Magnolia Green CDA, Woolridge Road and Otterdale Road Improvements
Transportation

Transportation Projects
Magnolia Green CDA, Woolridge Road and Otterdale Road Improvements
Project Details

Woolridge Road will be widened from two lanes to four lanes from the Swift Creek Reservoir to Otterdale Road. Otterdale Road will also be widened from two lanes to four lanes from Woolridge Road to just north of FoxCreek Crossing. A raised median will be provided to separate the lanes throughout the project. New traffic signals are proposed at the intersection of Woolridge Road and Timber Bluff Parkway, Woolridge Road and Fox Club Road and Woolridge Road and Otterdale Road.

Woolridge Road Traffic Simulation

Project Timeline Notes - Task Statuses

  • Engineering/design - VDOT approved the design plans on November 16, 2016.
  • Right-of-way and easement acquisition - Right-of-way and easement acquisition is complete.
  • Utility relocation - Utility relocations are underway and are expected to be complete by spring of 2018.
  • Construction - Bids for construction of the project were received on January 16, 2018.

Traffic Impacts
Woolridge and Otterdale Roads will remain open to traffic at all times. Some daytime alternating lane closures will be necessary during construction.

Project Timeline: Spring 2018 to Fall 2019

Contact
Brent Epps
804-748-1037



Go back to Transportation Projects list

Upcoming Events

No Events
 
Important Information
View Capital Improvement Projects App 

/uploadedImages/Department_Information/Community_Development/Transportation/Images/thoroughfare-plan(1).png 
Thoroughfare Plan
 


Chesterfield GRTC Express Route
 

 
Resources

Virginia Department of Transportation
Click to Report a Road Problem
511 Traffic InformationVirginia Department of Motor Vehicles
GRTC Transit SystemRidefinders
School's TransportationAccess Chesterfield 

 
Related Links