETPOND MUST BE
PROVIDED.
C) A QUITCLAIM TO VDOT OR A SATISFACTORY COMMITMENT
THEREOF BY DOMINION VIRGINIA POWER FOR THE LOCATIONS
WHERE CENTRALIA STATION ROAD, RIGHT-F-WAY WILL CROSS THE
DOMINION VIRGINIA POWER EASEMENT SHALL BE A PREREQUISITE
TO SUBDIVISION PLAT RECORDATION. REFER TO TENTATIVE
CONDITION #11.
==================== END OF COMMENTS =======================