Thanksgiving Holiday Closings... MORE

Hover here for Site Tools
Subdivision Review Comments
All Subdivision Review Comments for Case # 15CP0075




For VDOT’s comments please contact Virginia Department of Transportation at (804) 674-2814 or send e-mail to Boris.Solomonov@VDOT.Virginia.gov

For Tentative Subdivision resubmittals:

1. Please note that submittal fees include the original submittal and two (2) additional reviews.

2. A letter of transmittal is required to accompany each submittal.

3. Please verify that Environmental Engineering, Fire, CDOT, VDOT, and Planning have reviewed the submittal before resubmitting. A resubmittal tendered, prior to receiving all the required departments’ review, will be counted as an additional submittal. Go to Case Selection Form or Go to Project List


 
CASE NO: 15CP0075 STATUS: PENDING APPROVAL
PROJECT NAME: IRON MILL SEC 5 - LAST INTERNET UPDATE: 11/22/17
SUBMITTAL TYPE: CONSTRUCTION PLAN
DEPARTMENT...REV..ROUTED..RESPONSE..STATUS....DATE...RVW..PHONE
ASSESSOR----: 00 02/20/15 03/13/15 ******** ********
ENVIR.ENGR.-: 01 05/19/15 06/09/15 COMPLETE 06/08/15 JFH 796-7103
FIRE DEPT.--: 01 05/19/15 06/09/15 AMENDED* 05/27/15 JKL 748-1489
HOUSE NUMBER: 00 02/20/15 03/13/15 ******** ********
MAPPING/GIS-: 00 02/20/15 03/13/15 ******** ********
PLANNING----: 01 05/19/15 06/09/15 COMPLETE 06/15/15 GWK 706-7691
TRANSPORT.--: 01 05/19/15 06/09/15 COMPLETE 06/02/15 SES 751-4912
UTIL.PLAN.--: 01 05/19/15 06/09/15 ******** ********
UTILITIES---: 01 05/19/15 06/09/15 ******** 03/03/15 WBV 748-1343
UTIL.R.O.W.-: 01 05/19/15 06/09/15 ******** ********
VDOT--------: 01 05/19/15 06/09/15 ******** ********
REVIEW DEPARTMENT: UTILITIES
REVIEW/PHONE #: BILL VIER/748-1343
PLAN NAME: IRON MILL, SECTION 5
PLAN NUMBER: 15CP0075
ORIGINAL PLAN DATE: 1/13/09
REVIEW DATE: 3/3/15
LATEST SUBMISSION DATE: 2/20/15
SUBMITTAL NUMBER: 1
STATUS: REVISIONS REQUIRED
TABLE REVIEW: NO
IN REGARD TO YOUR SUBMITTAL OF UTILITIES PLANS FOR THE
ABOVE REFERENCED PROJECT DATED JANUARY 13, 2009, WITH
THE LATEST REVISION DATED JANUARY 9, 2015, WE MAKE THE
FOLLOWING COMMENTS AND RECOMMENDATIONS:
1. A COPY OF VIRGINIA DEPARTMENT OF TRANSPORTATION'S
APPROVAL LETTER REGARDING PAVEMENT REPLACEMENT, METHOD OF
CROSSING, AND ALIGNMENT OF UTILITY WITH STATE RIGHT OF
WAY, AND A COPY OF ENVIRONMENTAL ENGINEERING'S INITIAL
REVIEW LETTER MUST BE SUBMITTED BEFORE REVISED PLANS ARE
SUBMITTED FOR RE-REVIEW.
2. PRIOR TO RELEASING TO THE CONSTRUCTION SECTION, A
COPY OF THE ENVIRONMENTAL ENGINEERING APPROVAL LETTER
AND/OR ALL OTHER APPLICABLE LOCAL STATE AND FEDERAL
AGENCIES' APPROVAL LETTERS MUST BE RECEIVED BY THIS
DEPARTMENT. IN ADDITION, ALL EASEMENTS NOT INCLUDED WITH
THE SUBDIVISION PLAT MUST BE DEDICATED WITH A SEPARATE
PLAT AND AGREEMENT TO THE COUNTY PRIOR TO RELEASING THE
PROJECT TO THE CONSTRUCTION SECTION.
3. SHOW THE COUNTY PROJECT NUMBER 15-0058 ON THE LOWER
RIGHT HAND CORNER OF EACH SHEET.
4. FIELD VERIFY THE TOP AND ALL INVERT ELEVATIONS OF THE
PROPOSED TIE IN MANHOLE REFLECTING THE FIELD DATA ON THE
PLANS.
5. DUCTILE IRON WATERLINE LOCATED IN FILL SECTIONS IS TO
BE SPECIFIED AS CLASS 52 MINIMUM.
6. RELOCATE THE PROPOSED 1" IRRIGATION METER SUCH THAT
IT IS IN OPEN SPACE AND PROVIDE A SIGNED, COMPLETED,
"WATER METER SIZING FORM" FOR IT.'
7. EXAMINE THE NUMBER OF WATER AND SEWER SERVICES FOR
ACCURACY, REVISING AS NECESSARY.
8. THOROUGHLY EXAMINE ALL SHEETS TO CORRECT ALL
EXTRANEOUS MARKINGS, OVERLAPPING TEXT, ILLEGIBLE TEXT AND
DRAWING FEATURES, ETC. IN ORDER TO FACILITATE A CLEAN
DRAWING WITH ALL TEXT AND DRAWING FEATURES COMPLETELY
LEGIBLE AND ABUNDANTLY VISIBLE.
9. REVISE THE "MATERIALS LIST" AS NECESSARY.
PLEASE MAKE ALL OF THE SUGGESTED CHANGES PREVIOUSLY
MENTIONED, AND SUBMIT ONE (1) SET OF REVISED PLANS.
THE OWNER MUST ENTER INTO A COUNTY CONTRACT PRIOR TO THE
START OF CONSTRUCTION. PLEASE SEND ME A COPY OF THE
"ACCEPTED" BID PROPOSAL BETWEEN THE DEVELOPER AND THE
CONTRACTOR SO WE MAY PREPARE THE COUNTY CONTRACT. THE BID
PROPOSAL MUST BE BASED ON THE LATEST REVISED UTILITIES
PLANS REFLECTING THE REVIEWER'S STAMP, AND ALL WORK MUST
BE PERFORMED BY AN ACCEPTABLE UTILITIES CONTRACTOR. IF
PLANS ARE REVISED AFTER CONTRACT PREPARATION DUE TO A
CHANGE BECAUSE OF VIRGINIA DEPARTMENT OF TRANSPORTATION'S
AND/OR ENVIRONMENTAL ENGINEERING DEPARTMENT'S APPROVAL OF
THE ROAD, DRAINAGE, AND EROSION CONTROL DESIGN OR BECAUSE
OF STATE AGENCIES' REVIEW AND APPROVAL OF THE UTILITIES
DESIGN, A REVISED BID PROPOSAL MAY BE NECESSARY TO
ACCURATELY REFLECT THE LATEST UTILITIES DESIGN AND A NEW
CONTRACT PREPARATION MAY BE NECESSARY AND EXECUTED PRIOR
TO THE START OF CONSTRUCTION.
IF YOU HAVE ANY QUESTIONS, DO NOT HESITATE TO CONTACT ME
AT 748-1343.
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
REVIEW DEPARTMENT: CHESTERFIELD TRANSPORTATION DEPARTMENT
REVIEWER/PHONE#: STEVEN E. SIMONSON, P.E. (804)748-1037
NAME OF PLAN: IRON MILL, SEC 5
CASE NUMBER: 15CP0075
LATEST PLAN DATE: 01/09/15
DEPT. REC'D. DATE: 02/24/15
SUBMITTAL NUMBER: ONE
REVIEW DATE: 03/09/15
RECOMMENDATION: APPROVED
TABLE REVIEW: YES
REVIEW DEPARTMENT: CHESTERFIELD TRANSPORTATION DEPARTMENT
REVIEWER/PHONE#: STEVEN E. SIMONSON, P.E. (804)748-1037
NAME OF PLAN: IRON MILL, SEC 5
CASE NUMBER: 15CP0075
LATEST PLAN DATE: 05/12/15
DEPT. REC'D. DATE: 05/20/15
SUBMITTAL NUMBER: TWO
REVIEW DATE: 06/02/15
RECOMMENDATION: APPROVED
TABLE REVIEW: YES
PLANNING DEPARTMENT
CONSTRUCTION PLAN: IRON MILL, SECTION 2
CASE: 15CP0075
REVIEWED BY: WHIT KIRTLEY (706-7691)
SUBMITTAL: 1
REVIEW DATE: 3/18/15
REVISION DATE: 1/9/15
PLANNING REVIEW #: 1
PLANNING STATUS: REVISIONS REQUIRED
COMMENTS & REVISIONS:
1. SUBMIT AN ELEVATION PLAN FOR THE 3 AND 5 UNIT MODEL
PLAN FOR SECTION 2 SHOWING THE STREET TREE PLAN AND UNIT
PLANTING PLAN. FOR THE STREET TREE PLAN, SHOW TREE
PLACEMENT IN CONJUNCTION WITH PROPOSED DRIVEWAYS,
PER SEC. 19-518(H). STREET TREE BONDING WILL BE
REQUIRED WITH EACH CORRESPONDING SECTION PRIOR TO
RECORD PLAT SUBMITTAL.
2. THE LOT NUMBERS ON THE FINAL CHECK AND RECORD PLAT
SHALL DESIGNATE ANY DWELLING IN LAND BAY 3 THAT IS
LESSTHAN 1,700 SQUARE FEET.
3. ON THE FINAL PLAT, INDICATED WHICH LOTS ARE TO HAVE
SIDELOAD AND FRONT LOAD GARAGES
4. STREET TREE BONDING WILL BE REQUIRED WITH EACH
CORRESPONDING SECTION AT TIME OF RECORD PLAT SUBMITTAL.
5. SECTION 2 SHALL BE RECORDED PRIOR TO SECTION 5
NOTES
1. THE LANDSCAPE PLAN, DATED 7/29/2008, REVISED ON
12/10/2008, IS THE APPROVED LANDSCAPE PLAN FOR
IRONMILL, WITH THE EXCEPTIONS NOTED BELOW.
2. THE REVIEW OF THE LANDSCAPE PLAN DOES NOT CONSTITUTE
APPROVAL OR RE-APPROVAL OF THE BUFFER PLANTINGS. THE
BUFFER PLANTINGS WERE APPROVED UNDER THE ALTERNATIVE
TO THE CHAPTER 07TW0334.
3. THE REVIEW OF THE LANDSCAPE PLAN DOES NOT CONSTITUTE
APPROVAL OR RE-APPROVAL OF THE RECREATION AREA
PLANTINGS. THE RECREATION AREA PLANTINGS WERE APPROVED
UNDER THE SITE PLAN 08PR0275.
4. ANY LANDSCAPING PROPOSED WITHIN VDOT RIGHT-OF-WAY
MUST BE APPROVED BY VDOT. THE PLANNING DEPARTMENT
CANNOT APPROVE LANDSCAPING SHOWN IN THE ROUNDABOUT
OF IRON RIVER DRIVE.
5. THE ELEVATION PLANS (FOR IRON MILL, SECTIONS 1, 2 & 3,
RECEIVED JULY 7, 2009) AND OVERALL LAYOUT PLAN (FOR
SECTION 1 ONLY, RECEIVED JULY 9, 2009) ARE APPROVED.
STANDARD COMMENTS:
ANY BULK REQUIREMENTS (LOT AREA, LOT
WIDTH, SETBACKS, BUILDING ENVELOPES, ETC.) SHOWN ON THE
APPROVED CONSTRUCTION PLANS WILL BE SUBJECT TO REVIEW FOR
COMPLIANCE AT TIME OF FINAL CHECK.
BUFFER IS EXCLUSIVE OF EASEMENTS AND
SETBACKS. BUFFER MUST REMAIN IN A NATURAL STATE. BUFFER WIL
BE FIELD REVIEWED AT TIME OF FINAL CHECK. ANY CLEARING OR
REMOVAL OF VEGETATION FROM BUFFER WILL RESULT IN LANDSCAPE
PLAN SUBMITTAL AND BOND AT FINAL CHECK.
RETAINING WALL STANDARD NOTE: RETAINING WALLS ARE SUBJECT
TO REVIEW AT TIME OF TENTATIVE AND CONSTRUCTION PLAN
REVIEW. RETAINING WALLS SHALL BE RECORDED IN OPEN SPACE IF
THE WALL IS SEVEN (7') FEET OR GREATER IN HEIGHT AND SPANS
TWO OR MORE LOTS IN A SINGLE-FAMILY DEVELOPMENT OR IS
LOCATED IN A RESIDENTIAL TOWNHOUSE DEVELOPMENT.
-----------------------------------------------------------
PLANNING DEPARTMENT
CONSTRUCTION PLAN: IRON MILL, SECTION 5
CASE: 15CP0075
REVIEWED BY: WHIT KIRTLEY (706-7691)
SUBMITTAL: 2
REVIEW DATE: 6/4/15 (REVISED 6/15/15)
REVISION DATE: 5/12/15
PLANNING REVIEW #: 2
PLANNING STATUS: REVISIONS REQUIRED
CONDITIONS
1. AT TIME OF FINAL CHECK SUBMITTAL, SUBMIT A LANDSCAPE
PLAN FOR SECTION 2 SHOWING THE STREET TREE PLAN AND UNIT
PLANTING PLAN. FOR THE STREET TREE PLAN, SHOW TREE
PLACEMENT IN CONJUNCTION WITH PROPOSED DRIVEWAYS,
PER SEC. 19-518(H). STREET TREE BONDING WILL BE
REQUIRED WITH EACH CORRESPONDING SECTION PRIOR TO
RECORD PLAT SUBMITTAL.
2. THE LOT NUMBERS ON THE FINAL CHECK AND RECORD PLAT
SHALL DESIGNATE ANY DWELLING IN LAND BAY 3 THAT IS
LESSTHAN 1,700 SQUARE FEET.
3. ON THE FINAL PLAT, INDICATED WHICH LOTS ARE TO HAVE
SIDELOAD AND FRONT LOAD GARAGES
4. STREET TREE BONDING WILL BE REQUIRED WITH EACH
CORRESPONDING SECTION AT TIME OF RECORD PLAT SUBMITTAL.
5. SECTION 2 SHALL BE RECORDED PRIOR TO SECTION 5
NOTES
1. THE LANDSCAPE PLAN, DATED 7/29/2008, REVISED ON
12/10/2008, IS THE APPROVED LANDSCAPE PLAN FOR
IRONMILL, WITH THE EXCEPTIONS NOTED BELOW.
2. THE REVIEW OF THE LANDSCAPE PLAN DOES NOT CONSTITUTE
APPROVAL OR RE-APPROVAL OF THE BUFFER PLANTINGS. THE
BUFFER PLANTINGS WERE APPROVED UNDER THE ALTERNATIVE
TO THE CHAPTER 07TW0334.
3. THE REVIEW OF THE LANDSCAPE PLAN DOES NOT CONSTITUTE
APPROVAL OR RE-APPROVAL OF THE RECREATION AREA
PLANTINGS. THE RECREATION AREA PLANTINGS WERE APPROVED
REVIEW DEPARTMENT: FIRE AND LIFE SAFETY
REVIEWER / PHONE#: KIM LESTER / 748-1489
PLAN NAME: IRON MILL SEC. 5
PLAN NUMBER: 15CP0075
LATEST REVISION DATE: 1/9/15
REVIEW DATE: 3/4/15
LATEST SUBMISSION DATE: 2/23/15
SUBMITTAL NUMBER: 1ST REVIEW
STATUS: APPROVED
TABLE REVIEW:
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
REVIEW DEPARTMENT: FIRE AND LIFE SAFETY
REVIEWER / PHONE#: KIM LESTER / 748-1489
PLAN NAME: IRON MILL SEC. 5
PLAN NUMBER: 15CP0075
LATEST REVISION DATE: 5/12/15
REVIEW DATE: 5/27/15
LATEST SUBMISSION DATE: 5/20/15
SUBMITTAL NUMBER: 2ND REVIEW
STATUS: APPROVED
TABLE REVIEW: YES
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
============================================================
============================================================
REVIEW DEPARTMENT : ENVIRONMENTAL ENGINEERING
REVIEWER/PHONE # : JULIE HERZOG/796-7103
NAME OF PLAN : IRON MILL SECTION 5
SITE PLAN NO. : 15CP0075
LATEST PLAN DATE : 01/09/15
DEPT. REC'D DATE : 02/24/15
SUBMITTAL NUMBER : 1
REVIEW DATE : 03/13/15
RECOMMENDATION : REVISION REQUIRED
TABLE REVIEW : NO
-------- GENERAL NOTES --------
001. THE RESPONSIBILITY FOR COMPLIANCE WITH CHESTERFIELD
COUNTY STANDARDS AND POLICIES, AND WITH STATE AND
FEDERAL REGULATIONS WILL BE PLACED ON THE PROFESSIONAL
ENGINEER WHO SIGNS AND SEALS THE CONSTRUCTION PLANS
APPROVED.
002. THE RESPONSIBILITY FOR ACHIEVING AND MAINTAINING
SATISFACTORY LOT DRAINAGE WILL BE THAT OF THE DEVELOPER
UP THROUGH A PERIOD OF ONE YEAR AFTER STATE ACCEPTANCE
OF THE SUBDIVISION ROADS.
003. PLEASE ADD ITEMS 13-15 (LATITUDE AND LONGITUDE,
RECEIVING WATERS, VAHU6 FOUR DIGIT CODE) FROM THE
SUBDIVISION CHECKLIST TO SHEET 1.
004. SHEET C-7 HAS BEEN DUPLICATED AND ONE SHEET MAY BE
REMOVED.
005. PLEASE INCLUDE A POLLUTION PREVENTION PLAN SHEET.
006. SECTION 2 MUST BE APPROVED PRIOR TO SECTION 5 APPROVAL.
-------- EROSION CONTROL --------
001. PLEASE SUBMIT A REVISED ITEMIZED EROSION CONTROL BOND
COST ESTIMATE. TWO SEPARATE BOND ESTIMATES SHOULD BE
SUBMITTED, ONE FOR SECTION 2 AND ONE FOR SECTION 5.
002. PRIOR TO A LAND DISTURBANCE PERMIT ISSUANCE:
A) CONSTRUCTION PLANS MUST BE REAPPROVED.
B) AN EROSION CONTROL BOND MUST BE POSTED AND APPROVED.
C) IF APPLICABLE, A COPY OF THE VDOT LAND USE PERMIT
MUST BE RECEIVED.
D) FLAGGING AND/OR SAFETY FENCE AROUND USACOE
JURISDICTIONAL WETLANDS AND/OR OTHER ENVIRONMENTALLY
SENSITIVE AREAS MUST BE INSTALLED AND CLEARLY
VISIBLE.
E) PRIOR TO ISSUANCE OF A LAND DISTURBANCE PERMIT, A
COPY OF THE AUTOCAD FILE MUST BE SUBMITTED TO CAROLE
CLIBORNE OF ENVIRONMENTAL ENGINEERING. THE AUTOCAD
FILE MUST BE SAVED AS A .DWG OR .DXF IN AUTOCAD
VERSION 2009 OR EARLIER AND REFERENCED DIRECTLY TO
THE VIRGINIA STATE PLANE COORDINATE SYSTEM, SOUTH
ZONE IN THE NAD83 DATUM. THE AUTOCAD FILE MAY BE
SUBMITTED ON A CD, DVD, OR VIA EMAIL AND MUST BE
CLEARLY LABELED WITH THE SUBDIVISION NAME AND
SECTION, SUBDIVISION PLAN NUMBER, THE ENGINEERING
FIRM AND THE CAD FILE PREPARER'S NAME AND PHONE
NUMBER. THE FILE MUST CONTAIN THE FOLLOWING, EACH
CLEARLY LABELED IN SEPARATE LAYERS:
1. EDGES OF ROADS TO INCLUDE CURB AND GUTTER; AND
2. EDGES OF SIDEWALKS.
THE FILE MUST BE APPROVED BY ENVIRONMENTAL
ENGINEERING PRIOR TO ISSUANCE OF THE LAND
DISTURBANCE PERMIT.
003. AS PREVIOUSLY REQUESTED, PLEASE CORRECT THE FOLLOWING
ITEMS IN THE EROSION CONTROL NARRATIVE ON SHEETS C-6
AND C-7.
A) THE MS-19 CROSS SECTION AND TABLE LOCATION THE
THIRD BULLET OF THE STORMWATER RUNOFF
CONSIDERATIONS AND THE LAST BULLET OF THE EXISTING
CONDITIONS.
B) THE NUMBER OF SEDIMENT TRAPS IN THE SECOND BULLET
AND SHEET NUMBERS IN THE LAST SENTENCE OF THE
EROSION AND SEDIMENT CONTROL MEASURES.
004. PLEASE PROVIDE SOME NOTATION REGARDING WHICH SECTION
EACH MS-19 DISCHARGE POINT IS AFFILIATED WITH ON SHEET
1.
005. PLEASE PROVIDE A SOIL STOCKPILE AREA AND UPDATE
CONSTRUCTION NARRATIVE AS APPLICABLE.
006. PLEASE ADD INFORMATION REGARDING THE CONSTRUCTION
ENTRANCE FOR SECTION 5 UNDER THE ADJACENT AREAS TITLE
ON SHEETS C-6/C-7.
007. ADD SOME VARIATION OF THE PHRASE "COMMENCE CLEARING AND
GRUBBING OPERATIONS" AS STEP 2 UNDER THE IRON MILL
SECTION 5 CONSTRUCTION NARRATIVE ON SHEET C-6.
008. STEP 3 UNDER THE IRON MILL SECTION 5 CONSTRUCTION
NARRATIVE ON SHEET C-6 SHOULD INCLUDE THE INSTALLATION
OF SEDIMENT TRAP #2.
009. REMOVE THE NOTE STATING "SEDIMENT TRAP #2 IS AN
EXISTING SEDIMENT TRAP…" FROM STEP 3 OF THE IRON MILL
SECTION 5 CONSTRUCTION NARRATIVE ON SHEET C-6.
010. STEP 4 OF THE IRON MILL SECTION 5 CONSTRUCTION
NARRATIVE ON SHEET C-6 MAY BE REMOVED.
011. ADD SOME VARIATION OF THE PHRASE "CONTINUE CLEARING AND
GRUBBING OPERATIONS" AS STEP 2 UNDER THE IRON MILL
SECTION 5 CONSTRUCTION NARRATIVE ON SHEET C-7.
012. THE EXTRANEOUS STEP 12 MAY BE REMOVED FROM THE IRON
MILL SECTION 5 CONSTRUCTION NARRATIVE ON SHEET C-7.
013. IT IS THE RESPONSIBILITY OF THE APPLICANT TO COMPLY
WITH AND/OR ACQUIRE ALL APPLICABLE FEDERAL AND/OR STATE
PERMITS IN RELATION TO ENVIRONMENTAL FEATURES
INCLUDING, BUT NOT LIMITED TO, WETLANDS, SURFACE WATER,
GROUND WATER, AND AIR QUALITY. FINAL APPROVAL OF THESE
PLANS WILL NOT RELIEVE YOU OF YOUR RESPONSIBILITIES.
-------- CBPA --------
001. AS PREVIOUSLY REQUESTED, PLEASE INCLUDE AN MS-4 TABLE
THAT DETERMINES THE REQUIRED REMOVAL ON THE CBPA PLAN
SHEET (SHEET 12).
-------- ROAD AND DRAINAGE --------
001. THE LABEL AT SECTION 5 LOTS 3/4 SHOULD SPECIFY A
TEMPORARY TURNAROUND EASEMENT RATHER THAN AN ACCESS
EASEMENT. PLEASE CORRECT ON SHEET 3.
002. IN ORDER TO MEET 10-PRE/10-POST REQUIREMENTS,
STRUCTURES 10B AND 7B SHOULD OUTFALL INTO THE 100 YEAR
FLOODPLAIN. A SOLUTION IS THE BRING UP THE LIMITS OF
THE EXISTING 100 YEAR FLOODPLAIN TO MEET FLUSH AGAINST
THESE STRUCTURES. PLEASE REVISE ON SHEET C-3A AND
PROFILES AS NECESSARY. FURTHER DISCUSSION MAY BE
HELPFUL.
003. PLEASE PROVIDE ROOF DRAINS AND SPECIFY CLEANOUTS IN
PLAN VIEW ON THE GRADING PLAN.
004. PLEASE EXTEND THE RIPRAP AT STRUCTURE 10B TO MEET FLUSH
WITH THE USACOE WETLANDS ON THE BERKLEY MILL DRIVE
PROFILE ON SHEET C-9.
005. PLEASE ADD SECTION DESIGNATION BELOW THE TITLE FOR ALL
PROFILES ON SHEET 9B.
006. PLEASE REPLACE THE RPA RESTORATION DETAIL ON SHEET C-
10A WITH THE MOST RECENT RPA ESTABLISH PLAN DATED 12/14
(SEE ATTACHED).
007. IN LIEU OF THE STEEP RIPRAP OUTFALL AT STRUCTURE 6B,
SPECIFY A DEEPER CURB INLET AND PIPE THE FLOW TO
APPROXIMATE ELEVATION 138 ENDING WITH ENHANCES OUTLET
PROTECTION. FURTHER DISCUSSION MAY BE HELPFUL.
008. PLEASE ADD A NOTE TO SHEET C-4A SPECIFYING THAT MANHOLE
STEPS ARE REQUIRED IN STRUCTURES 4 FEET AND GREATER IN
DEPTH.
009. PLEASE PROVIDE A WRITTEN RESPONSE IN THE MARGIN OF A
COPY OF THESE REVIEW COMMENTS WITH YOUR NEXT PLAN
SUBMITTAL. DESIGN, DETAIL AND CALCULATIONS REQUIRED BY
THE ABOVE COMMENTS SHALL BE SUBJECT TO FURTHER REVIEW.
---- END OF ENV. ENG. COMMENTS ----
============================================================
============================================================
REVIEW DEPARTMENT : ENVIRONMENTAL ENGINEERING
REVIEWER/PHONE # : JULIE PRANGER (HERZOG)/796-7103
NAME OF PLAN : IRON MILL SECTION 5
SITE PLAN NO. : 15CP0075
LATEST PLAN DATE : 05/12/15
DEPT. REC'D DATE : 05/19/15
SUBMITTAL NUMBER : 2
REVIEW DATE : 06/08/15
RECOMMENDATION : APPROVED
TABLE REVIEW : YES
-------- GENERAL NOTES --------
001. THE RESPONSIBILITY FOR COMPLIANCE WITH CHESTERFIELD
COUNTY STANDARDS AND POLICIES, AND WITH STATE AND
FEDERAL REGULATIONS WILL BE PLACED ON THE PROFESSIONAL
ENGINEER WHO SIGNS AND SEALS THE CONSTRUCTION PLANS
APPROVED.
002. THE RESPONSIBILITY FOR ACHIEVING AND MAINTAINING
SATISFACTORY LOT DRAINAGE WILL BE THAT OF THE DEVELOPER
UP THROUGH A PERIOD OF ONE YEAR AFTER STATE ACCEPTANCE
OF THE SUBDIVISION ROADS.
003. PRIOR TO A LAND DISTURBANCE PERMIT ISSUANCE:
A) CONSTRUCTION PLANS MUST BE APPROVED.
B) THE LDP FOR SECTION 2 MUST BE ISSUED.
C) AN EROSION CONTROL BOND MUST BE POSTED IN THE AMOUNT
OF $43,271.00.
D) FLAGGING AND/OR SAFETY FENCE AROUND USACOE
JURISDICTIONAL WETLANDS AND/OR OTHER ENVIRONMENTALLY
SENSITIVE AREAS MUST BE INSTALLED AND CLEARLY
VISIBLE.
E) PRIOR TO ISSUANCE OF A LAND DISTURBANCE PERMIT, A
COPY OF THE AUTOCAD FILE MUST BE SUBMITTED TO CAROLE
CLIBORNE OF ENVIRONMENTAL ENGINEERING. THE AUTOCAD
FILE MUST BE SAVED AS A .DWG OR .DXF IN AUTOCAD
VERSION 2009 OR EARLIER AND REFERENCED DIRECTLY TO
THE VIRGINIA STATE PLANE COORDINATE SYSTEM, SOUTH
ZONE IN THE NAD83 DATUM. THE AUTOCAD FILE MAY BE
SUBMITTED ON A CD, DVD, OR VIA EMAIL AND MUST BE
CLEARLY LABELED WITH THE SUBDIVISION NAME AND
SECTION, SUBDIVISION PLAN NUMBER, THE ENGINEERING
FIRM AND THE CAD FILE PREPARER'S NAME AND PHONE
NUMBER. THE FILE MUST CONTAIN THE FOLLOWING, EACH
CLEARLY LABELED IN SEPARATE LAYERS:
1. EDGES OF ROADS TO INCLUDE CURB AND GUTTER; AND
2. EDGES OF SIDEWALKS.
THE FILE MUST BE APPROVED BY ENVIRONMENTAL
ENGINEERING PRIOR TO ISSUANCE OF THE LAND
DISTURBANCE PERMIT.
004. AS A PREREQUISITE TO SUBDIVISION PLAT RECORDATION:
A) A $100 PER LOT MAINTENANCE FEE MUST BE RECEIVED.
005. IT IS THE RESPONSIBILITY OF THE APPLICANT TO COMPLY
WITH AND/OR ACQUIRE ALL APPLICABLE FEDERAL AND/OR STATE
PERMITS IN RELATION TO ENVIRONMENTAL FEATURES
INCLUDING, BUT NOT LIMITED TO, WETLANDS, SURFACE WATER,
GROUND WATER, AND AIR QUALITY. FINAL APPROVAL OF THESE
PLANS WILL NOT RELIEVE YOU OF YOUR RESPONSIBILITIES.
---- END OF ENV. ENG. COMMENTS ----
============================================================
============================================================

Go to Case Selection Form or Go to Project List