Thanksgiving Holiday Closings... MORE

Hover here for Site Tools
Subdivision Review Comments
All Subdivision Review Comments for Case # 04TS0279




For VDOT’s comments please contact Virginia Department of Transportation at (804) 674-2814 or send e-mail to Boris.Solomonov@VDOT.Virginia.gov

For Tentative Subdivision resubmittals:

1. Please note that submittal fees include the original submittal and two (2) additional reviews.

2. A letter of transmittal is required to accompany each submittal.

3. Please verify that Environmental Engineering, Fire, CDOT, VDOT, and Planning have reviewed the submittal before resubmitting. A resubmittal tendered, prior to receiving all the required departments’ review, will be counted as an additional submittal. Go to Case Selection Form or Go to Project List


 
CASE NO: 04TS0279 STATUS: PENDING APPROVAL
PROJECT NAME: CHARTER COLONY ADDIT - LAST INTERNET UPDATE: 11/22/17
SUBMITTAL TYPE: TENTATIVE SUBDIVISION
DEPARTMENT...REV..ROUTED..RESPONSE..STATUS....DATE...RVW..PHONE
ENVIR.ENGR.-: 00 02/12/04 03/04/04 ******** ********
FIRE DEPT.--: 00 02/12/04 03/04/04 ******** ********
HOUSE NUMBER: 00 02/12/04 03/04/04 ******** ********
MAPPING/GIS-: 00 02/12/04 03/04/04 ******** ********
PLANNING----: 00 02/12/04 03/04/04 COMPLETE 03/17/04 DAH 748-1967
PARKS & REC.: 00 02/12/04 03/05/04 ******** ********
SCHOOL BOARD: 00 02/12/04 03/04/04 ******** ********
SOILS-------: 00 02/12/04 03/04/04 ******** ********
TRANSPORT.--: 00 02/12/04 03/04/04 ******** ********
UTIL.PLAN.--: 00 02/12/04 03/04/04 AMENDED* 03/15/04 TVM 751-4435
UTILITIES---: 00 02/12/04 03/04/04 ******** ********
VDOT--------: 00 02/12/04 03/04/04 ******** ********
UTILITIES DEPT. COMMENTS FOR CHARTER COLONY ADDITION:
1.THE USE OF THE PUBLIC WATER AND WASTEWATER SYSTEMS IS
REQUIRED BY ORDINANCE.
2.IT WILL BE THE RESPONSIBILITY OF THE SUBDIVIDER TO
MAKE CERTAIN THAT ALL PROPOSED SECTIONS WITHIN THE
DEVELOPMENT COMPLIES WITH THE CHESTERFIELD COUNTY FIRE
DEPARTMENT'S REQUIRED FIRE FLOW OF 1000GPM AT 20PSI
RESIDUAL.
3.APPROVAL OF THE TENTATIVE SUBDIVISION IS NOT AN
APPROVAL OF THE WATER AND/OR SEWER LAYOUT AS SHOWN ON
THE SUBDIVIDER'S TENTATIVE SUBDIVISION PLAT. THE
REVIEW OF THE TENTATIVE WATER/SEWER LAYOUT IS BEING
PERFORMED TO IDENTIFY ANY POTENTIAL CONTROVERSIAL
PROBLEMS AND TO INTEGRATE THE DEPARTMENT OF UTILITIES'
RECOMMENDATIONS AS SET FORTH IN THE LATEST WATER/SEWER
FACILITIES PLAN IN AN EFFORT TO FACILITATE A MUCH
SMOOTHER REVIEW OF THE FINAL DESIGN OF EACH SECTION.
THE SUBDIVIDER UNDERSTANDS THAT AS THE FINAL
DETAILS OF EACH DEVELOPMENT SECTION ARE REVIEWED, THE
UTILITIES DEPARTMENT MAY REQUIRE CHANGES TO THE
ORIGINAL LAYOUT AS DEEMED IN THE BEST INTEREST OF THE
COUNTY, WHICH ULTIMATELY BENEFITS THE DEPARTMENT'S
CUSTOMERS AS USERS OF PUBLIC WATER/SEWER SYSTEMS.
4.A WATER LINE CONNECTION ALONG BROOK COLONY LANE
SHALL BE MADE TO THE EXISTING 24-INCH WATER LINE.
PLANNING
1. AS PREVIOUSLY DISCUSSED, THE TENTATIVE PLAT CAN NOT BE AP
PROVED UNTIL THE PLANNING COMMISSION APPROVES THE REVISED SC
HEMATIC PLAN FOR THE CENTREPOINTE ZONING CASE. AS SUCH ALL
COMMENTS AND NOTES ARE SUBJECT TO REVISION BASED UPON IMPACT
S OF THAT CASE.
2. COMPLIANCE WITH SECTION 17-76 SHALL BE MAINTAINED AT ALL
TIMES.
3. STANDARD CONDITIONS
4. COALFIELD ROAD SHALL HAVE A THIRTY-FIVE (35) FOOT BUFFER
COMPLYING WITH SECTION 17-70.
5. ALL PORTIONS OF DEDICATED ROADWAY TO BE ABANDONDED AND
VAVATED, SHALL BE VACATED PRIOR TO TENTATIVE APPROVAL.
6. THE SUBDIVIDER SHALL CONSTRUCT A PAVED WALKWAY MATCHING T
HE EXISTING SECTION ALONG LUCKS LAND AND DEDICATE AN EASEMEN
T TO THE COUNTY FOR THE WALKWAY.
7. PLEASE PLACE APPROPRIATE PROFFER CONDITIONS GOVERNING TH
IS AREA ON PLANS.
8. PROVIDE REQUIRED POWER OF ATTORNEY FORM FROM OWNER
9. PLEASE NOTE THAT BUFFERS ARE EXCLUSIVE OF EASEMENTS AND
SETBACKS. PLEASE REVISE ACCORDINGLY.
10. A NOTE WILL BE REQUIRED ON THE FINAL CHECK AND RECORD P
LAT FOR ALL LOTS WITH SOUND SETBACKS NOTING THAT NO VEGETATI
ON CAN BE REMOVED WITHOUT PLANNING COMMISSION APPROVAL.
11. PLEASE SHOW THE PROPERTY OWNERS NAMES AND GPINS FOR PAR
CELS FRONTING COALFIELD ROAD.
12. PLEASE NOTE THAT THE SOUND SETBACK IS EXCLUSIVE OF YARD
SETBACKS AND THE BUILDING ENVELOPES DEPICTED ON THE PLAT SHO
ULD BE ADJUSTED ACCORDINGLY.
13. CLARIFY PROPOSED ROADS WILL HAVE CURB AND GUTTER. DOES T
HIS INVOLVED RELOCATED/RECONSTRUCTED.