All Subdivision Review Comments for Case # 11PA0232




For VDOT’s comments please contact Virginia Department of Transportation at (804) 674-2814 or send e-mail to Boris.Solomonov@VDOT.Virginia.gov

For Tentative Subdivision resubmittals:

1. Please note that submittal fees include the original submittal and two (2) additional reviews.

2. A letter of transmittal is required to accompany each submittal.

3. Please verify that Environmental Engineering, Fire, CDOT, VDOT, and Planning have reviewed the submittal before resubmitting. A resubmittal tendered, prior to receiving all the required departments’ review, will be counted as an additional submittal. Go to Case Selection Form or Go to Project List


 
CASE NO: 11PA0232 STATUS: PENDING APPROVAL
PROJECT NAME: 3HD HOLDING COMPANY - LAST INTERNET UPDATE: 11/22/17
SUBMITTAL TYPE: PARCEL ACREAGE
DEPARTMENT...REV..ROUTED..RESPONSE..STATUS....DATE...RVW..PHONE
HEALTH DEPT.: 00 06/06/11 06/27/11 ******** ********
PLANNING----: 00 06/06/11 06/27/11 COMPLETE 06/09/11 RPR 768-7592
REVIEW DEPARTMENT : PLANNING
REVIEWER / PHONE # : RYAN RAMSEY / 768-7592
PLAN NAME : 8500 SALEM CHURCH ROAD
PLAN NUMBER : 11PA0232
ORIGINAL PLAN DATE : 5/31/2011
REVIEW DATE : 6/9/2011
LATEST SUBMISSION DATE : 6/2/2011
SUBMITTAL NUMBER : 1
STATUS : REVISIONS REQUIRED
REVISIONS REQUIRED:
1) SEVERAL OUTSTANDING ISSUES ARE PRESENT WITH CURRENT
PARCEL LINE MODIFICATION APPLICATION. THE PROPERTY IS
CURRENTLY ZONED R-12. THE UNDERLYING ZONING CASE,
05SN0295, HAS SEVERAL CONDITIONS OF ZONING THAT ARE
APPLICABLE AT TIME OF THE INITIAL SUBDIVISION RECORDATION.
THESE ITEMS INCLUDE 1) RIGHT-OF-WAY DEDICATION ALONG
SALEM CHURCH ROAD & KINGSLAND ROAD 2) RECORDATION OF
RESTRICTIVE COVENANTS AND 3) RECORDATION OF DEED
RESTRICTIONS (CONDITIONS 7, 12 AND 16). PRIOR TO THE
RECORDATION OF THE PARCEL LINE MODIFICATION, THESE ITEMS
WOULD NEED TO BE ADDRESSED ACCORDINGLY.
STAFF ALSO HAS CONCERN ABOUT THE ULTIMATE CREATION OF THE
BUFFER AND OPEN SPACE THAT IS SHOWN ON THE APPROVED
TENTATIVE PLAT FOR THE SUBJECT PROPERTY. THE CORRECT
PROCESS TO RECORD THE FIRST LOT IN THE SUBDIVISION IS TO
GENERATE A ONE-LOT SUBDIVISION PLAT AND PHASED
CONSTRUCTION PLAN OF REEDY SPRINGS, SECTION A. PLEASE
NOTE THAT THE FIRST LOT WILL REQUIRE A MINIMUM OF 50' OF
STATE MAINTAINED ROAD FRONTAGE.
THE POSSIBLE SALE OF THIS PROPOSED PARCEL (PARCEL B) ALSO
POSES AN UNCERTAINTY IN ENSURING THAT THIS PROPERTY IS
INCLUDED IN THE FIRST SECTION OF THE SUBDIVISION. IF THE
PROPERTY IS CONVEYED TO A THIRD PARTY OUTSIDE OF THE
DEVELOPER'S CONTROL, THE DEVELOPER COULD LOSE THE ABILITY
TO INCLUDE THIS PROPERTY WITHIN THE BOUNDARIES OF REEDY
SPRINGS, SECTION A WHEN IT IS READY TO RECORD.
CONSEQUENTLY, IT MAY PROVE DIFFICULT TO INCORPORATE THIS
PROPERTY THROUGH A LOT SUBDIVISION PROCESS AND HAVE
"PARCEL B" MEET ALL OF THE UNDERLYING ZONING CONDITIONS.
2) IF A RESUBMITTAL OF THIS PLAT IS SUBMITTED, PROVIDE STAFF
WITH A NARRATIVE THAT DESCRIBES HOW ALL OF THE ITEMS IN THE
FIRST COMMENT ARE ADDRESSED ABOVE.
**END OF COMMENTS**
============================================================